Scoop and restore: Pittsburgh District dredges Monongahela River to support navigation industry

Pittsburgh District
Published March 28, 2025
The dredging contract consists of two dredging crews that have been working six days a week since September. The crews have removed more than 314 barges of material so far, equivalent to 166,000 tons of soil, rocks and debris from the river bottom.

Art Innamorato, a construction manager for a U.S. Army Corps of Engineers Pittsburgh District contractor, climbs onto a boat during a dredging operation on the Monongahela River south of Pittsburgh, March 20, 2025. The dredging contract consists of two dredging crews that have been working six days a week since September. The crews have removed more than 314 barges of material so far, equivalent to 166,000 tons of soil, rocks and debris from the river bottom. The contract aims to restore up to ten feet of depth along the Monongahela River in specific shallow areas to allow navigation industries to transport bulk commodities through the region. The dredging work is necessary because the pool level dropped approximately two feet after the Pittsburgh District removed the navigation dam near Elizabeth, Pennsylvania in 2024. The current pool elevation is approximately 724 feet above sea level between the towns of Charleroi and Braddock, Pennsylvania. Elevation figures are based on the North American Vertical Datum of 1988. Eventually, the Pittsburgh District will drop the revel another foot in the pool being dredged. The district has not yet determined a timeline for the final elevation drop. The district is actively assessing the navigation channel and the impact the pool change has on shoreside facilities, navigation industries and other stakeholders. Once the district has completed the necessary dredging and completed its assessments, it will determine when to drop the river level to its final authorized elevation. The final pool elevations will be 723.1 feet. (U.S. Army Corps of Engineers Pittsburgh District photo by Michel Sauret)

The dredging contract consists of two dredging crews that have been working six days a week since September. The crews have removed more than 314 barges of material so far, equivalent to 166,000 tons of soil, rocks and debris from the river bottom.

Art Innamorato, a construction manager for a U.S. Army Corps of Engineers Pittsburgh District contractor, points to a screen showing a live view of an excavator dredging material from the Monongahela River south of Pittsburgh, March 20, 2025. The dredging contract consists of two dredging crews that have been working six days a week since September. The crews have removed more than 314 barges of material so far, equivalent to 166,000 tons of soil, rocks and debris from the river bottom. The contract aims to restore up to ten feet of depth along the Monongahela River in specific shallow areas to allow navigation industries to transport bulk commodities through the region. The dredging work is necessary because the pool level dropped approximately two feet after the Pittsburgh District removed the navigation dam near Elizabeth, Pennsylvania in 2024. The current pool elevation is approximately 724 feet above sea level between the towns of Charleroi and Braddock, Pennsylvania. Elevation figures are based on the North American Vertical Datum of 1988. Eventually, the Pittsburgh District will drop the revel another foot in the pool being dredged. The district has not yet determined a timeline for the final elevation drop. The district is actively assessing the navigation channel and the impact the pool change has on shoreside facilities, navigation industries and other stakeholders. Once the district has completed the necessary dredging and completed its assessments, it will determine when to drop the river level to its final authorized elevation. The final pool elevations will be 723.1 feet. (U.S. Army Corps of Engineers Pittsburgh District photo by Michel Sauret)

The dredging contract consists of two dredging crews that have been working six days a week since September. The crews have removed more than 314 barges of material so far, equivalent to 166,000 tons of soil, rocks and debris from the river bottom.

An excavator for a U.S. Army Corps of Engineers Pittsburgh District contractor scoops up dredge material removed from the Monongahela River from a barge onto a dump truck that will transport it to a disposal site south of Pittsburgh, March 20, 2025. The dredging contract consists of two dredging crews that have been working six days a week since September. The crews have removed more than 314 barges of material so far, equivalent to 166,000 tons of soil, rocks and debris from the river bottom. The contract aims to restore up to ten feet of depth along the Monongahela River in specific shallow areas to allow navigation industries to transport bulk commodities through the region. The dredging work is necessary because the pool level dropped approximately two feet after the Pittsburgh District removed the navigation dam near Elizabeth, Pennsylvania in 2024. The current pool elevation is approximately 724 feet above sea level between the towns of Charleroi and Braddock, Pennsylvania. Elevation figures are based on the North American Vertical Datum of 1988. Eventually, the Pittsburgh District will drop the revel another foot in the pool being dredged. The district has not yet determined a timeline for the final elevation drop. The district is actively assessing the navigation channel and the impact the pool change has on shoreside facilities, navigation industries and other stakeholders. Once the district has completed the necessary dredging and completed its assessments, it will determine when to drop the river level to its final authorized elevation. The final pool elevations will be 723.1 feet. (U.S. Army Corps of Engineers Pittsburgh District photo by Michel Sauret)

The dredging contract consists of two dredging crews that have been working six days a week since September. The crews have removed more than 314 barges of material so far, equivalent to 166,000 tons of soil, rocks and debris from the river bottom.

A U.S. Army Corps of Engineers Pittsburgh District contractor dredges soil, rocks and other materials from the Monongahela River south of Pittsburgh, March 20, 2025. The dredging contract consists of two dredging crews that have been working six days a week since September. The crews have removed more than 314 barges of material so far, equivalent to 166,000 tons of soil, rocks and debris from the river bottom. The contract aims to restore up to ten feet of depth along the Monongahela River in specific shallow areas to allow navigation industries to transport bulk commodities through the region. The dredging work is necessary because the pool level dropped approximately two feet after the Pittsburgh District removed the navigation dam near Elizabeth, Pennsylvania in 2024. The current pool elevation is approximately 724 feet above sea level between the towns of Charleroi and Braddock, Pennsylvania. Elevation figures are based on the North American Vertical Datum of 1988. Eventually, the Pittsburgh District will drop the revel another foot in the pool being dredged. The district has not yet determined a timeline for the final elevation drop. The district is actively assessing the navigation channel and the impact the pool change has on shoreside facilities, navigation industries and other stakeholders. Once the district has completed the necessary dredging and completed its assessments, it will determine when to drop the river level to its final authorized elevation. The final pool elevations will be 723.1 feet. (U.S. Army Corps of Engineers Pittsburgh District photo by Michel Sauret)

The dredging contract consists of two dredging crews that have been working six days a week since September. The crews have removed more than 314 barges of material so far, equivalent to 166,000 tons of soil, rocks and debris from the river bottom.

Art Innamorato, a construction manager for a U.S. Army Corps of Engineers Pittsburgh District contractor, drives a boat past a dredging barge on the Monongahela River south of Pittsburgh, March 20, 2025. The dredging contract consists of two dredging crews that have been working six days a week since September. The crews have removed more than 314 barges of material so far, equivalent to 166,000 tons of soil, rocks and debris from the river bottom. The contract aims to restore up to ten feet of depth along the Monongahela River in specific shallow areas to allow navigation industries to transport bulk commodities through the region. The dredging work is necessary because the pool level dropped approximately two feet after the Pittsburgh District removed the navigation dam near Elizabeth, Pennsylvania in 2024. The current pool elevation is approximately 724 feet above sea level between the towns of Charleroi and Braddock, Pennsylvania. Elevation figures are based on the North American Vertical Datum of 1988. Eventually, the Pittsburgh District will drop the revel another foot in the pool being dredged. The district has not yet determined a timeline for the final elevation drop. The district is actively assessing the navigation channel and the impact the pool change has on shoreside facilities, navigation industries and other stakeholders. Once the district has completed the necessary dredging and completed its assessments, it will determine when to drop the river level to its final authorized elevation. The final pool elevations will be 723.1 feet. (U.S. Army Corps of Engineers Pittsburgh District photo by Michel Sauret)

The dredging contract consists of two dredging crews that have been working six days a week since September. The crews have removed more than 314 barges of material so far, equivalent to 166,000 tons of soil, rocks and debris from the river bottom.

