The U.S. Army Corps of Engineers, Buffalo District, entered into an agreement in November 2021 with the Village of Lodi to provide $1,075,000 in partial funding assistance toward the Village’s design and construction costs for water system improvements.
A survey of the Bank Street water tower (constructed in the 1930s) showed extensive corrosion on the riser of the tower, and the tank’s components were given a poor rating. The Village proposes to construct a new 200,000-gallon water storage tank on Evergreen Street and to replace the water main, services, valves and hydrants on Janice, Redfield, and Baker Street from the new tank to State Route 83. The preliminary cost estimate for design and construction is $2,637,950.