Click any column header to sort table data.
LRB | Sandusky Harbor Dredging - Channel maintenance dredging | Sandusky (Ohio) | $500K-$1M | 237990 | Small Business Set Aside | MATOC | TO | FY25 Q4 | FY25 Q4 |
LRB | Fairport Dredging - Channel mainenance dredging | Fairport (Ohio) | $1M-$5M | 237990 | Small Business Set Aside | MATOC | TO | FY25 Q2 | FY24 Q3 |
LRB | Cleveland Harbor Dredging - Channel mainenance dredging | Cleveland (Ohio) | $5M-$10M | 237990 | Small Business Set Aside | NA | IFB | FY25 Q2 | FY25 Q2 |
LRB | Ashtabula Harbor Dredging - Channel mainenance dredging | Ashtabula (Ohio) | $1M-$5M | 237990 | Small Business Set Aside | MATOC | TO | FY25 Q3 | FY25 Q3 |
LRB | Buffalo Harbor Dredging - Channel mainenance dredging | Buffalo (New York) | $1M-$5M | 237990 | Small Business Set Aside | MATOC | TO | FY25 Q4 | FY25 Q4 |
LRB | Conneaut Harbor Dredging - Channel mainenance dredging | Conneaut (Ohio) | $1M-$5M | 237990 | Small Business Set Aside | MATOC | TO | FY25 Q2 | FY25 Q3 |
LRB | Rocky River Harbor Dredging - Channel mainenance dredging | Rocky River (Ohio) | $500K-$1M | 237990 | Small Business Set Aside | MATOC | TO | FY25 Q3 | FY25 Q3 |
LRB | Great Sodus/Oak Orchard Harbor Dredging - Channel mainenance dredging | Great Sodus and Oak Orchard (New York) | $500K-$1M | 237990 | Small Business Set Aside | MATOC | TO | FY25 Q2 | FY25 Q4 |
LRB | Lorain Harbor Dredging - Channel mainenance dredging | Lorain (Ohio) | $1M-$5M | 237990 | Small Business Set Aside | MATOC | TO | FY25 Q3 | FY25 Q3 |
LRB | Maumee Bay and River Dredging - Channel mainenance dredging | Toledo(Ohio) | $1M-$5M | 237990 | Small Business Set Aside | SATOC | TO | N/A | FY25 Q3 |
LRB | Oswego Harbor West Arrowhead Breakwater Repair - Repair Breakwater | Oswego (New York) | $5M-$10M | 237990 | Unrestricted | MATOC | TO | FY25 Q2 | FY25 Q3 |
LRB | SLDA Remediation | Parks Township (Pennsylvania) | $250M-$500M | 562910 | Unrestricted | NA | RFP | FY25 Q3 | FY26 Q2 |
LRB | Guterl Remediation | Lockport (New York) | $249M | 562910 | Small Business Set Aside | NA | RFP | FY25 Q2 | FY25 Q4 |
LRB | Big John Salvage River Area | Fairmont (West Virginia) | $25M-$100M | 562910 | Small Business Set Aside | NA | RFP | FY25 Q4 | FY26 Q1 |
LRB | Big John Salvage Upland Area | Fairmont (West Virginia) | $25M-$100M | 562910 | Small Business Set Aside | NA | RFP | FY25 Q4 | FY26 Q1 |
LRB | Erie North Pier Repair | Erie (Pennsylvania) | $1M-$5M | 237990 | Unrestricted | MATOC | TO | FY25 Q3 | FY25 Q4 |
LRB | Boston Mills Ecosystem Restoration | Cleveland (Ohio) | $10M-$25M | 237990 | TBA | NA | IFB | FY25 Q3 | FY25 Q4 |
LRB | Euclid Creek Ecosystem Restoration | Euclid (Ohio) | $1M-$5M | 237990 | TBA | NA | IFB | FY25 Q3 | FY25 Q4 |
LRB | Buffalo CDF Repair | Buffalo (New York) | $10M-$25M | 237990 | Unrestricted | MATOC | TO | FY25 Q2 | FY25 Q2 |
LRB | Barcelona Breakwater Grouting Repair | Barcelona (New York) | $1M-$5M | 237990 | Unrestricted | MATOC | TO | FY25 Q4 | FY25 Q4 |
LRB | West Valley Spillway Repairs | West Valley(New York) | $1M-$5M | 237990 | Unrestricted | NA | RFP | FY25 Q2 | FY25 Q2 |
LRB | USDA Grape Research Facility | Geneva (New York) | $25M-$100M | 237990 | Unrestricted | NA | RFP | FY25 Q2 | FY25 Q3 |
LRC | Replace Windows in Control Tower- Mississinewa Lake- IN | Peru- IN | $50K-100K | TBD | TBD | TBD | TBD | FY25 Q1 | FY25 Q1 |
LRC | Water Treatment - Indiana Harbor and Canal- IN | East Chicago- IN | $5M-$10M | TBD | TBD | TBD | TBD | FY25 Q1 | FY25 Q1 |
LRC | Harbor Channel Maintenance- Big Suamico River- WI | Suamico- WI | $500K-$1M | TBD | TBD | TBD | TBD | FY25 Q2 | FY25 Q3 |
LRC | Shorearm Extension & Eastern Outer Breakwater Repair- Chicago Harbor | Chicago. IL | $5M-$10M | TBD | TBD | TBD | TBD | FY24 Q4 | FY25 Q2 |
LRC | Aquatic Ecosystem Restoration- Honey Creek Sec 206 | Milwaukee- WI | $10M-$25M | TBD | TBD | TBD | TBD | FY26 Q2 | FY26 Q3 |
LRC | Manitowoc North & South Breakwater Repair- Manitowoc Harbor- WI | Manitowoc- WI | $5M-$10M | TBD | TBD | TBD | TBD | FY25 Q4 | FY25 Q4 |
LRC | Water Main Improvements- Cook County Sec 219- Cicero- IL | Cicero- IL | $1M-$5M | TBD | TBD | TBD | TBD | FY25 Q2 | FY25 Q2 |
LRC | Dredging- Indiana Harbor- IN | East Chicago- IN | $1M-$5M | TBD | TBD | TBD | TBD | FY25 Q2 | FY25 Q2 |
LRC | Dam Removal- Horlick Dam- WI- Sec 506 | Racine- WI | $1M-$5M | TBD | TBD | TBD | TBD | FY25 Q4 | FY25 Q4 |
LRC | North Breakwater Repair- Algoma Harbor- WI | Algoma- WI | $10M-$25M | TBD | TBD | TBD | TBD | FY25 Q3 | FY25 Q4 |
LRC | CSSC Electric Dispersial Barrier- IL- Barrier ID Generator Replacement | Lockport- IL | $250K-$500K | TBD | TBD | TBD | TBD | FY25 Q2 | FY25 Q2 |
LRC | CSSC Electric Dispersial Barrier- IL- Barrier I Camera Upgrades | Lockport- IL | $150K-$300K | TBD | TBD | TBD | TBD | FY25 Q1 | FY25 Q2 |
LRC | Herbicide Facility Services- Multiple Locations | Chicago- IL / Lockport- IL | $50K-$100K | TBD | TBD | TBD | TBD | FY25 Q2 | FY25 Q2 |
LRC | Chicago Harbor Lock & Dam- Platform Work Boat Procurement | Chicago- IL | $50K-$100K | TBD | TBD | TBD | TBD | FY25 Q2 | FY25 Q2 |
LRC | T.J.O'Brien Lock and Dam- East/West Embankment Raising | Chicago- IL | $1M-$5M | TBD | TBD | TBD | TBD | FY25 Q4 | FY25 Q4 |
LRC | Herbicide Facility Services- Multiple Locations | IL- IN- WI | TBD | TBD | TBD | TBD | TBD | FY25 Q2 | FY25 Q2 |
LRC | Crane Contract- Multiple Locations | IL- IN- WI | $150K-$300K | TBD | TBD | TBD | TBD | FY25 Q2 | FY25 Q2 |
LRC | General Jones Armory- AE Contract- Design Build | Chicago- IL | $10M-$25M | TBD | TBD | TBD | TBD | FY25 Q3 | FY26 Q1 |
LRC | Kenosha Harbor Sediment Sampling | IL- IN- WI | $100K-$150K | TBD | TBD | TBD | TBD | FY25 Q3 | FY25 Q3 |
LRC | Port Washington Sediment Sampling | IL- IN- WI | $100K-$150K | TBD | TBD | TBD | TBD | FY25 Q3 | FY25 Q3 |
LRC | Michigan City Sediment Sampling | IL- IN- WI | $100K-$150K | TBD | TBD | TBD | TBD | FY25 Q3 | FY25 Q3 |