A deckhand passes a gas can to Art Innamorato, a construction manager for a U.S. Army Corps of Engineers Pittsburgh District contractor, during a dredging operation on the Monongahela River south of Pittsburgh, March 20, 2025. The dredging contract consists of two dredging crews that have been working six days a week since September. The crews have removed more than 314 barges of material so far, equivalent to 166,000 tons of soil, rocks and debris from the river bottom. The contract aims to restore up to ten feet of depth along the Monongahela River in specific shallow areas to allow navigation industries to transport bulk commodities through the region. The dredging work is necessary because the pool level dropped approximately two feet after the Pittsburgh District removed the navigation dam near Elizabeth, Pennsylvania in 2024. The current pool elevation is approximately 724 feet above sea level between the towns of Charleroi and Braddock, Pennsylvania. Elevation figures are based on the North American Vertical Datum of 1988. Eventually, the Pittsburgh District will drop the revel another foot in the pool being dredged. The district has not yet determined a timeline for the final elevation drop. The district is actively assessing the navigation channel and the impact the pool change has on shoreside facilities, navigation industries and other stakeholders. Once the district has completed the necessary dredging and completed its assessments, it will determine when to drop the river level to its final authorized elevation. The final pool elevations will be 723.1 feet. (U.S. Army Corps of Engineers Pittsburgh District photo by Michel Sauret)

The dredging contract consists of two dredging crews that have been working six days a week since September. The crews have removed more than 314 barges of material so far, equivalent to 166,000 tons of soil, rocks and debris from the river bottom.

A U.S. Army Corps of Engineers Pittsburgh District contractor dredges soil, rocks and other materials from the Monongahela River south of Pittsburgh, March 20, 2025. The dredging contract consists of two dredging crews that have been working six days a week since September. The crews have removed more than 314 barges of material so far, equivalent to 166,000 tons of soil, rocks and debris from the river bottom. The contract aims to restore up to ten feet of depth along the Monongahela River in specific shallow areas to allow navigation industries to transport bulk commodities through the region. The dredging work is necessary because the pool level dropped approximately two feet after the Pittsburgh District removed the navigation dam near Elizabeth, Pennsylvania in 2024. The current pool elevation is approximately 724 feet above sea level between the towns of Charleroi and Braddock, Pennsylvania. Elevation figures are based on the North American Vertical Datum of 1988. Eventually, the Pittsburgh District will drop the revel another foot in the pool being dredged. The district has not yet determined a timeline for the final elevation drop. The district is actively assessing the navigation channel and the impact the pool change has on shoreside facilities, navigation industries and other stakeholders. Once the district has completed the necessary dredging and completed its assessments, it will determine when to drop the river level to its final authorized elevation. The final pool elevations will be 723.1 feet. (U.S. Army Corps of Engineers Pittsburgh District photo by Michel Sauret)

The dredging contract consists of two dredging crews that have been working six days a week since September. The crews have removed more than 314 barges of material so far, equivalent to 166,000 tons of soil, rocks and debris from the river bottom.

The dredging contract consists of two dredging crews that have been working six days a week since September. The crews have removed more than 314 barges of material so far, equivalent to 166,000 tons of soil, rocks and debris from the river bottom. The contract aims to restore up to ten feet of depth along the Monongahela River in specific shallow areas to allow navigation industries to transport bulk commodities through the region. The dredging work is necessary because the pool level dropped approximately two feet after the Pittsburgh District removed the navigation dam near Elizabeth, Pennsylvania in 2024. The current pool elevation is approximately 724 feet above sea level between the towns of Charleroi and Braddock, Pennsylvania. Elevation figures are based on the North American Vertical Datum of 1988. Eventually, the Pittsburgh District will drop the revel another foot in the pool being dredged. The district has not yet determined a timeline for the final elevation drop. The district is actively assessing the navigation channel and the impact the pool change has on shoreside facilities, navigation industries and other stakeholders. Once the district has completed the necessary dredging and completed its assessments, it will determine when to drop the river level to its final authorized elevation. The final pool elevations will be 723.1 feet. (U.S. Army Corps of Engineers Pittsburgh District photo by Michel Sauret)

The dredging contract consists of two dredging crews that have been working six days a week since September. The crews have removed more than 314 barges of material so far, equivalent to 166,000 tons of soil, rocks and debris from the river bottom.

Radar screens help a U.S. Army Corps of Engineers Pittsburgh District contractor vessel navigate the Monongahela River while dredging material from the river bottom south of Pittsburgh, March 20, 2025. The dredging contract consists of two dredging crews that have been working six days a week since September. The crews have removed more than 314 barges of material so far, equivalent to 166,000 tons of soil, rocks and debris from the river bottom. The contract aims to restore up to ten feet of depth along the Monongahela River in specific shallow areas to allow navigation industries to transport bulk commodities through the region. The dredging work is necessary because the pool level dropped approximately two feet after the Pittsburgh District removed the navigation dam near Elizabeth, Pennsylvania in 2024. The current pool elevation is approximately 724 feet above sea level between the towns of Charleroi and Braddock, Pennsylvania. Elevation figures are based on the North American Vertical Datum of 1988. Eventually, the Pittsburgh District will drop the revel another foot in the pool being dredged. The district has not yet determined a timeline for the final elevation drop. The district is actively assessing the navigation channel and the impact the pool change has on shoreside facilities, navigation industries and other stakeholders. Once the district has completed the necessary dredging and completed its assessments, it will determine when to drop the river level to its final authorized elevation. The final pool elevations will be 723.1 feet. (U.S. Army Corps of Engineers Pittsburgh District photo by Michel Sauret)

The dredging contract consists of two dredging crews that have been working six days a week since September. The crews have removed more than 314 barges of material so far, equivalent to 166,000 tons of soil, rocks and debris from the river bottom.
PHOTO DETAILS  /   DOWNLOAD HI-RES 10 of 24

A deckhand works a rope on a dredging barge contracted by the U.S. Army Corps of Engineers Pittsburgh District to remove soil, rocks and other materials from the Monongahela River south of Pittsburgh, March 20, 2025. The dredging contract consists of two dredging crews that have been working six days a week since September. The crews have removed more than 314 barges of material so far, equivalent to 166,000 tons of soil, rocks and debris from the river bottom. The contract aims to restore up to ten feet of depth along the Monongahela River in specific shallow areas to allow navigation industries to transport bulk commodities through the region. The dredging work is necessary because the pool level dropped approximately two feet after the Pittsburgh District removed the navigation dam near Elizabeth, Pennsylvania in 2024. The current pool elevation is approximately 724 feet above sea level between the towns of Charleroi and Braddock, Pennsylvania. Elevation figures are based on the North American Vertical Datum of 1988. Eventually, the Pittsburgh District will drop the revel another foot in the pool being dredged. The district has not yet determined a timeline for the final elevation drop. The district is actively assessing the navigation channel and the impact the pool change has on shoreside facilities, navigation industries and other stakeholders. Once the district has completed the necessary dredging and completed its assessments, it will determine when to drop the river level to its final authorized elevation. The final pool elevations will be 723.1 feet. (U.S. Army Corps of Engineers Pittsburgh District photo by Michel Sauret)

The dredging contract consists of two dredging crews that have been working six days a week since September. The crews have removed more than 314 barges of material so far, equivalent to 166,000 tons of soil, rocks and debris from the river bottom.
PHOTO DETAILS  /   DOWNLOAD HI-RES 11 of 24

