  • CAP Section 205, Eaton Rapids, MI, decision document review plan

    This Review Plan is a supplement to the Project Management Plan (PMP), dated July 2014, for the CAP Section 205 Eaton Rapids, Michigan, Flood Risk Management project and fulfills the requirement of Engineer Circular (EC) 1165-2-214, “Civil Works Review.” This Review Plan defines the scope and level of peer review for the feasibility report (integrated Detailed Project Report (DPR) and Environmental Assessment (EA)) developed under Section 205, Flood Control Act of 1948, as amended. This project is a single purpose, Flood Risk Management (FRM) project.

Consolidation of Studies

The Water Resources Development Act establishes a single-phase cost-shared study process that for each feasibility study undertaken, the district engineer will develop a detailed study schedule and notify the non-federal interests.

Overviews of study schedule milestones are posted below.