LRC | Bat Survey- Survey/Sampling | IL- IN- WI | $100K-$150K | TBD | TBD | TBD | TBD | FY25 Q3 | FY25 Q3 |
LRC | CSSC Electric Dispersal Barrier- IL - Lewis Property Demolition | Lockport- IL | $400K-$600K | TBD | TBD | TBD | TBD | FY25 Q2 | FY25 Q2 |
LRC | Kaukauna Right Abutment Repair - Construction and Repair of the right abutment wall adjacent to the Kewaunee Dam | Kewaunee- IL | $1M-$5M | TBD | TBD | TBD | TBD | FY25 Q3 | FY25 Q4 |
LRC | Lake George East Phase II Dredging- Dredging 45-000 to 60-000 CY of material- placement in the CDF | East Chicago- IN | $5M-$10M | TBD | TBD | TBD | TBD | FY25 Q4 | FY26 Q1 |
LRC | Lake George West Sampling - Sediment Sampling | Hammond- IN | $100K-$250K | TBD | TBD | TBD | TBD | TBD | TBD |
LRC | Sheboygan Harbor Sediment Sampling | Sheboyan Harbor- WI | $100K-$250K | TBD | TBD | TBD | TBD | FY25 Q3 | FY26 Q3 |
LRC | Strugeon Bay Dredging- Dredging of 80-000 cubic yards | Sturgeon Bay- WI | $1M-$2M | TBD | TBD | TBD | TBD | FY26 Q2 | FY26 Q3 |
LRC | Section 219- Calumet Region -Sanitary Sewer Project | Chesterton- IN | $1M-$5M | TBD | TBD | TBD | TBD | FY25 Q4 | FY25 Q4 |
LRC | Section 219- Calumet Airport- Gary Airport -
Infrastructure Improvementsfor the Storm Sewer System- sanitary system and a pump station | Gary- IN | $1M-$5M | TBD | TBD | TBD | TBD | FY25 Q4 | FY25 Q4 |
LRC | Section 219- Cook County- Niles- Stormwater Pipeline
Project | Niles- IL | $1M-$5M | TBD | TBD | TBD | TBD | FY25 Q4 | FY25 Q4 |
LRC | Section 219- Cook County- Park Forest- Water Main Project | Park Forest- IL | $1M-$5M | TBD | TBD | TBD | TBD | FY25 Q3 | FY25 Q4 |
LRC | Section 219- Cook County- Flossmoor- Stormwater Pipeline Project | Flossmoor- IL | $1M-$5M | TBD | TBD | TBD | TBD | FY25 Q3 | FY25 Q4 |
LRC | Section 219- Cook County- La Grange- Sanitary Sewer Project | La Grange- IL | $1M-$5M | TBD | TBD | TBD | TBD | FY25 Q4 | FY25 Q4 |
LRC | Section 219- Cook County- Steger- Stormwater Pipeline Project | Steger- IL | $1M-$5M | TBD | TBD | TBD | TBD | FY25 Q4 | FY25 Q4 |
LRC | Section 219- Cook County- Glenview- Infrastructure Improvements Projects | Glenview- IL | $1M-$5M | TBD | TBD | TBD | TBD | FY25 Q3 | FY25 Q3 |
LRC | CAP 206- Dutch Gap AER- Aquatic Ecosystem Restoration- Restoreation of rare and significant aquatic habitats within Lake County. | Antioch- IL | $10M-$15M | TBD | TBD | TBD | TBD | FY25 Q3 | FY25 Q4 |
LRC | Upper Des Plaines River and Tributaries Phase AER- Aquatic Ecosystem Restoration- Pollack Lake and Hastings Creek (Raven Glen) | Antioch- IL | $10M-$25M | TBD | TBD | TBD | TBD | FY25 Q4 | FY25 Q4 |
LRC | Green Bay Harbor Dredging | Green Bay- WI | $2M-$3M | TBD | TBD | TBD | TBD | FY25 Q3 | FY25 Q3 |
LRC | LGB-FR AOC - Spawning and Habitat Reefs - Aquatic Ecosystem Restoration | Green Bay- WI | $5M-$10M | TBD | TBD | TBD | TBD | FY25 Q4 | FY25 Q4 |
LRC | LGB-FR AOC - Longtail Point Habitat Restoration- Aquatic Ecosystem Restoration | Green Bay- WI | $15M-$20M | TBD | TBD | TBD | TBD | FY26 Q4 | FY26 Q4 |
LRC | LGB-FR AOC - De Pere Dam Riverine Wetland Restoration- Aquatic Ecosystem Restoration | De Pere- WI | $20M-$25M | TBD | TBD | TBD | TBD | FY26 Q4 | FY26 Q4 |
LRC | Kaukauna Parcel J Tree Removal | Kaukauna- WI | $100K-$250K | TBD | TBD | TBD | TBD | FY25 Q2 | FY25 Q2 |
LRC | Kaukauna Dry Dock #3- Soil Excavation | Kaukauna- WI | $1M-$5M | TBD | TBD | TBD | TBD | FY26 Q1 | FY26 Q1 |
LRC | Kaukauna Parcel J - Soil Excavation | Kaukauna- WI | $1M-$5M | TBD | TBD | TBD | TBD | FY25 Q4 | FY26 Q1 |
LRC | Kewaunee Dredging | Kewaunee- WI | $1M-$5M | TBD | TBD | TBD | TBD | FY26 Q2 | FY26 Q3 |
LRC | Upper Appleton Wall Repair | Appleton- WI | $5M-$10M | TBD | TBD | TBD | TBD | FY25 Q3 | FY25 Q4 |
LRC | Kewaunee Breakwater Repair- Section C | Kewaunee- WI | $1M-$5M | TBD | TBD | TBD | TBD | FY26 Q2 | FY26 Q2 |
LRC | Kaukauna Dam - Right Abutment Repair | Kaukauna- WI | $1M-$5M | TBD | TBD | TBD | TBD | FY25 Q4 | FY25 Q4 |
LRE | Grand Haven North Pier Wave Attenuator: demolish a section of the harbor's north pier to allow for the construction of a rubble mound wave attenuator. | Grand Haven (Michigan) | Between $5M and $10M | 237990 | Small Business Set Aside | NA | IFB | FY25 Q2 | FY25 Q4 |
LRE | Little Manistee Sea Lamprey Barrier & Trap: Work primarily consists of replacing the concrete spillway structure located north of the Little Manistee Weir. | Manistee (Michigan) | Between $1M and $5M | 237990 | Unrestricted | NA | IFB | FY24 Q2 | FY25 Q3 |
LRE | 15KV Switchgear for the SOO | Sault Ste. Marie (Michigan) | Between $5M and $10M | 238210 | Unrestricted | NA | RFP | FY25 Q2 | FY25 Q3 |
LRE | SOO Duct Bank and Generator: Standby Generator System – construction of new natural gas fueled back-up generator system with removal of existing back-up generators and associated diesel fuel storage and distribution system. | Sault Ste. Marie (Michigan) | Between $10M and $25M | 236220 | Unrestricted | NA | RFP | FY25 Q2 | FY25 Q3/Q4 |
LRE | Sault Material Storage Fac and Site Improvements
Complex. | Sault Ste. Marie (Michigan) | Between $5M and $10M | 237990 | Unrestricted | Task Order off Disgn-Build MAOC (W912P523D0001-W912P523D0007 | RFP | FY25 Q2 | FY25 Q3 |
LRE | Sebewaing River South Levee Repairs | Sebewaing (Michigan) | Between $10-000-000 and $25-000-000 | 237990 | Small Business Set Aside | N/A | IFB | FY25 Q2 | FY25 Q3 |
LRE | SPO Fleet Dry Dock Inspections- Repairs | Sault Ste Marie (Michigan) | $1M and $5M | 336611 | 8(a) | 8(a) | RFP | FY25 Q1 | FY25 Q2 |
LRE | Window Cleaning at the Sault Project Office | Sault Ste Marie (Michigan) | TBD | TBD | TBD | N/A | RFP | FY25 Q2 | FY25 Q3 |
LRE | Lansing 219 Sewer Separation: provide infrastructure work to eliminate combined sewer overflows via construction of a new- dedicated sanitary sewer and rehabilitation of existing combined sewer into a dedicated storm sewer. | Lansing (Michigan) | Between $5-000-000 and $10-000-000 | 237110 | Full and Open | N/A | IFB | FY25 Q3 | FY26 Q1 |