Art Innamorato, a construction manager for a U.S. Army Corps of Engineers Pittsburgh District contractor, ties off a boat against a dredging rig on the Monongahela River south of Pittsburgh, March 20, 2025. The dredging contract consists of two dredging crews that have been working six days a week since September. The crews have removed more than 314 barges of material so far, equivalent to 166,000 tons of soil, rocks and debris from the river bottom. The contract aims to restore up to ten feet of depth along the Monongahela River in specific shallow areas to allow navigation industries to transport bulk commodities through the region. The dredging work is necessary because the pool level dropped approximately two feet after the Pittsburgh District removed the navigation dam near Elizabeth, Pennsylvania in 2024. The current pool elevation is approximately 724 feet above sea level between the towns of Charleroi and Braddock, Pennsylvania. Elevation figures are based on the North American Vertical Datum of 1988. Eventually, the Pittsburgh District will drop the revel another foot in the pool being dredged. The district has not yet determined a timeline for the final elevation drop. The district is actively assessing the navigation channel and the impact the pool change has on shoreside facilities, navigation industries and other stakeholders. Once the district has completed the necessary dredging and completed its assessments, it will determine when to drop the river level to its final authorized elevation. The final pool elevations will be 723.1 feet. (U.S. Army Corps of Engineers Pittsburgh District photo by Michel Sauret)

The dredging contract consists of two dredging crews that have been working six days a week since September. The crews have removed more than 314 barges of material so far, equivalent to 166,000 tons of soil, rocks and debris from the river bottom.
PHOTO DETAILS  /   DOWNLOAD HI-RES 12 of 24

A U.S. Army Corps of Engineers Pittsburgh District contractor dredges soil, rocks and other materials from the Monongahela River south of Pittsburgh, March 20, 2025. The dredging contract consists of two dredging crews that have been working six days a week since September. The crews have removed more than 314 barges of material so far, equivalent to 166,000 tons of soil, rocks and debris from the river bottom. The contract aims to restore up to ten feet of depth along the Monongahela River in specific shallow areas to allow navigation industries to transport bulk commodities through the region. The dredging work is necessary because the pool level dropped approximately two feet after the Pittsburgh District removed the navigation dam near Elizabeth, Pennsylvania in 2024. The current pool elevation is approximately 724 feet above sea level between the towns of Charleroi and Braddock, Pennsylvania. Elevation figures are based on the North American Vertical Datum of 1988. Eventually, the Pittsburgh District will drop the revel another foot in the pool being dredged. The district has not yet determined a timeline for the final elevation drop. The district is actively assessing the navigation channel and the impact the pool change has on shoreside facilities, navigation industries and other stakeholders. Once the district has completed the necessary dredging and completed its assessments, it will determine when to drop the river level to its final authorized elevation. The final pool elevations will be 723.1 feet. (U.S. Army Corps of Engineers Pittsburgh District photo by Michel Sauret)

The dredging contract consists of two dredging crews that have been working six days a week since September. The crews have removed more than 314 barges of material so far, equivalent to 166,000 tons of soil, rocks and debris from the river bottom.
PHOTO DETAILS  /   DOWNLOAD HI-RES 13 of 24

A U.S. Army Corps of Engineers Pittsburgh District contractor dredges soil, rocks and other materials from the Monongahela River south of Pittsburgh, March 20, 2025. The dredging contract consists of two dredging crews that have been working six days a week since September. The crews have removed more than 314 barges of material so far, equivalent to 166,000 tons of soil, rocks and debris from the river bottom. The contract aims to restore up to ten feet of depth along the Monongahela River in specific shallow areas to allow navigation industries to transport bulk commodities through the region. The dredging work is necessary because the pool level dropped approximately two feet after the Pittsburgh District removed the navigation dam near Elizabeth, Pennsylvania in 2024. The current pool elevation is approximately 724 feet above sea level between the towns of Charleroi and Braddock, Pennsylvania. Elevation figures are based on the North American Vertical Datum of 1988. Eventually, the Pittsburgh District will drop the revel another foot in the pool being dredged. The district has not yet determined a timeline for the final elevation drop. The district is actively assessing the navigation channel and the impact the pool change has on shoreside facilities, navigation industries and other stakeholders. Once the district has completed the necessary dredging and completed its assessments, it will determine when to drop the river level to its final authorized elevation. The final pool elevations will be 723.1 feet. (U.S. Army Corps of Engineers Pittsburgh District photo by Michel Sauret)

The dredging contract consists of two dredging crews that have been working six days a week since September. The crews have removed more than 314 barges of material so far, equivalent to 166,000 tons of soil, rocks and debris from the river bottom.
PHOTO DETAILS  /   DOWNLOAD HI-RES 14 of 24

The American flag flutters in the wind on the back of a towboat contracted by the U.S. Army Corps of Engineers Pittsburgh District to dredge the Monongahela River south of Pittsburgh, March 20, 2025. The dredging contract consists of two dredging crews that have been working six days a week since September. The crews have removed more than 314 barges of material so far, equivalent to 166,000 tons of soil, rocks and debris from the river bottom. The contract aims to restore up to ten feet of depth along the Monongahela River in specific shallow areas to allow navigation industries to transport bulk commodities through the region. The dredging work is necessary because the pool level dropped approximately two feet after the Pittsburgh District removed the navigation dam near Elizabeth, Pennsylvania in 2024. The current pool elevation is approximately 724 feet above sea level between the towns of Charleroi and Braddock, Pennsylvania. Elevation figures are based on the North American Vertical Datum of 1988. Eventually, the Pittsburgh District will drop the revel another foot in the pool being dredged. The district has not yet determined a timeline for the final elevation drop. The district is actively assessing the navigation channel and the impact the pool change has on shoreside facilities, navigation industries and other stakeholders. Once the district has completed the necessary dredging and completed its assessments, it will determine when to drop the river level to its final authorized elevation. The final pool elevations will be 723.1 feet. (U.S. Army Corps of Engineers Pittsburgh District photo by Michel Sauret)

The dredging contract consists of two dredging crews that have been working six days a week since September. The crews have removed more than 314 barges of material so far, equivalent to 166,000 tons of soil, rocks and debris from the river bottom.
PHOTO DETAILS  /   DOWNLOAD HI-RES 15 of 24

The American flag flutters in the wind on the back of a towboat contracted by the U.S. Army Corps of Engineers Pittsburgh District to dredge the Monongahela River south of Pittsburgh, March 20, 2025. The dredging contract consists of two dredging crews that have been working six days a week since September. The crews have removed more than 314 barges of material so far, equivalent to 166,000 tons of soil, rocks and debris from the river bottom. The contract aims to restore up to ten feet of depth along the Monongahela River in specific shallow areas to allow navigation industries to transport bulk commodities through the region. The dredging work is necessary because the pool level dropped approximately two feet after the Pittsburgh District removed the navigation dam near Elizabeth, Pennsylvania in 2024. The current pool elevation is approximately 724 feet above sea level between the towns of Charleroi and Braddock, Pennsylvania. Elevation figures are based on the North American Vertical Datum of 1988. Eventually, the Pittsburgh District will drop the revel another foot in the pool being dredged. The district has not yet determined a timeline for the final elevation drop. The district is actively assessing the navigation channel and the impact the pool change has on shoreside facilities, navigation industries and other stakeholders. Once the district has completed the necessary dredging and completed its assessments, it will determine when to drop the river level to its final authorized elevation. The final pool elevations will be 723.1 feet. (U.S. Army Corps of Engineers Pittsburgh District photo by Michel Sauret)

The dredging contract consists of two dredging crews that have been working six days a week since September. The crews have removed more than 314 barges of material so far, equivalent to 166,000 tons of soil, rocks and debris from the river bottom.
PHOTO DETAILS  /   DOWNLOAD HI-RES 16 of 24

