We are dedicated to providing strong protection of Alabama's aquatic resources and wetlands by reviewing and approving projects that might impact the state of Alabama. Applications are reviewed on a first come-first served basis with a target response time of 60 days after an application is submitted. Early coordination makes the process easier for you and will help towards a timely authorization. Pre-application meetings are encouraged, particularly for larger projects.
Authorities
- Section 10 of the Rivers & Harbors Act: All work in, over, or under navigable water within Alabama under Nashville District's area of responsibility requires authorization.
- Section 404 of the Clean Water Act: All discharges of dredged or fill material into waters of the U.S. (generally lakes, rivers, streams, wetlands, etc.) require authorization.
Types of Permits
- Nationwide Permits are a series of general permits issued by USACE for minor projects in certain areas. All nationwide permits have special conditions which must be met in order for a project to qualify for nationwide permit status. Some nationwide permits also require pre-construction notification to the Corps prior to the initiation of any activities.
- Regional Permits & Programmatic General Permits are types of general permits as defined in 33 CFR 322.2(f) and 33 CFR 323.2(n). They may be issued by a division or district engineer after compliance with the other procedures of this regulation.
- Individual Permits are required if your project does not fall under the criteria for a general permit or letter of permission. If your project requires an individual permit, the Corps issues a Public Notice advising all interested parties of the proposed activity. This Public Notice process helps the Corps to evaluate the probable impact of the project as part of the public interest review.
Learn more about types of permits.
Tips for a Smooth Process
- Find the Right Office: Regulatory boundaries are drawn by a combination of state, county, and watershed. Pinpoint your project's location with the USACE Regulatory Boundary Map to confirm the correct servicing district.
- Start Early: Contact us during your planning stage BEFORE submitting an application. We can help guide you.
- Pre-Application Meetings: Pre-application meetings are optional, but highly recommended to understand requirements before submitting. Schedule a pre-application meeting.
- Common Mistakes: Double-check your submission to ensure all parts are complete.