LRE | SPO Non-Destructive Weld Testing Master BPA | Sault Ste Marie (Michigan) | TBD | 541380 | Small Business Set Aside | N/A | RFP | FY25 Q2 | FY25 Q2/Q3 |
LRE | GE Vernova Parts | Sault Ste Marie (Michigan) | | 811310 | Sole Source | N/A | RFQ | FY25 Q2 | FY25 Q2/Q3 |
LRE | ESS Upgrade: The U.S. Army Corps of Engineers (USACE) is seeking to establish a contract with the purpose of upgrading existing CCURE and Software House Security Access Control hardware. | Sault Ste Marie (Michigan) | Between $100-000 and $250-000 | TBD | Sole Source | N/A | RFP | FY25 Q1/Q2 | FY25 Q2/Q3 |
LRE | Arcadia Harbor MD | (Michigan) | $1M and $5M | 237990 | Small Business Set Aside | Task Order off MD MATOC (W911XK21D0001 - W911XK21D0008) | RFP | FY25 Q2/Q3 | FY25 Q3 |
LRE | New Buffalo Harbor MD | (Michigan) | $1M and $5M | 237990 | Small Business Set Aside | Task Order off MD MATOC (W911XK21D0001 - W911XK21D0008) | RFP | FY25 Q2/Q3 | FY25 Q3 |
LRE | Great Lakes Dredging MATOC: Establishing a new MD MATOC | within LRE | | 237990 | TBD | N/A | RFP | FY25 Q1/Q2 | FY25 Q2/Q3 |
LRE | Water Street CSO: Develop RTA construction documents for
the redesign and construction of the combined sewer overflow system. | Sault Ste. Marie (Michigan) | TBD | 541330 | Small Business Set Aside | Task Order off of LRE A-E Planning and Design Service IDIQs- Contracts Nos W911XK22D0001- W911XK22D0002- and W911XK22D0003 | RFP | FY24 Q4 | FY25 Q2/Q3 |
LRE | Clinton River Microbial Source Tracking: conduct analyses to determine where E. coli is present in the Clinton River Area | Clinton River Area located in Macomb and Oakland Counties (Michigan) | $100-000 to $500-000 | 541380 | TBD | TBD | TBD | FY25 Q1 | FY25 Q2/Q3 |
LRE | St Mary's Pier Inspection AE: Contract for Inspection and Assessment of Soo Locks Piers. | Sault Ste. Marie (Michigan) | TBD | 541330 | Small Business Set Aside | Task Order off of LRE A-E Planning and Design Service IDIQs- Contracts Nos W911XK22D0001- W911XK22D0002- and W911XK22D0003 | RFP | FY25 Q1/Q2 | FY25 Q2 |
LRE | Lane Street Remedial Design - A-E Design Services for Lane Street Superfund Project includes pilot study and design. | Elkhart (Indiana) | Between $500-000 and $1-000-000 | 541330 | Unrestricted | Task order off LRL A-E Environmental – Unrestricted IDIQs-
Contract Nos. W912QR23D0001 through W912QR23D0005 | RFP | FY25 Q1 | FY25 Q2 |
LRE | Toumey Nursery Design Develop RTA construction
documents for construction of a new growing and processing facility at the J.W. Toumey Nursery | Watersmeet (Michigan) | $1M and $5M | 541330 | Small Business Set Aside | Task order off LRD IIJA Unrestricted A-E IDIQs
under Contract Nos. W912QR23D0041 through W912QR23D0047 | RFP | FY25 Q1 | FY25 Q2/Q3 |
LRE | FY25 Monroe Harbor MD and CDF Maintenance | (Michigan) | $1M and $5M | 237990 | Small Business Set Aside | TBD | IFB | FY25 Q2/Q3 | FY25 Q3/Q4 |
LRE | Crib Dam Stabilization | (Michigan) | TBD | TBD | TBD | TBD | TBD | FY25 Q1/Q2 | FY25 Q3/Q4 |
LRE | FY24 Drone Detection System: provide supplies for a drone detection system | Sault Ste Marie (Michigan) | $100-000 to $500-000 | TBD | Small Business Set Aside | TBD | TBD | FY25 Q2/Q3 | FY25 Q2/Q3 |
LRE | O&M Leland and Portage Lake Harbors MD | (Michigan) | $1M and $5M | 237990 | TBD | TBD | TBD | FY25 Q1/Q2 | FY25 Q2/Q3 |
LRE | Duluth Vessel Yard Phase II QA Testing | Duluth (Minnesota) | TBD | 541330 | TBD | TBD | TBD | FY25 Q2/Q3 | FY25 Q2 |
LRE | Duluth Ship Canal QA Testing on Concrete | Duluth (Minnesota) | TBD | 541330 | TBD | TBD | TBD | FY25 Q1/Q2 | FY25 Q2/Q3 |
LRE | FY23 Inland Route Restroom Addition: Prefabricated restroom structure placed on existing concrete pad and sewage line to municipal main | | TBD | TBD | Small Business Set Aside | N/A | IFB | FY25 Q1/Q2 | FY25 Q2 |
LRE | Lexington Breakwater Repair | Lexington (Michigan) | $5M and $8 | | Small Business Set Aside | N/A | IFB | FY26 Q1 | FY26 Q2 |
LRE | Soo Crib Dam Stabalization: Construction to stabilize the Soo Crib Dam. Anticipated design to include a hybrid SSP wall along the length of the crib dam (to be constructed mainly from water- support from land) and mix of reconstruction/grouting at the east and west tie-ins (with coffer dam(s) at the tie-in areas). | Sault Ste Marie (Michigan) | $10M and $15 | TBD | Unrestricted | N/A | BVTO | FY25 Q3/Q4 | FY25 Q4 |
LRE | FY25 Holland Inner MD | Holland (Michigan) | $1M and $2M | 237990 | Small Business Set Aside | N/A | IFB | FY25 Q3/Q4 | FY25 Q4 |
LRE | Duluth Superior MD | Duluth (Minnesota) | $5M and $8 | 237990 | Unrestricted | N/A | IFB | FY25 Q3/Q4 | FY25 Q4 |
LRE | Erie Pier CDF Material Removal | Duluth (Minnesota) | $1M and $5M | | Small Business Set Aside | N/A | RFP | FY25 Q3/Q4 | FY25 Q4 |
LRE | FY25 Manistique Harbor MD | Manistique (Michigan) | $1M and $5M | 237990 | Small Business Set Aside | N/A | IFB | FY25 Q3/Q4 | FY25 Q4 |
LRE | FY25 Holland Inner MD | Holland (Michigan) | $1M and $5M | 237990 | Small Business Set Aside | N/A | IFB | FY25 Q3/Q4 | FY25 Q4 |
LRE | FY23 Saginaw River CDF Dike Raising | Saginaw (Michigan) | $500-000 and $1-000-000 | 237990 | Small Business Set Aside | N/A | IFB | FY25 Q3/Q4 | FY25 Q4 |
LRE | FY25 Monroe Harbor M/D & CDF Maintenance | Monroe (Michigan) | $1M and $5M | 237990 | Small Business Set Aside | N/A | IFB | FY25 Q3/Q4 | FY25 Q4 |
LRE | Ashland- Bayfield- La Pointe Harbor Sediment Sampling | Wisconsin | $250-000 and $500-000 | 541620 | Small Business Set Aside | Task Order off of LRE Environmental Services MATOC | RFP | FY25 Q2/Q3 | FY25 Q3 |
LRE | North Lansing Dam Sediment Sampling and Survey | Michigan | TBD | 541620 | 8(a) | Task Order off of LRE (8a) Environmental Services MATOC | RFP | TBD | TBD |
LRE | Keweenaw Waterway and Eagle Harbor Sediment Sampling | Michigan | $200-000 and $500-000 | 541620 | Small Business Set Aside | Task Order off of LRE Environmental Services MATOC | RFP | FY25 Q2/Q3 | FY25 Q3 |
