SAULT STE. MARIE, Mich. – The U.S. Army Corps of Engineers New Lock at the Soo project remains on schedule as major construction continues with phases 2 and 3 this season.
Joint ventures Kokosing-Alberici (Upstream Approach Walls, Phase 2), and Kokosing, Alberici, Traylor (New Lock, Phase 3) have a busy construction season ahead of them.
“Since resuming major construction this season, the Phase 2 contractor has placed 13 concrete caps, bringing the total caps placed to 68 and preparation for placement of new steel sheets, steel posts and concrete panel wall are in progress,” New Lock Senior Project Manager Mollie Mahoney said. “The Phase 3 contractor plans to focus on demolition of aging structures, extensive electrical work, bridge construction, and coffer dam construction to allow for dewatering.”