A U.S. Army Corps of Engineers Pittsburgh District contractor dredges soil, rocks and other materials from the Monongahela River south of Pittsburgh, March 20, 2025. The dredging contract consists of two dredging crews that have been working six days a week since September. The crews have removed more than 314 barges of material so far, equivalent to 166,000 tons of soil, rocks and debris from the river bottom. The contract aims to restore up to ten feet of depth along the Monongahela River in specific shallow areas to allow navigation industries to transport bulk commodities through the region. The dredging work is necessary because the pool level dropped approximately two feet after the Pittsburgh District removed the navigation dam near Elizabeth, Pennsylvania in 2024. The current pool elevation is approximately 724 feet above sea level between the towns of Charleroi and Braddock, Pennsylvania. Elevation figures are based on the North American Vertical Datum of 1988. Eventually, the Pittsburgh District will drop the revel another foot in the pool being dredged. The district has not yet determined a timeline for the final elevation drop. The district is actively assessing the navigation channel and the impact the pool change has on shoreside facilities, navigation industries and other stakeholders. Once the district has completed the necessary dredging and completed its assessments, it will determine when to drop the river level to its final authorized elevation. The final pool elevations will be 723.1 feet. (U.S. Army Corps of Engineers Pittsburgh District photo by Michel Sauret)

The dredging contract consists of two dredging crews that have been working six days a week since September. The crews have removed more than 314 barges of material so far, equivalent to 166,000 tons of soil, rocks and debris from the river bottom.
PHOTO DETAILS  /   DOWNLOAD HI-RES 17 of 24

A U.S. Army Corps of Engineers Pittsburgh District contractor dredges soil, rocks and other materials from the Monongahela River south of Pittsburgh, March 20, 2025. The dredging contract consists of two dredging crews that have been working six days a week since September. The crews have removed more than 314 barges of material so far, equivalent to 166,000 tons of soil, rocks and debris from the river bottom. The contract aims to restore up to ten feet of depth along the Monongahela River in specific shallow areas to allow navigation industries to transport bulk commodities through the region. The dredging work is necessary because the pool level dropped approximately two feet after the Pittsburgh District removed the navigation dam near Elizabeth, Pennsylvania in 2024. The current pool elevation is approximately 724 feet above sea level between the towns of Charleroi and Braddock, Pennsylvania. Elevation figures are based on the North American Vertical Datum of 1988. Eventually, the Pittsburgh District will drop the revel another foot in the pool being dredged. The district has not yet determined a timeline for the final elevation drop. The district is actively assessing the navigation channel and the impact the pool change has on shoreside facilities, navigation industries and other stakeholders. Once the district has completed the necessary dredging and completed its assessments, it will determine when to drop the river level to its final authorized elevation. The final pool elevations will be 723.1 feet. (U.S. Army Corps of Engineers Pittsburgh District photo by Michel Sauret)

The dredging contract consists of two dredging crews that have been working six days a week since September. The crews have removed more than 314 barges of material so far, equivalent to 166,000 tons of soil, rocks and debris from the river bottom.
PHOTO DETAILS  /   DOWNLOAD HI-RES 18 of 24

A U.S. Army Corps of Engineers Pittsburgh District contractor dredges soil, rocks and other materials from the Monongahela River south of Pittsburgh, March 20, 2025. The dredging contract consists of two dredging crews that have been working six days a week since September. The crews have removed more than 314 barges of material so far, equivalent to 166,000 tons of soil, rocks and debris from the river bottom. The contract aims to restore up to ten feet of depth along the Monongahela River in specific shallow areas to allow navigation industries to transport bulk commodities through the region. The dredging work is necessary because the pool level dropped approximately two feet after the Pittsburgh District removed the navigation dam near Elizabeth, Pennsylvania in 2024. The current pool elevation is approximately 724 feet above sea level between the towns of Charleroi and Braddock, Pennsylvania. Elevation figures are based on the North American Vertical Datum of 1988. Eventually, the Pittsburgh District will drop the revel another foot in the pool being dredged. The district has not yet determined a timeline for the final elevation drop. The district is actively assessing the navigation channel and the impact the pool change has on shoreside facilities, navigation industries and other stakeholders. Once the district has completed the necessary dredging and completed its assessments, it will determine when to drop the river level to its final authorized elevation. The final pool elevations will be 723.1 feet. (U.S. Army Corps of Engineers Pittsburgh District photo by Michel Sauret)

The dredging contract consists of two dredging crews that have been working six days a week since September. The crews have removed more than 314 barges of material so far, equivalent to 166,000 tons of soil, rocks and debris from the river bottom.
PHOTO DETAILS  /   DOWNLOAD HI-RES 19 of 24

A U.S. Army Corps of Engineers Pittsburgh District contractor dredges soil, rocks and other materials from the Monongahela River south of Pittsburgh, March 20, 2025. The dredging contract consists of two dredging crews that have been working six days a week since September. The crews have removed more than 314 barges of material so far, equivalent to 166,000 tons of soil, rocks and debris from the river bottom. The contract aims to restore up to ten feet of depth along the Monongahela River in specific shallow areas to allow navigation industries to transport bulk commodities through the region. The dredging work is necessary because the pool level dropped approximately two feet after the Pittsburgh District removed the navigation dam near Elizabeth, Pennsylvania in 2024. The current pool elevation is approximately 724 feet above sea level between the towns of Charleroi and Braddock, Pennsylvania. Elevation figures are based on the North American Vertical Datum of 1988. Eventually, the Pittsburgh District will drop the revel another foot in the pool being dredged. The district has not yet determined a timeline for the final elevation drop. The district is actively assessing the navigation channel and the impact the pool change has on shoreside facilities, navigation industries and other stakeholders. Once the district has completed the necessary dredging and completed its assessments, it will determine when to drop the river level to its final authorized elevation. The final pool elevations will be 723.1 feet. (U.S. Army Corps of Engineers Pittsburgh District photo by Michel Sauret)

The dredging contract consists of two dredging crews that have been working six days a week since September. The crews have removed more than 314 barges of material so far, equivalent to 166,000 tons of soil, rocks and debris from the river bottom.
PHOTO DETAILS  /   DOWNLOAD HI-RES 20 of 24

A dredging excavator reflects off the glass of a towboat while another dredging rig sets up in the distance on the Monongahela River south of Pittsburgh, March 20, 2025. The dredging is part of a contract for the U.S. Army Corps of Engineers Pittsburgh District. The dredging contract consists of two dredging crews that have been working six days a week since September. The crews have removed more than 314 barges of material so far, equivalent to 166,000 tons of soil, rocks and debris from the river bottom. The contract aims to restore up to ten feet of depth along the Monongahela River in specific shallow areas to allow navigation industries to transport bulk commodities through the region. The dredging work is necessary because the pool level dropped approximately two feet after the Pittsburgh District removed the navigation dam near Elizabeth, Pennsylvania in 2024. The current pool elevation is approximately 724 feet above sea level between the towns of Charleroi and Braddock, Pennsylvania. Elevation figures are based on the North American Vertical Datum of 1988. Eventually, the Pittsburgh District will drop the revel another foot in the pool being dredged. The district has not yet determined a timeline for the final elevation drop. The district is actively assessing the navigation channel and the impact the pool change has on shoreside facilities, navigation industries and other stakeholders. Once the district has completed the necessary dredging and completed its assessments, it will determine when to drop the river level to its final authorized elevation. The final pool elevations will be 723.1 feet. (U.S. Army Corps of Engineers Pittsburgh District photo by Michel Sauret)

The dredging contract consists of two dredging crews that have been working six days a week since September. The crews have removed more than 314 barges of material so far, equivalent to 166,000 tons of soil, rocks and debris from the river bottom.
PHOTO DETAILS  /   DOWNLOAD HI-RES 21 of 24