LRE | Manistique Harbor Sediment Sampling | Michigan | $200-000 and $500-000 | 541620 | Small Business Set Aside | Task Order off of LRE Environmental Services MATOC | RFP | FY25 Q2/Q3 | FY25 Q3 |
LRE | Port Austin Harbor Sediment Sampling | Michigan | $100-000 and $300-000 | 54120 | Small Business Set Aside | Task Order off of LRE Environmental Services MATOC | RFP | FY25 Q2/Q3 | FY25 Q3 |
LRE | Channels of Lake St. Clair Sediment Sampling | Michigan | $200-000 and $500-000 | 54120 | Small Business Set Aside | Task Order off of LRE Environmental Services MATOC | RFP | FY25 Q2/Q3 | FY25 Q3 |
LRE | Point Lookout & Tawas Bay Harbor Sediment Sampling and Analysis | Michigan | $250-000 and $500-000 | 54120 | Small Business Set Aside | Task Order off of LRE Environmental Services MATOC | RFP | FY25 Q2/Q3 | FY25 Q3 |
LRE | St. Clair River Harbor Sediment Sampling | Michigan | TBD | 54120 | Small Business Set Aside | Task Order off of LRE Environmental Services MATOC | RFP | TBD | TBD |
LRE | Cedar River Harbor Sediment Sampling | Michigan | TBD | 54120 | 8(a) | Task Order off of LRE (8a) Environmental Services MATOC | RFP | TBD | TBD |
LRE | Au Sable Harbor Sediment Sampling | Michigan | TBD | 54120 | 8(a) | Task Order off of LRE (8a) Environmental Services MATOC | RFP | TBD | TBD |
LRE | Harrisville Harbor Sediment Sampling | Michigan | TBD | 54120 | 8(a) | Task Order off of LRE (8a) Environmental Services MATOC | RFP | TBD | TBD |
LRE | Detour Harbor Sediment Sampling | Michigan | TBD | 54120 | 8(a) | Task Order off of LRE (8a) Environmental Services MATOC | RFP | TBD | TBD |
LRE | Pine River Harbor Sediment Sampling | Michigan | TBD | 54120 | 8(a) | Task Order off of LRE (8a) Environmental Services MATOC | RFP | TBD | TBD |
LRE | Two Harbors Harbor Sediment Sampling | Minnesota | TBD | 54120 | 8(a) | Task Order off of LRE (8a) Environmental Services MATOC | RFP | TBD | TBD |
LRE | Tallis Bay Sediment Sampling and Benchscale testing | Minnesota | TBD | 54120 | 8(a) | Task Order off of LRE (8a) Environmental Services MATOC | RFP | TBD | TBD |
LRE | Elijah Root Dam Sediment Sampling and Archeologic Survey | Michigan | TBD | 54120 | 8(a) | Task Order off of LRE (8a) Environmental Services MATOC | RFP | TBD | TBD |
LRE | Clinton River Confined Disposal Facility (CDF) Sampling and Analysis | Michigan | TBD | 54120 | Small Business Set Aside | Task Order off of LRE Environmental Services MATOC | RFP | TBD | TBD |
LRE | Point Mouillee CDF Sampling and Analysis | Michigan | TBD | 54120 | Small Business Set Aside | Task Order off of LRE Environmental Services MATOC | RFP | TBD | TBD |
LRE | Les Cheneaux and Hammond Bay Harbor Sampling/Survey | Michigan | TBD | 54120 | Small Business Set Aside | Task Order off of LRE Environmental Services MATOC | RFP | TBD | TBD |
LRE | St. Joseph (Inner) Sediment Sampling | Michigan | TBD | 54120 | Small Business Set Aside | Task Order off of LRE Environmental Services MATOC | RFP | TBD | TBD |
LRE | Pointe Mouille Confined Disposal Facility (CDF) Sediment Sampling | Michigan | TBD | 54120 | Small Business Set Aside | Task Order off of LRE Environmental Services MATOC | RFP | TBD | TBD |
LRE | Detroit River Sediment Sampling | Michigan | TBD | 54120 | Small Business Set Aside | Task Order off of LRE Environmental Services MATOC | RFP | TBD | TBD |
LRH | Repair Pound River Sewage Service | John W. Flannagan Dam VA | Between $25K and $100K | 221320 | SBSA | | | Q12025 | Q22025 |
LRH | Replace Workshop/Garage | Tappan Lake OH | Between $100K and $500K | 236220 | SBSA | SAP | | TBD | TBD |
LRH | Hazmat Building | Bluestone Dam WV | Between $100K and $500K | 236220 | SBSA | SAP | | Q22025 | Q22025 |
LRH | Shelter Replacement | Alum Creek Dam OH | Between $100K and $500K | 236220 | SBSA | SAP | | Q12025 | Q12025 |
LRH | Guardrail Replacement | Delaware Lake OH | Between $100K and $500K | 237310 | SBSA | SAP | | TBD | TBD |
LRH | Paving IDIQ(s) | Huntington District | NTE $3M | 237310 | TBD | MATOC | IDIQ | Q32025 | Q42025 |
LRH | Intake Structure and Dam Rehab | Fishtrap Lake KY | Between $1M and $5M | 237990 | SBSA | IFB | | Q12025 | Q12025 |
LRH | Repair Spalling Concrete on Tainter Gate Abutments | Fishtrap Lake KY | Between $500K and $1M | 237990 | SBSA | IFB | | Q22025 | Q22025 |
LRH | Shutters on Main Chambers for Meldahl and Greenup Dams | Felicity OH and Greenup KY | Between $100K and $500K | 237990 | SBSA | TBD | | TBD | TBD |
LRH | Gantry Crane Replacement | Dillon Lake OH | Between $500K and $1M | 237990 | TBD | IIJA MATOC | Task Order | Q12025 | Q22025 |
LRH | Intake Structure and Dam Rehab | Fishtrap Lake KY | Between $1M and $5M | 237990 | SBSA | IFB | | Q12025 | Q22025 |
LRH | Repair Spalling Concrete on Tainter Gate Abutments - Machinery Platform | Fishtrap Lake KY | Between $500K and $1M | 237990 | SBSA | IFB | | Q12025 | Q22025 |
LRH | Replace Lower Twin Campground Road Bridge | John W. Flannagan Dam VA | Between $500K and $1M | 237990 | TBD | LRD DB MATOC | Task Order | Q12025 | Q22025 |
LRH | Rip rap addition to upstream face of dike | Paint Creek Lake OH | Between $1M and $5M | 237990 | SBSA | IFB | | Q12025 | Q12025 |
LRH | Big Sandy Dredge | KY | Between $1M and $5M | 237990 | TBD | | | Q32025 | Q32025 |
LRH | Ohio River Open Channel Dredge | Ohio River | Between $1M and $5M | 237990 | TBD | | | Q32025 | Q32025 |
LRH | Replace Motor Control Center | Grayson Lake KY | | 335314 | SBSA | TBD | | Q22025 | Q22025 |
LRH | Concrete spalling repair | Delaware Lake OH | Between $100K and $500K | 237990 | SBSA | SB MATOC | Task Order | Q12025 | Q12025 |
LRH | Concrete Spalling Repair | Tom Jenkins Dam OH | Between $100K and $500K | 237990 | SBSA | SB MATOC | Task Order | Q12025 | Q12025 |
LRH | Repair Sinkhole and Downstream Bank Erosion | Fishtrap Lake KY | Between $1M and $5M | 237990 | SBSA | SB MATOC | Task Order | Q22025 | Q32025 |
LRH | Kanawha River Dredge | Kanawha River WV | <$25K | 237990 | TBD | | | Q32025 | Q32025 |
LRH | Replace Greenfield Levee relief wells | Paint Creek Lake OH | <$25K | 237990 | TBD | | | Q32025 | Q32025 |
LRH | Spring Dredging | District | Between $100K and $500K | 237990 | TBD | MATOC | Task Order | Q32025 | Q32025 |
LRH | Channel Bank Repair | Roseville OH | Between $100K and $500K | 237990 | SBSA | SB MATOC | Task Order | Q12025 | Q12025 |
LRH | Motor Control Center (MCC) Replacement | Burnsville Lake WV | | 335314 | SBSA | BPA Call | | Q12025 | Q12025 |
LRH | Replace Emergency Generator | Yatesville Lake KY | Between $500K and $1M | 237990 | SBSA | SB MATOC | Task Order | Q12025 | Q22025 |
LRH | Magnolia pump station tuck & point | Bolivar Dam OH | Between $25K and $100K | 238140 | SBSA | SAP | | Q32025 | Q32025 |
LRH | LCF CROC Roof Repair | R3F Regional | Between $100K and $500K | 238160 | SBSA | SAP | | Q12025 | Q12025 |
LRH | Brewster Electric Rehab | Beach City OH | Between $25K and $100K | 238210 | SBSA | SAP | | Q12025 | Q22025 |
LRH | Upgrade Incoming Power (Feeder and MCC) | Willow Island Lock and Dam OH | Between $500K and $1M | 238210 | SBSA | TBD | | Q42025 | Q42025 |
LRH | Fencing Replacement | Clendening Dam OH | Between $100K and $500K | 238990 | SBSA | TBD | | TBD | TBD |
LRH | LCF Office Trailers | R3F Regional | | 321991 | SBSA | TBD | | Q12025 | Q12025 |
LRH | Stone Supply | Summersville Dam WV | | 327991 | SBSA | SAP | | TBD | TBD |
LRH | Cheatham Gate & Valve Rehab - Steel BPA Call | Marietta Repair Station OH | | 331110 | SBSA | BPA Call | | Q12025 | Q22025 |
LRH | HCF Steel Material BPA - Gate Lift System | R3F Regional | | 331110 | SBSA | BPA Call | | Q12025 | Q22025 |
LRH | Replace Low Flow Gate (Knife Valve) | East Lynn Lake WV | | 332312 | SBSA | TBD | | Q22025 | Q32025 |
LRH | U-Bolt Fabrication | Capt. Anthony Meldahl L&D OH | | 332312 | SBSA | | | Q12025 | Q12025 |
LRH | Fabricate four Culvert Valve Bulkheads | Capt. Anthony Meldahl L&D OH | | 332312 | SBSA | MATOC | Task Order | Q12025 | Q12025 |
LRH | Dam Bulkhead Replacement | R.C. Byrd Locks and Dam WV | | 332313 | SBSA | MATOC | Task Order | Q22025 | Q22025 |
LRH | C2 Scaffolding BPA | R3F Regional | | 332323 | SBSA | BPA Call | | Q12025 | Q22025 |
LRH | MCF Boiler Replacement | R3F Regional | | 332410 | SBSA | SAP | | TBD | TBD |
LRH | Original Wire replacement | Winfield Locks and Dam WV | | 332618 | SBSA | RFP | | Q12025 | Q22025 |
LRH | Sandblasting & Painting Gathrite Gates | Marietta Repair Station OH | | 332813 | SBSA | BPA Call | | Q12025 | Q12025 |
LRH | C2 Machining/Water Jet Material Services BPA (New Pool) | R3F Regional | | 333515 | SBSA | New BPA | | Q12025 | Q12025 |
LRH | Supersaw | Bluestone Dam WV | | 333515 | SBSA | SAP | | Q22025 | Q22025 |
LRH | LCF 250KW Generator Set LCF & MCF | R3F Regional | | 333611 | SBSA | SAP | | Q12025 | Q12025 |
LRH | Office Generator | John W. Flannagan Dam VA | | 333611 | SBSA | | | Q12025 | Q22025 |
LRH | LCF MRS & HCF 30 ft Gooseneck Trailer | R3F Regional | | 333924 | SBSA | SAP | | TBD | TBD |
LRH | Altoona Hydraulic Cylinder Material | Marietta Repair Station OH | | 333995 | SBSA | BPA Call | | Q12025 | Q12025 |
LRH | LCF Submersible pump 95 HP | R3F Regional | | 333996 | SBSA | SAP | | Q12025 | Q12025 |
LRH | MCF Evanick & Service Barge 101 Dry Dock | R3F Regional | | 336611 | SBSA | SAP | | Q12025 | Q12025 |
LRH | LCF Man Baskets - safety equipment BPA | R3F Regional | | 532412 | SBSA | BPA Call | | TBD | TBD |
LRH | LCF Man Baskets for Crane | R3F Regional | | 532412 | SBSA | BPA Call | | TBD | TBD |
LRH | Savannah Bluff Crane Rental | Marietta Repair Station OH | | 532412 | SBSA | On Hold | | On Hold | On Hold |
LRH | Nat'l Nuclear Security Admin Production Modernization (NA-19) FY25 | DOE | | 541330 | Unrestricted | SATOC | Task Order | Q32025 | Q32025 |
LRH | Prado Dam Engineering During Construction | Corona CA | | 541330 | Unrestricted | MATOC | Task Order | TBD | Q42025 |
LRH | RDLP Con 1 Engineering During Construction by designer of record. | | | 541330 | SBSA | SAA MATOC | Task Order | Q22025 | Q32025 |
LRH | Dam Safety Emergency Action Plan | Bluestone Dam WV | | 541330 | Unrestricted | LB MATOC | Task Order | Q22025 | Q42025 |
LRH | Dam Safety Mngt Center Geotechnical Services | USACE | NTE $45M | 541330 | Unrestricted | | New IDIQ | Q12025 | Q22025 |
LRH | Materials Explorations and Testing | Garrison Dam | | 541330 | Unrestricted | LB SATOC | Task Order | Q12025 | Q22025 |
LRH | SRS Nuclear Materials Stabilization Safety Support CY25 | SC | | 541330 | Unrestricted | SATOC | Task Order | Q12025 | Q12025 |
LRH | Dam Safety Design MATOC (New) | USACE | NTE $20M | 541330 | SBSA | New MATOC | IDIQ | Q22025 | Q22025 |
LRH | Ohio River Mussel Survey | Ohio River | | 541330 | SBSA | SATOC | Task Order | Q32025 | Q32025 |
LRH | Kanawha River Mussel Survey and Biological Assessment | Kanawha River WV | | 541330 | SBSA | SATOC | Task Order | Q32025 | Q32025 |
LRH | Ph. IV Geotechnical Explorations & Testing | Guajataca | | 541330 | Unrestricted | SATOC | Task Order | Q12026 | Q12026 |
LRH | Safety Assurance Review | Guajataca | | 541330 | Unrestricted | SATOC | Task Order | 2Q2026 | 2Q2026 |
LRH | C2 Fire Supression Inspection BPA | R3F Regional | | 541990 | SBSA | New BPA | | Q12025 | Q12025 |
LRH | Intake Scructure Security System | Fishtrap Lake KY | Between $1M and $5M | 237990 | SBSA | IFB | | TBD | TBD |
LRH | Security Cameras | Upper Tuscarawas Area OH | | 561621 | SBSA | TBD | | TBD | TBD |
LRH | Security Cameras | Lower Tuscarawas Area OH | | 561621 | SBSA | TBD | | TBD | TBD |
LRH | Office Security System | Summersville Dam WV | | 561621 | SBSA | TBD | | Q12025 | Q12025 |
LRH | Cleaning 2026 - 2030 | Summersville Dam WV | | 561720 | SBSA | SAP | | Q12025 | Q12025 |
LRH | Cleaning 2026 - 2030 | Sutton Lake WV | | 561720 | SBSA | SAP | | Q22025 | Q32025 |
LRH | Cleaning & Mowing Services Contract | Marietta Repair Station OH | | 561730 | SBSA | SAP | | Q12025 | Q12025 |
LRH | Herbicide Services Contract | Scioto Area Office Mt. Sterling OH | | 561730 | SBSA | RFQ | | Q22025 | Q22025 |