Ethan Shimko, the captain of a towboat for a U.S. Army Corps of Engineers Pittsburgh District contractor, steers a rig with a barge and excavator to dredge the Monongahela River south of Pittsburgh, March 20, 2025. The dredging contract consists of two dredging crews that have been working six days a week since September. The crews have removed more than 314 barges of material so far, equivalent to 166,000 tons of soil, rocks and debris from the river bottom. The contract aims to restore up to ten feet of depth along the Monongahela River in specific shallow areas to allow navigation industries to transport bulk commodities through the region. The dredging work is necessary because the pool level dropped approximately two feet after the Pittsburgh District removed the navigation dam near Elizabeth, Pennsylvania in 2024. The current pool elevation is approximately 724 feet above sea level between the towns of Charleroi and Braddock, Pennsylvania. Elevation figures are based on the North American Vertical Datum of 1988. Eventually, the Pittsburgh District will drop the revel another foot in the pool being dredged. The district has not yet determined a timeline for the final elevation drop. The district is actively assessing the navigation channel and the impact the pool change has on shoreside facilities, navigation industries and other stakeholders. Once the district has completed the necessary dredging and completed its assessments, it will determine when to drop the river level to its final authorized elevation. The final pool elevations will be 723.1 feet. (U.S. Army Corps of Engineers Pittsburgh District photo by Michel Sauret)

The dredging contract consists of two dredging crews that have been working six days a week since September. The crews have removed more than 314 barges of material so far, equivalent to 166,000 tons of soil, rocks and debris from the river bottom.
PHOTO DETAILS  /   DOWNLOAD HI-RES 22 of 24

The U.S. Army Corps of Engineers Pittsburgh District contracted a river crew to dredge soil and material from the Monongahela River bottom to restore river depth in certain areas south of Pittsburgh, March 20, 2025. The dredging contract consists of two dredging crews that have been working six days a week since September. The crews have removed more than 314 barges of material so far, equivalent to 166,000 tons of soil, rocks and debris from the river bottom. The contract aims to restore up to ten feet of depth along the Monongahela River in specific shallow areas to allow navigation industries to transport bulk commodities through the region. The dredging work is necessary because the pool level dropped approximately two feet after the Pittsburgh District removed the navigation dam near Elizabeth, Pennsylvania in 2024. The current pool elevation is approximately 724 feet above sea level between the towns of Charleroi and Braddock, Pennsylvania. Elevation figures are based on the North American Vertical Datum of 1988. Eventually, the Pittsburgh District will drop the revel another foot in the pool being dredged. The district has not yet determined a timeline for the final elevation drop. The district is actively assessing the navigation channel and the impact the pool change has on shoreside facilities, navigation industries and other stakeholders. Once the district has completed the necessary dredging and completed its assessments, it will determine when to drop the river level to its final authorized elevation. The final pool elevations will be 723.1 feet. (U.S. Army Corps of Engineers Pittsburgh District photo by Michel Sauret)

The dredging contract consists of two dredging crews that have been working six days a week since September. The crews have removed more than 314 barges of material so far, equivalent to 166,000 tons of soil, rocks and debris from the river bottom.
PHOTO DETAILS  /   DOWNLOAD HI-RES 23 of 24

Sgt. 1st Class Jonathan Baker, a quality assurance representative for the U.S. Army Corps of Engineers Pittsburgh District, rides on a boat to a construction rig on the Monongahela River where a contractor is performing dredging to restore river depth for navigation industries south of Pittsburgh, March 20, 2025. The dredging contract consists of two dredging crews that have been working six days a week since September. The crews have removed more than 314 barges of material so far, equivalent to 166,000 tons of soil, rocks and debris from the river bottom. The contract aims to restore up to ten feet of depth along the Monongahela River in specific shallow areas to allow navigation industries to transport bulk commodities through the region. The dredging work is necessary because the pool level dropped approximately two feet after the Pittsburgh District removed the navigation dam near Elizabeth, Pennsylvania in 2024. The current pool elevation is approximately 724 feet above sea level between the towns of Charleroi and Braddock, Pennsylvania. Elevation figures are based on the North American Vertical Datum of 1988. Eventually, the Pittsburgh District will drop the revel another foot in the pool being dredged. The district has not yet determined a timeline for the final elevation drop. The district is actively assessing the navigation channel and the impact the pool change has on shoreside facilities, navigation industries and other stakeholders. Once the district has completed the necessary dredging and completed its assessments, it will determine when to drop the river level to its final authorized elevation. The final pool elevations will be 723.1 feet. (U.S. Army Corps of Engineers Pittsburgh District photo by Michel Sauret)

The dredging contract consists of two dredging crews that have been working six days a week since September. The crews have removed more than 314 barges of material so far, equivalent to 166,000 tons of soil, rocks and debris from the river bottom.
PHOTO DETAILS  /   DOWNLOAD HI-RES 24 of 24

Art Innamorato, a construction manager for a U.S. Army Corps of Engineers Pittsburgh District contractor, talks on the radio while driving a boat on the Monongahela River south of Pittsburgh, March 20, 2025. The dredging contract consists of two dredging crews that have been working six days a week since September. The crews have removed more than 314 barges of material so far, equivalent to 166,000 tons of soil, rocks and debris from the river bottom. The contract aims to restore up to ten feet of depth along the Monongahela River in specific shallow areas to allow navigation industries to transport bulk commodities through the region. The dredging work is necessary because the pool level dropped approximately two feet after the Pittsburgh District removed the navigation dam near Elizabeth, Pennsylvania in 2024. The current pool elevation is approximately 724 feet above sea level between the towns of Charleroi and Braddock, Pennsylvania. Elevation figures are based on the North American Vertical Datum of 1988. Eventually, the Pittsburgh District will drop the revel another foot in the pool being dredged. The district has not yet determined a timeline for the final elevation drop. The district is actively assessing the navigation channel and the impact the pool change has on shoreside facilities, navigation industries and other stakeholders. Once the district has completed the necessary dredging and completed its assessments, it will determine when to drop the river level to its final authorized elevation. The final pool elevations will be 723.1 feet. (U.S. Army Corps of Engineers Pittsburgh District photo by Michel Sauret)

PITTSBURGH – Scooping up rocks and soil from the river may seem simple. After all, who hasn’t played with dirt, shovels or excavating toys on the beach when they were kids?

Except, dredging the bottom of the Monongahela River isn’t anything like playing on the beach, and it’s no child’s play. It is hard work requiring laser-focused coordination, planning, soil testing and precision.

The dredging contract consists of two dredging crews that have been working six days a week since September. The crews have removed more than 314 barges of material so far, equivalent to 166,000 tons of soil, rocks and debris from the river bottom.
Monongahela Dredging
A U.S. Army Corps of Engineers Pittsburgh District contractor dredges soil, rocks and other materials from the Monongahela River south of Pittsburgh, March 20, 2025. The dredging contract consists of two dredging crews that have been working six days a week since September. The crews have removed more than 314 barges of material so far, equivalent to 166,000 tons of soil, rocks and debris from the river bottom. The contract aims to restore up to ten feet of depth along the Monongahela River in specific shallow areas to allow navigation industries to transport bulk commodities through the region. The dredging work is necessary because the pool level dropped approximately two feet after the Pittsburgh District removed the navigation dam near Elizabeth, Pennsylvania in 2024. The current pool elevation is approximately 724 feet above sea level between the towns of Charleroi and Braddock, Pennsylvania. Elevation figures are based on the North American Vertical Datum of 1988. Eventually, the Pittsburgh District will drop the revel another foot in the pool being dredged. The district has not yet determined a timeline for the final elevation drop. The district is actively assessing the navigation channel and the impact the pool change has on shoreside facilities, navigation industries and other stakeholders. Once the district has completed the necessary dredging and completed its assessments, it will determine when to drop the river level to its final authorized elevation. The final pool elevations will be 723.1 feet. (U.S. Army Corps of Engineers Pittsburgh District photo by Michel Sauret)
Photo By: Michel Sauret
VIRIN: 250320-A-TI382-1873

“Our contractor has been doing a great job,” said Sgt. 1st Class Jonathan Baker, the quality assurance representative validating the work daily for the U.S. Army Corps of Engineers Pittsburgh District.