LRH | Herbicide Services Contract | Summersville Dam WV | | 561730 | SBSA | RFQ | | Q12025 | Q12025 |
LRH | Park Attendant 2025 - 2029 | Burnsville Lake WV | | 561730 | SBSA | RFQ | | Q22025 | Q22025 |
LRH | Maintenance Service 2025 - 2029 | Beech Fork Lake WV | | 561730 | SBSA | RFQ | | Q42024 | Q12025 |
LRH | Maintenance Service 2025 - 2029 | Fishtrap Lake KY | NTE $2.5M | 561730 | SBSA | RFQ | | Q12025 | Q22025 |
LRH | Maintenance Service 2025 - 2029 | Grayson Lake KY | | 561730 | SBSA | RFQ | | Q12025 | Q12025 |
LRH | Maintenance Service 2025 - 2029 | Beach City and Bolivar Dam OH | | 561730 | SBSA | RFQ | | Q12025 | Q12025 |
LRH | Maintenance Service 2026 - 2030 | Lower Tuscarawas Area OH | | 561730 | SBSA | RFQ | | Q32025 | Q42025 |
LRH | Mowing & Maintenance 2026 - 2030 | Delaware Lake OH | | 561730 | SBSA | RFQ | | Q32025 | Q42025 |
LRH | Mowing & Maintenance 2026 - 2030 | Paint Creek Lake OH | | 561730 | SBSA | RFQ | | Q32025 | Q42025 |
LRH | Mowing & Maintenance 2026 - 2030 | Pikeville Lake KY | | 561730 | SBSA | RFQ | | Q32025 | Q42025 |
LRH | Mowing and Maintenance 2026 - 2031 | Alum Creek Dam OH | | 561730 | SBSA | RFQ | | Q32025 | Q42025 |
LRH | MCF Waste Call | R3F Regional | | 562111 | TBD | BPA Call | | TBD | TBD |
LRH | HCF Waste Removal | R3F Regional | | 562111 | TBD | BPA Call | | TBD | TBD |
LRH | C2 Waste Removal BPA Call (MRS) - Waterjet | R3F Regional | | 562111 | TBD | BPA Call | | Q32025 | Q32025 |
LRH | HCF LRS Hazardous Waste Removal | R3F Regional | | 562112 | TBD | BPA Call | | TBD | TBD |
LRH | Park Attendant 2025 - 2029 | East Lynn Lake WV | | 721211 | SBSA | RFQ | | Q22025 | Q22025 |
LRH | Park Attendant - 2025 - 2029 | John W. Flannagan Dam VA | | 721211 | SBSA | RFQ | | Q12025 | Q12025 |
LRH | MCF Crane Inspection | R3F Regional | | 811300 | TBD | BPA Call | | TBD | TBD |
LRH | MCF New Vendor Pressure Vessel Inspection - NDT Tanknicians L.L.C. | R3F Regional | | 811300 | TBD | BPA | | TBD | TBD |
LRH | MCF Pressure Vessel Inspection | R3F Regional | | 811300 | TBD | BPA Call | | TBD | TBD |
LRH | C2 New Lathe Machine Repair & Supply BPA Vendor - Plant Service Company | R3F Regional | | 811310 | TBD | BPA | | TBD | TBD |
LRH | C2 Pump Repair and Inspection BPAs | R3F Regional | | 811310 | TBD | BPA | | TBD | TBD |
LRH | HCF 10 in Submersible Pump Repair | R3F Regional | | 811310 | TBD | SAP | | TBD | TBD |
LRH | HCF Fire Safety Repairs | R3F Regional | | 811310 | TBD | SAP | | TBD | TBD |
LRH | LCF Submersible Pump Repairs 200 HP | R3F Regional | | 811310 | TBD | SAP | | TBD | TBD |
LRH | MCF 3406 Engine Rebuild - CAT BPA | R3F Regional | | 811310 | TBD | BPA Call | | TBD | TBD |
LRH | Nickajack Cylinder Rebuild | Marietta Repair Station OH | | 811310 | TBD | BPA Call | | TBD | TBD |
LRH | Elevator Service | Bluestone Dam WV | | 811310 | TBD | | | Q42024 | Q42024 |
LRH | C2 New BPA Pool - Dive equipment- purchase- service- & inspection | R3F Regional | | | TBD | BPA | | TBD | TBD |
LRH | Materials for Selective Withdrawal Panel | Atwood Lake OH | | | TBD | | | Q22025 | Q32025 |
LRH | Monument Rehab | Muskingam River Area OH | Between $25K and $100K | 238990 | SBSA | RFQ | | Q22025 | Q32025 |
LRH | Replace Maintenance Garage | Dover Dam OH | Between $100K and $500K | 236220 | SBSA | | | Q12025 | Q12025 |
LRH | Roller Gate Storage area | Winfield Locks and Dam WV | TBD | | TBD | | | TBD | TBD |
LRH | Sommerdale Flagging Services - BPA Call | Dover Dam OH | | | TBD | BPA Call | | Q22025 | Q22025 |
LRH | Water Tower Security Fence | Burnsville Lake WV | | | SBSA | | | Q22025 | Q22025 |
LRH | Task Order Cleaning Services FY25 | Burnsville Lake WV | | 561720 | SBSA | | | Q12025 | Q12025 |
LRH | Task Order Negotiated Work | Summersville Dam WV | | 561730 | TBD | | | Q12025 | Q12025 |
LRH | Task Order Sewage/Sludge Service FY25 | Burnsville Lake WV | | 561730 | SBSA | | | Q12025 | Q12025 |
LRH | Trash/Debris Boom | Burnsville Lake WV | | 326199 | SBSA | | | Q32025 | Q32025 |
LRH | Pontoon Dock | Burnsville Lake WV | | | SBSA | | | Q42025 | Q42025 |
LRH | Prado Engineering During Construction | Corona CA | | 541330 | Unrestricted | LB MATOC | Task Order | Q32025 | Q42025 |
LRH | Prefab Building | Marietta Repair Station OH | | | SBSA | SAP | | Q22025 | Q22025 |
LRH | Sewer Sludge Disposal | Sutton Lake WV | | 562111 | TBD | | | Q22025 | Q22025 |
LRH | Playground Material | Burnsville Lake WV | | | SBSA | | | Q42025 | Q42025 |
LRH | Task Order Dumpster Services | Summersville Dam WV | | | SBSA | | Task Order | Q12025 | Q12025 |
LRH | Task Order Cleaning Services FY25 | Summersville Dam WV | | 561720 | SBSA | | Task Order | Q12025 | Q12025 |
LRH | Task Order Dumpster Services FY25 | Burnsville Lake WV | | | SBSA | | Task Order | Q12025 | Q12025 |
LRH | Task Order Mowing FY25 | Summersville Dam WV | | 561730 | SBSA | | Task Order | Q12025 | Q12025 |
LRH | Task Order Mowing Services FY 25 | Burnsville Lake WV | | 561730 | SBSA | | Task Order | Q12025 | Q12025 |
LRH | Task Order Park Attendant FY25 | Summersville Dam WV | | 721211 | SBSA | | Task Order | Q12025 | Q12025 |
LRH | Task Order Park Attendant FY25 | Burnsville Lake WV | | 721211 | SBSA | | Task Order | Q22025 | Q22025 |
LRH | Waterway Signage | Capt. Anthony Meldahl L&D OH | | | SBSA | | | Q12025 | Q12025 |
LRH | London Pierhouse Roofing | London Locks and Dam WV | Between $1M and $5M | 238160 | SBSA | SB MATOC | Task Order | Q12025 | Q22025 |
LRH | Lower Mud River FRM Project | Milton WV | TBD | 237990 | Unrestricted | TBD | TBD | Q12026 | Q42026 |
LRH | Marmet Service Bridge and Pier 3 Rehab | Marmet Locks and Dam WV | Between $5M and $10M | 237990 | SBSA | IFB | | 1Q2025 | 2Q2025 |
LRH | Flap Gate #6 & Roller Gate Fabrication | Winfield Locks and Dam WV | | 332312 | Unrestricted | | | 1Q2025 | 2Q2025 |
LRH | Miter Gate | Greenup Locks and Dam KY | | 332312 | SBSA | | | Q12025 | Q22025 |
LRH | Replace US & DS Dogging Beam | Capt. Anthony Meldahl L&D OH | | 331221 | SBSA | | | Q12025 | Q22025 |