The dredging contract consists of two dredging crews that have been working six days a week since September. The crews have removed more than 314 barges of material so far, equivalent to 166,000 tons of soil, rocks and debris from the river bottom.
Monongahela Dredging
Sgt. 1st Class Jonathan Baker, a quality assurance representative for the U.S. Army Corps of Engineers Pittsburgh District, rides on a boat to a construction rig on the Monongahela River where a contractor is performing dredging to restore river depth for navigation industries south of Pittsburgh, March 20, 2025. The dredging contract consists of two dredging crews that have been working six days a week since September. The crews have removed more than 314 barges of material so far, equivalent to 166,000 tons of soil, rocks and debris from the river bottom. The contract aims to restore up to ten feet of depth along the Monongahela River in specific shallow areas to allow navigation industries to transport bulk commodities through the region. The dredging work is necessary because the pool level dropped approximately two feet after the Pittsburgh District removed the navigation dam near Elizabeth, Pennsylvania in 2024. The current pool elevation is approximately 724 feet above sea level between the towns of Charleroi and Braddock, Pennsylvania. Elevation figures are based on the North American Vertical Datum of 1988. Eventually, the Pittsburgh District will drop the revel another foot in the pool being dredged. The district has not yet determined a timeline for the final elevation drop. The district is actively assessing the navigation channel and the impact the pool change has on shoreside facilities, navigation industries and other stakeholders. Once the district has completed the necessary dredging and completed its assessments, it will determine when to drop the river level to its final authorized elevation. The final pool elevations will be 723.1 feet. (U.S. Army Corps of Engineers Pittsburgh District photo by Michel Sauret)
Photo By: Michel Sauret
VIRIN: 250320-A-TI382-1049

The Pittsburgh District contracted a crew to dredge the Monongahela River between the towns of Elizabeth and Charleroi. The work began in mid-September 2024.  Dredging clears the way for industries to transport bulk commodities through the southern region of Pittsburgh.

“Without it, navigation on the river would be severely hampered. The industry understands the need for this work, and so do we,” said Art Innamorato, the contractor’s construction manager. “This work is challenging but rewarding. No two days are ever the same.”

Dredging became necessary when the pool level dropped approximately two feet in the summer of 2024 after the Pittsburgh District removed the navigation dam near Elizabeth due to its aging infrastructure and costly lock maintenance repairs. The removal of the navigation facility created 33 miles of unobstructed riverway.

The dredging contract consists of two dredging crews that have been working six days a week since September. The crews have removed more than 314 barges of material so far, equivalent to 166,000 tons of soil, rocks and debris from the river bottom.
Monongahela Dredging
A U.S. Army Corps of Engineers Pittsburgh District contractor dredges soil, rocks and other materials from the Monongahela River south of Pittsburgh, March 20, 2025. The dredging contract consists of two dredging crews that have been working six days a week since September. The crews have removed more than 314 barges of material so far, equivalent to 166,000 tons of soil, rocks and debris from the river bottom. The contract aims to restore up to ten feet of depth along the Monongahela River in specific shallow areas to allow navigation industries to transport bulk commodities through the region. The dredging work is necessary because the pool level dropped approximately two feet after the Pittsburgh District removed the navigation dam near Elizabeth, Pennsylvania in 2024. The current pool elevation is approximately 724 feet above sea level between the towns of Charleroi and Braddock, Pennsylvania. Elevation figures are based on the North American Vertical Datum of 1988. Eventually, the Pittsburgh District will drop the revel another foot in the pool being dredged. The district has not yet determined a timeline for the final elevation drop. The district is actively assessing the navigation channel and the impact the pool change has on shoreside facilities, navigation industries and other stakeholders. Once the district has completed the necessary dredging and completed its assessments, it will determine when to drop the river level to its final authorized elevation. The final pool elevations will be 723.1 feet. (U.S. Army Corps of Engineers Pittsburgh District photo by Michel Sauret)
Photo By: Michel Sauret
VIRIN: 250320-A-TI382-2170

However, lowering the pool exposed shallow areas upstream of Elizabeth. The district is responsible for maintaining at least a nine-foot draft for larger vessels transporting goods such as coal or construction material.

The contractor has been operating two dredging crews six days a week since the channel restoration began. So far, crews have removed more than 314 barges of sediment, totaling 166,000 tons of soil, rock, and debris from the river bottom.

The dredging contract consists of two dredging crews that have been working six days a week since September. The crews have removed more than 314 barges of material so far, equivalent to 166,000 tons of soil, rocks and debris from the river bottom.
Monongahela Dredging
Art Innamorato, a construction manager for a U.S. Army Corps of Engineers Pittsburgh District contractor, ties off a boat against a dredging rig on the Monongahela River south of Pittsburgh, March 20, 2025. The dredging contract consists of two dredging crews that have been working six days a week since September. The crews have removed more than 314 barges of material so far, equivalent to 166,000 tons of soil, rocks and debris from the river bottom. The contract aims to restore up to ten feet of depth along the Monongahela River in specific shallow areas to allow navigation industries to transport bulk commodities through the region. The dredging work is necessary because the pool level dropped approximately two feet after the Pittsburgh District removed the navigation dam near Elizabeth, Pennsylvania in 2024. The current pool elevation is approximately 724 feet above sea level between the towns of Charleroi and Braddock, Pennsylvania. Elevation figures are based on the North American Vertical Datum of 1988. Eventually, the Pittsburgh District will drop the revel another foot in the pool being dredged. The district has not yet determined a timeline for the final elevation drop. The district is actively assessing the navigation channel and the impact the pool change has on shoreside facilities, navigation industries and other stakeholders. Once the district has completed the necessary dredging and completed its assessments, it will determine when to drop the river level to its final authorized elevation. The final pool elevations will be 723.1 feet. (U.S. Army Corps of Engineers Pittsburgh District photo by Michel Sauret)
Photo By: Michel Sauret
VIRIN: 250320-A-TI382-1153

The Pittsburgh District plans to lower the channel another foot to a final elevation of 723.1 feet, but only after careful assessment of the impact on shoreside industries, navigation, and other stakeholders.

Dredging is complex and meticulously planned operation. Each rig is outfitted with a port-sized excavator, a barge capable of holding over 500 tons of material, and a towboat to maneuver their setup into position. Crews use state-of-the-art radar and sonar mapping systems to create 3D contour maps of the riverbed, which ensure precise execution of dredging where needed. These maps, generated using millions of data points, allow operators to track depth changes and real time validation of their work.

The dredging contract consists of two dredging crews that have been working six days a week since September. The crews have removed more than 314 barges of material so far, equivalent to 166,000 tons of soil, rocks and debris from the river bottom.
Monongahela Dredging
Art Innamorato, a construction manager for a U.S. Army Corps of Engineers Pittsburgh District contractor, points to a screen showing a live view of an excavator dredging material from the Monongahela River south of Pittsburgh, March 20, 2025. The dredging contract consists of two dredging crews that have been working six days a week since September. The crews have removed more than 314 barges of material so far, equivalent to 166,000 tons of soil, rocks and debris from the river bottom. The contract aims to restore up to ten feet of depth along the Monongahela River in specific shallow areas to allow navigation industries to transport bulk commodities through the region. The dredging work is necessary because the pool level dropped approximately two feet after the Pittsburgh District removed the navigation dam near Elizabeth, Pennsylvania in 2024. The current pool elevation is approximately 724 feet above sea level between the towns of Charleroi and Braddock, Pennsylvania. Elevation figures are based on the North American Vertical Datum of 1988. Eventually, the Pittsburgh District will drop the revel another foot in the pool being dredged. The district has not yet determined a timeline for the final elevation drop. The district is actively assessing the navigation channel and the impact the pool change has on shoreside facilities, navigation industries and other stakeholders. Once the district has completed the necessary dredging and completed its assessments, it will determine when to drop the river level to its final authorized elevation. The final pool elevations will be 723.1 feet. (U.S. Army Corps of Engineers Pittsburgh District photo by Michel Sauret)
Photo By: Michel Sauret
VIRIN: 250320-A-TI382-2368

As a safety measure, the towboat captains rely on a “Rose Point” navigation system to monitor nearby vessels. When commercial towboats pass through the dredging zone, crews pull their spuds – vertical anchors that stabilize their rigs – and momentarily pause operations to allow safe passage. Once the vessel clears, dredging resumes without significant delays.

Despite their high-tech capabilities, crews have faced heavy challenges – literally. On a few occasions, the excavator clam grabbed hold of boulders too heavy to lift. One boulder was the size of a dining room table. It was too heavy to remove from the water. Instead, the crew dragged the boulder out of the channel’s navigation path toward the riverbank to keep vessels safe.

The dredging contract consists of two dredging crews that have been working six days a week since September. The crews have removed more than 314 barges of material so far, equivalent to 166,000 tons of soil, rocks and debris from the river bottom.
Monongahela Dredging
A dredging excavator reflects off the glass of a towboat while another dredging rig sets up in the distance on the Monongahela River south of Pittsburgh, March 20, 2025. The dredging is part of a contract for the U.S. Army Corps of Engineers Pittsburgh District. The dredging contract consists of two dredging crews that have been working six days a week since September. The crews have removed more than 314 barges of material so far, equivalent to 166,000 tons of soil, rocks and debris from the river bottom. The contract aims to restore up to ten feet of depth along the Monongahela River in specific shallow areas to allow navigation industries to transport bulk commodities through the region. The dredging work is necessary because the pool level dropped approximately two feet after the Pittsburgh District removed the navigation dam near Elizabeth, Pennsylvania in 2024. The current pool elevation is approximately 724 feet above sea level between the towns of Charleroi and Braddock, Pennsylvania. Elevation figures are based on the North American Vertical Datum of 1988. Eventually, the Pittsburgh District will drop the revel another foot in the pool being dredged. The district has not yet determined a timeline for the final elevation drop. The district is actively assessing the navigation channel and the impact the pool change has on shoreside facilities, navigation industries and other stakeholders. Once the district has completed the necessary dredging and completed its assessments, it will determine when to drop the river level to its final authorized elevation. The final pool elevations will be 723.1 feet. (U.S. Army Corps of Engineers Pittsburgh District photo by Michel Sauret)
Photo By: Michel Sauret
VIRIN: 250320-A-TI382-1415

“Some boulders are just too big to remove, so we have to work around them,” Innamorato said.

In 2000, the Pittsburgh District performed a dredging contract in the Monongahela River specifically to remove sediment and material that did not meet environmental standards. That material was taken to a commercial facility authorized to receive those types of wastes.

The dredging contract consists of two dredging crews that have been working six days a week since September. The crews have removed more than 314 barges of material so far, equivalent to 166,000 tons of soil, rocks and debris from the river bottom.
Monongahela Dredging
Ethan Shimko, the captain of a towboat for a U.S. Army Corps of Engineers Pittsburgh District contractor, steers a rig with a barge and excavator to dredge the Monongahela River south of Pittsburgh, March 20, 2025. The dredging contract consists of two dredging crews that have been working six days a week since September. The crews have removed more than 314 barges of material so far, equivalent to 166,000 tons of soil, rocks and debris from the river bottom. The contract aims to restore up to ten feet of depth along the Monongahela River in specific shallow areas to allow navigation industries to transport bulk commodities through the region. The dredging work is necessary because the pool level dropped approximately two feet after the Pittsburgh District removed the navigation dam near Elizabeth, Pennsylvania in 2024. The current pool elevation is approximately 724 feet above sea level between the towns of Charleroi and Braddock, Pennsylvania. Elevation figures are based on the North American Vertical Datum of 1988. Eventually, the Pittsburgh District will drop the revel another foot in the pool being dredged. The district has not yet determined a timeline for the final elevation drop. The district is actively assessing the navigation channel and the impact the pool change has on shoreside facilities, navigation industries and other stakeholders. Once the district has completed the necessary dredging and completed its assessments, it will determine when to drop the river level to its final authorized elevation. The final pool elevations will be 723.1 feet. (U.S. Army Corps of Engineers Pittsburgh District photo by Michel Sauret)
Photo By: Michel Sauret
VIRIN: 250320-A-TI382-1375

The current dredging consists of mostly sands and gravel, transported daily to a site known as “Victory Hollow” owned and operated locally by the U.S. Army Corps of Engineers. All the material disposed here has been tested and determined to meet Pennsylvania’s Management of Fill Policy.

“When conducting Lower Mon dredging, we do annual checks for any changes in the environment or spills in the areas that may affect the locations where we will be,” said Bobbi Jo McClain, the Pittsburgh District’s chief of the environmental section.

The dredging contract consists of two dredging crews that have been working six days a week since September. The crews have removed more than 314 barges of material so far, equivalent to 166,000 tons of soil, rocks and debris from the river bottom.
Monongahela Dredging
A U.S. Army Corps of Engineers Pittsburgh District contractor dredges soil, rocks and other materials from the Monongahela River south of Pittsburgh, March 20, 2025. The dredging contract consists of two dredging crews that have been working six days a week since September. The crews have removed more than 314 barges of material so far, equivalent to 166,000 tons of soil, rocks and debris from the river bottom. The contract aims to restore up to ten feet of depth along the Monongahela River in specific shallow areas to allow navigation industries to transport bulk commodities through the region. The dredging work is necessary because the pool level dropped approximately two feet after the Pittsburgh District removed the navigation dam near Elizabeth, Pennsylvania in 2024. The current pool elevation is approximately 724 feet above sea level between the towns of Charleroi and Braddock, Pennsylvania. Elevation figures are based on the North American Vertical Datum of 1988. Eventually, the Pittsburgh District will drop the revel another foot in the pool being dredged. The district has not yet determined a timeline for the final elevation drop. The district is actively assessing the navigation channel and the impact the pool change has on shoreside facilities, navigation industries and other stakeholders. Once the district has completed the necessary dredging and completed its assessments, it will determine when to drop the river level to its final authorized elevation. The final pool elevations will be 723.1 feet. (U.S. Army Corps of Engineers Pittsburgh District photo by Michel Sauret)
Photo By: Michel Sauret
VIRIN: 250320-A-TI382-1796

Additionally, the contractor inspects the machinery regularly to minimize any leaks from the excavator’s hydraulic lines. The contractor checks the bucket at the beginning and end of each 12-hour shift, as well as once during the shift to mitigate any negative impact to aquatic life.

“We monitor it closely,” Innamorato said.