LRH | Relief Well Engineering A/E | Huntington District | | 541330 | SBSA | | | Q12025 | Q32025 |
LRH | Limited GeoTech A/E | Huntington District | NTE $45M | 541330 | Unrestricted | New SATOC | IDIQ | Q12025 | Q32025 |
LRH | Engineering & Construction Services A/E | Huntington District | TBD | 541330 | Unrestricted | New SATOC | IDIQ | Q32025 | Q22026 |
LRH | Inland Nav/Planning Services A/E | Huntington District | NTE $15M | 541330 | SBSA | New SATOC | IDIQ | Q32025 | Q22026 |
LRH | Dam Safety Design A/E | Huntington District | NTE $20M (shared) | 541330 | SBSA | New MATOC | IDIQ | Q22025 | Q42025 |
LRH | HTRW A/E | Huntington District | NTE $3M | 541330 | SBSA | New SATOC | IDIQ | Q22026 | Q42026 |
LRH | Cranesnest Access Road Paving | John W. Flannagan Dam VA | Between $500K and $1M | 237310 | SBSA | IFB | | Q32025 | Q32025 |
LRH | Pound River Access Road Paving | John W. Flannagan Dam VA | Between $1M and $5M | 237990 | SBSA | SB MATOC | Task Order | Q12025 | Q22025 |
LRL | Renovate Aircrew Readiness Facility / BAEY234305CB Aircrew Readiness Facility | Beale AFB (California) | Between $5M and $10M | 236220 | Small Business Set Aside | IFB | AE Design Bid Build | FY25 Q3 | FY25 Q4 |
LRL | Preservation of The Force & Family (POTFF) | Davis Monthan Air Force Base (Arizona) | Between $5M - $10M | 236220 | Small Business Set Aside | N/A | AE Design Bid Build | FY25 Q2 | FY25 Q3 |
LRL | Add Repair Component Medical Training Facility B3120 | Eglin AFB (Florida) | Between $1M and $5M | 236220 | Small Business Set Aside | SE MATOC | AE Design Bid Build | FY25 Q2 | FY25 Q3 |
LRL | Indoor Small Arms Range | Grissom Air Force Base (Indiana) | Between $25M and $100M | 236220 | Unrestricted | N/A | AE Design Bid Build | FY25 Q1 | FY25 Q3 |
LRL | KC-46 Two-Bay Maintenance/Fuel Cell Hangar and Add/Alt Bldg 1244 FUT/Cargo Pallet Staging / Repair Ramp Mooring Points | March Air Force Base (California) | Between $100M and $250M | 236220 | Unrestricted | N/A | AE Design Bid Build | FY24 Q4 | FY25 Q4 |
LRL | KC-46A Alter Bldg 2245 Squad Ops | March Air Force Base (California) | Between $1M and $5M | 236220 | TBD | N/A | AE Design Bid Build | FY25 Q3 | FY25 Q4 |
LRL | B2303 Repair Admin Area (Aero Repair)- Alter B2320 Hydraulics/Boom Shop- Alter B2327 Battery Shop | March Air Force Base (California) | Between $5M and $10M | 236220 | TBD | N/A | AE Design Bid Build | FY25 Q3 | FY25 Q4 |
LRL | Add/Alt Bldg 600 for KC46 Flight Simulator | March Air Force Base (California) | Between $5M and $10M | 236220 | TBD | N/A | AE Design Bid Build | FY25 Q3 | FY25 Q4 |
LRL | Construct Addition and Renovation EOD Fac B750 | Minneapolis St. Paul JAP (Minnesota) | Between $1M and $5M | 236220 | TBD | N/A | AE Design Bid Build | FY25 Q3 | FY25 Q4 |
LRL | Construct Addition and Renovate AGE FAC B820 | Minneapolis St. Paul JAP (Minnesota) | Between $1M and $5M | 236220 | TBD | N/A | AE Design Bid Build | FY25 Q3 | FY25 Q4 |
LRL | BOWST Addition B321 & Alter Flight Simulator | Niagara Falls ARS (New York) | Between $5M and $10M | 236220 | Small Business Set Aside | N/A | AE Design Bid Build | FY25 Q3 | FY25 Q4 |
LRL | Combined Operations Facility | Niagara Falls ARS (New York) | Between $25M and $100M | 236220 | TBD | NA | AE Design Bid Build | FY26 | FY26 |
LRL | Taxiway Golf Extension | Westover Air Force Base (Massachusetts) | Between $25M and $100M | 236220 | TBD | N/A | AE Design Bid Build | FY27 | FY27 |
LRL | Aerospace Gound Equipment Maintenance Facility | Joint Base San Antonio (Texas) | Between $10M and $25M | 236220 | TBD | N/A | In-House Design Build | FY26 | FY26 |
LRL | Aeromedical Evacuation Facility | Joint Base Charleston (South Carolina) | Between $10M and $25M | 236220 | TBD | N/A | In-House Design Build | FY28 | FY28 |
LRL | Construct 512th Operations Group Complex | Dover Air Force Base (Delaware) | Between $25M and $100M | 236220 | TBD | N/A | AE Design Bid Build | FY26 Q3 | FY26 Q4 |
LRL | Construct/Renovate for 414 FG & 307 FS- Bldg 4517 | Seymour Johnson AFB (North Carolina) | Between $1M and $5M | 236220 | TBD | N/A | AE Design Bid Build | FY25 Q3 | FY25 Q4 |
LRL | Repair Aircraft Arresting Systems- Restripe Runway | Homestead AFB (Florida) | Between $5M and $10M | 236220 | TBD | N/A | AE Design Bid Build | FY25 Q3 | FY25 Q4 |
LRL | Renovate Building 7087- Phase III and IV | Westover Air Force Base (Massachusetts) | Between $5M and $10M | 236220 | Small Business Set Aside | N/A | AE Design Bid Build | FY25 Q2 | FY25 Q3 |
LRL | Base Fire Station | Youngstown (Ohio) | Between $10M and $25M | 236220 | Unrestricted | N/A | AE Design Bid Build | FY25 Q2 | FY25 Q3 |
LRL | Repair Aircraft Arresting Systems- Restripe Runway | Homestead Air Force Base (Florida) | Between $5M and $10M | 236220 | TBD | N/A | AE Design Bid Build | FY25 Q3 | FY25 Q4 |
LRL | Aeromedical Evacaution Facility | Joint Base Charleston (South Carolina) | Between $25M and $100M | 236220 | TBD | N/A | AE Design Bid Build | FY28 | FY28 |
LRL | Aerospace Ground Equipment Maintenance Facility | Lackland Air Force Base (New Jersey) | Between $10M and $25M | 236220 | TBD | N/A | In House Design Bid Build | FY26 | FY26 |
LRL | Renovate and Construct Addition to Comms Facility | Niagara Falls ARS (New York) | Between $1M and $5M | 236220 | TBD | N/A | AE Design Bid Build | FY25 Q4 | FY26 Q1 |
LRL | Area Maintenance Support Center | (San Tan Valley) Phoenix (Arizona) | Between $10M and $25M | 236220 | Unrestricted | N/A | AE Design Bid Build | FY25 Q1 | FY25 Q3 |
LRL | Army Reserve Center | Birmingham (Alabama) | Between $25M and $100M | 236220 | Unrestricted | N/A | AE Design Bid Build | FY25 Q3 | FY26 Q1 |
LRL | Advanced Skills Training Barracks | Camp Parks (California) | Between $25M and $100M | 236220 | TBD | N/A | AE Design Bid Build | FY25 Q2 | FY25 Q3 |
LRL | Area Maintenance Support Activity / VMS | Defense Supply Center Richmond (Virginia) | Between $10M and $25M | 236220 | Unrestricted | N/A | AE Design Bid Build | FY25 Q3 | FY25 Q4 |