The dredging contract consists of two dredging crews that have been working six days a week since September. The crews have removed more than 314 barges of material so far, equivalent to 166,000 tons of soil, rocks and debris from the river bottom.
Monongahela Dredging
A U.S. Army Corps of Engineers Pittsburgh District contractor dredges soil, rocks and other materials from the Monongahela River south of Pittsburgh, March 20, 2025. The dredging contract consists of two dredging crews that have been working six days a week since September. The crews have removed more than 314 barges of material so far, equivalent to 166,000 tons of soil, rocks and debris from the river bottom. The contract aims to restore up to ten feet of depth along the Monongahela River in specific shallow areas to allow navigation industries to transport bulk commodities through the region. The dredging work is necessary because the pool level dropped approximately two feet after the Pittsburgh District removed the navigation dam near Elizabeth, Pennsylvania in 2024. The current pool elevation is approximately 724 feet above sea level between the towns of Charleroi and Braddock, Pennsylvania. Elevation figures are based on the North American Vertical Datum of 1988. Eventually, the Pittsburgh District will drop the revel another foot in the pool being dredged. The district has not yet determined a timeline for the final elevation drop. The district is actively assessing the navigation channel and the impact the pool change has on shoreside facilities, navigation industries and other stakeholders. Once the district has completed the necessary dredging and completed its assessments, it will determine when to drop the river level to its final authorized elevation. The final pool elevations will be 723.1 feet. (U.S. Army Corps of Engineers Pittsburgh District photo by Michel Sauret)
Photo By: Michel Sauret
VIRIN: 250320-A-TI382-2696

The contractor performing the work is a company with extensive experience in river dredging and salvage work. The same contractor previously contributed to pier repairs at Montgomery Locks and Dams and performed emergency operations at Dashields Locks and Dams. They are experts in handling floating heavy equipment vital to the project’s success. Their work extends beyond dredging; they also specialize in raising sunken barges, installing massive lock gates, and providing salvage services when extreme weather causes breakaways.

But the contractor does not do it alone. The Pittsburgh District oversees and has planned the dredging efforts since day one.

“Our job is to validate the contractor’s work,” said Baker, whose role involves meticulously time-stamping operations from morning to evening, ensuring compliance with contract specifications. “The contractor has been doing a fantastic job. Outside of Mother Nature’s interruptions, they’ve been nonstop.”

The dredging contract consists of two dredging crews that have been working six days a week since September. The crews have removed more than 314 barges of material so far, equivalent to 166,000 tons of soil, rocks and debris from the river bottom.
Monongahela Dredging
The U.S. Army Corps of Engineers Pittsburgh District contracted a river crew to dredge soil and material from the Monongahela River bottom to restore river depth in certain areas south of Pittsburgh, March 20, 2025. The dredging contract consists of two dredging crews that have been working six days a week since September. The crews have removed more than 314 barges of material so far, equivalent to 166,000 tons of soil, rocks and debris from the river bottom. The contract aims to restore up to ten feet of depth along the Monongahela River in specific shallow areas to allow navigation industries to transport bulk commodities through the region. The dredging work is necessary because the pool level dropped approximately two feet after the Pittsburgh District removed the navigation dam near Elizabeth, Pennsylvania in 2024. The current pool elevation is approximately 724 feet above sea level between the towns of Charleroi and Braddock, Pennsylvania. Elevation figures are based on the North American Vertical Datum of 1988. Eventually, the Pittsburgh District will drop the revel another foot in the pool being dredged. The district has not yet determined a timeline for the final elevation drop. The district is actively assessing the navigation channel and the impact the pool change has on shoreside facilities, navigation industries and other stakeholders. Once the district has completed the necessary dredging and completed its assessments, it will determine when to drop the river level to its final authorized elevation. The final pool elevations will be 723.1 feet. (U.S. Army Corps of Engineers Pittsburgh District photo by Michel Sauret)
Photo By: Michel Sauret
VIRIN: 250320-A-TI382-1213

Beyond excavation, coordination plays a crucial role in the operation. Dredging any river near a populated city requires extreme caution. Before digging begins, crews must identify underwater utilities such as power lines, gas mains and communication cables. In one instance, the contractors discovered a fiber-optic line and a high-pressure gas main within the dredging zone. They formulated a plan to complete the work without causing costly damage to critical infrastructure.

Data management is another crucial component. The Army Corps supplies contractors with detailed files containing extensive latitude, longitude, and depth data to provide their dredging guidance. The contractor’s operators rely on this data to maintain accurate depths while ensuring minimal environmental and industrial impact.

The dredging contract consists of two dredging crews that have been working six days a week since September. The crews have removed more than 314 barges of material so far, equivalent to 166,000 tons of soil, rocks and debris from the river bottom.
Monongahela Dredging
An excavator for a U.S. Army Corps of Engineers Pittsburgh District contractor scoops up dredge material removed from the Monongahela River from a barge onto a dump truck that will transport it to a disposal site south of Pittsburgh, March 20, 2025. The dredging contract consists of two dredging crews that have been working six days a week since September. The crews have removed more than 314 barges of material so far, equivalent to 166,000 tons of soil, rocks and debris from the river bottom. The contract aims to restore up to ten feet of depth along the Monongahela River in specific shallow areas to allow navigation industries to transport bulk commodities through the region. The dredging work is necessary because the pool level dropped approximately two feet after the Pittsburgh District removed the navigation dam near Elizabeth, Pennsylvania in 2024. The current pool elevation is approximately 724 feet above sea level between the towns of Charleroi and Braddock, Pennsylvania. Elevation figures are based on the North American Vertical Datum of 1988. Eventually, the Pittsburgh District will drop the revel another foot in the pool being dredged. The district has not yet determined a timeline for the final elevation drop. The district is actively assessing the navigation channel and the impact the pool change has on shoreside facilities, navigation industries and other stakeholders. Once the district has completed the necessary dredging and completed its assessments, it will determine when to drop the river level to its final authorized elevation. The final pool elevations will be 723.1 feet. (U.S. Army Corps of Engineers Pittsburgh District photo by Michel Sauret)
Photo By: Michel Sauret
VIRIN: 250320-A-TI382-3000

For the crew members, the work is more than just a job – it’s a complex puzzle requiring skill, adaptability, and teamwork. One worker described the daily satisfaction of tackling unique challenges, from maneuvering large rigs around tight river bends to safely relocating oversized debris.

“You never know what you’re going to pull up from the river,” Innamorato said. “We’ve found everything from massive boulders and trees to old sheet piling left over from decades ago.”

The dredging contract consists of two dredging crews that have been working six days a week since September. The crews have removed more than 314 barges of material so far, equivalent to 166,000 tons of soil, rocks and debris from the river bottom.
Monongahela Dredging
The American flag flutters in the wind on the back of a towboat contracted by the U.S. Army Corps of Engineers Pittsburgh District to dredge the Monongahela River south of Pittsburgh, March 20, 2025. The dredging contract consists of two dredging crews that have been working six days a week since September. The crews have removed more than 314 barges of material so far, equivalent to 166,000 tons of soil, rocks and debris from the river bottom. The contract aims to restore up to ten feet of depth along the Monongahela River in specific shallow areas to allow navigation industries to transport bulk commodities through the region. The dredging work is necessary because the pool level dropped approximately two feet after the Pittsburgh District removed the navigation dam near Elizabeth, Pennsylvania in 2024. The current pool elevation is approximately 724 feet above sea level between the towns of Charleroi and Braddock, Pennsylvania. Elevation figures are based on the North American Vertical Datum of 1988. Eventually, the Pittsburgh District will drop the revel another foot in the pool being dredged. The district has not yet determined a timeline for the final elevation drop. The district is actively assessing the navigation channel and the impact the pool change has on shoreside facilities, navigation industries and other stakeholders. Once the district has completed the necessary dredging and completed its assessments, it will determine when to drop the river level to its final authorized elevation. The final pool elevations will be 723.1 feet. (U.S. Army Corps of Engineers Pittsburgh District photo by Michel Sauret)
Photo By: Michel Sauret
VIRIN: 250320-A-TI382-1699

Contractors expect dredging to continue into late spring and possibly summertime. Afterward, the Pittsburgh District will reassess the river’s conditions before deciding on the next steps. Until then, the crews remain focused on their mission: ensuring the Monongahela River remains a navigable and vital artery for commerce, industry, and the communities that rely on it.