LRL | Renovate/Repair Army Reserve Center and Area Maintenance Support Activity | Sacramento (California) | Between $25M and $100M | 236220 | Small Business Set Aside | N/A | Design Build | FY25 Q4 | FY25 Q4 |
LRL | Collective Training Enlisted Barracks | Devens (Massachusetts) | Between $25M and $100M | 236220 | Unrestricted | N/A | Design Bid Build | FY25 Q2 | FY25 Q3 |
LRL | Army Reserve Center | Dobbins Air Force Base (Georgia) | Between $25M and $100M | 236220 | Unrestricted | N/A | In-House Design Bid Build | FY25 Q3 | FY25 Q4 |
LRL | Institutional Training Unaccompanied Housing | Fort Buchanan (Puerto Rico) | Between $25M and $100M | 236220 | TBD | N/A | AE Design Bid Build | FY25 Q3 | FY25 Q4 |
LRL | Multipurpose Athletic Field - Army Combat | Fort McCoy (Wisconsin) | Between $5M and $10M | 236220 | TBD | N/A | AE Design Bid Build | FY28 | FY28 |
LRL | Area Maintenance Support Activity | Fort Sheridan (Illinois) | Between $25M and $100M | 236220 | TBD | N/A | In-House Design Bid Build | FY31 | FY31 |
LRL | Vehicle Maintenance Shop | Manitowoc (Wisconsin) | Between $10M and $25M | 236220 | TBD | N/A | AE Design Bid Build | FY26 Q4 | FY27 Q1 |
LRL | Area Maintenance Support Activity | New Castle (Pennsylvania) | Between $10M and $25M | 236220 | TBD | N/A | AE Design Bid Build | FY25 Q4 | FY26 Q1 |
LRL | Area Maintenance Support Activity Equipment | Wilkes Barre (Pennsylvania) | Between $10 and $25M | 236220 | Unrestricted | N/A | AE Design Bid Build | FY24 Q4 | FY25 Q2 |
LRL | Area Maintenance Support Activity | Patton USARC (California) | Between $25M and $100M | 236220 | TBD | N/A | AE Design Bid Build | FY29 | FY29 |
LRL | Vertical Skills Training Facility | Joint Base McGuire-Dix-Lakehurst (New Jersey) | Between $10M and $25M | 236220 | Small Business Set Aside | N/A | AE Design Bid Build | FY25 Q1 | FY25 Q3 |
LRL | Aviation Support Facility Hanger | Fort Knox (Kentucky) | Between $100M and $250M | 236220 | Unrestricted | N/A | AE Design Bid Build | FY26 Q2 | FY26 Q4 |
LRL | Area Maintenance Support Activity | Joint Base Elmendorf-Richardson (Alaska) | Between $10M and $25M | 236220 | TBD | N/A | In-House Design Bid Build | FY31 | FY31 |
LRL | Collective Training Enlisted Barracks | Camp Parks (California) | Between $25M and $100M | 236220 | TBD | N/A | AE Design Build | FY27 | FY27 |
LRL | Advanced Skills Training Barracks | Camp Parks (California) | Between $25M and $100M | 236220 | TBD | N/A | AE Design Build | FY28 | FY28 |
LRL | Vehicle Maintenance Shop | Tonganoixie (Kansas) | Between $10M and $25M | 236220 | TBD | N/A | AE Design Build | FY26 | FY26 |
LRL | Airborne Equipment Parachute Repair Shop | Patton USARC (California) | Between $10M and $25M | 236220 | TBD | N/A | AE Design Bid Build | FY28 | FY28 |
LRL | Modernization of General Instruction Building | Fort Huachuca (Arizona) | Between $5M and $10M | 236220 | TBD | N/A | TBD | FY25 Q3 | FY25 Q4 |
LRL | Metro Louisville Pump Stations- Walls & Assoc. Features | Metro Louisville (Kentucky) | Between $25M and $100M | 236220 | TBD | TBD | TBD | TBD | TBD |
LRL | Johnson County Flood Warning & Emergency Evacuation Plan | Paintsville (Kentucky) | Between $5M and $10M | 236220 | TBD | TBD | TBD | TBD | TBD |
LRL | Johnson County Levees & Floodwalls | Paintsville (Kentucky) | Between $25M and $100M | 236220 | TBD | TBD | TBD | TBD | TBD |
LRL | Dam Outlet works & Cutoff Wall Phase 2 | Rough River Dam (Kentucky) | Between $250M and $500M | 237990 | Unrestricted | TBD | Design Bid Build | FY25 Q1 | FY25 Q4 |
LRL | Demolition of 2 Buildings | (DSCC) Columbus (Ohio) | Between $1M and $5M | 236220 | TBD | N/A | AE Design Build | FY25 Q4 | FY26 |
LRL | Replacing Switch Gears for DFAS | (DSCC) Columbus (Ohio) | Between $1M and $5M | 236220 | TBD | N/A | AE Design Build | FY25 Q2 | FY25 Q3 |
LRL | Carpet Replacement Building 21 | (DSCC) Columbus (Ohio) | Between $1M and $5M | 236220 | TBD | N/A | AE Design Build | FY25 Q2 | FY25 Q3 |
LRL | B3659 Composites Engr Innovation Ctr | Crane (Indiana) | Between $1M and $5M | 236220 | Small Business Set Aside | N/A | In House Design Build | FY25 Q3 | FY25 Q4 |
LRL | Building 143 Renovate Bays 1 & 3 | Crane (Indiana) | Between $1M and $5M | 236220 | TBD | N/A | AE Design Bid Build | FY26 Q4 | FY27 Q1 |
LRL | B3748 Trusted Microelectronic Assurance Center | Crane (Indiana) | Between $5M and $10M | 236220 | TBD | N/A | AE Design Bid Build | FY26 Q2 | FY26 Q4 |
LRL | Pyrotechnic Production Facility | Crane (Indiana) | Between $25M and $100M | 236220 | TBD | N/A | AE Design Bid Build | FY26 Q1 | FY26 Q4 |
LRL | Virtualized Electro Warfare & Mission Eng. Center | Crane (Indiana) | Between $5M and $10M | 236220 | TBD | N/A | AE Design Bid Build | FY26 Q2 | FY26 Q4 |
LRL | Shipboard/Ground Systems Lab | Crane (Indiana) | Between $25M and $100M | 236220 | TBD | N/A | AE Design Bid Build | FY27 Q2 | FY27 Q4 |
LRL | B-198 HVAC- Chillers- and MAU | Crane (Indiana) | Between $1M and $5M | 236220 | TBD | N/A | AE Design Bid Build | FY25 Q3 | FY26 Q1 |
LRL | Unmanned Fusion Warfare Laboratory | Crane (Indiana) | Between $5M and $10M | 236220 | TBD | N/A | AE Design Bid Build | FY26 Q3 | FY27 Q2 |
LRL | DTA PEO Bldg. 231 1st Floor Renovation | Detroit Arsenal (Michigan) | Between $10M and $25M | 236220 | TBD | N/A | AE Design Bid Build | FY25 Q3 | FY25 Q4 |
LRL | Manned/Unmanned Tactical Vehicle Lab | Detroit Arsenal (Michigan) | Between $25M and $100M | 236220 | Unrestricted | N/A | AE Design Bid Build | FY25 Q1 | FY25 Q3 |
LRL | Mulitpurpose Training Range | Fort Campbell (Kentucky) | Between $25M and $100M | 236220 | Unrestricted | N/A | AE Design Bid Build | FY25 Q1 | FY25 Q2 |
LRL | Automated Record Fire Range | Fort Campbell (Kentucky) | Between $10M and $25M | 236220 | TBD | N/A | In House Design Bid Build | FY25 Q4 | FY26 |
LRL | Rectifier Replacement | Fort Campbell (Kentucky) | Between $5M and $10M | 236220 | TBD | MATOC | AE Design Build | FY25 Q1 | FY25 Q2 |
LRL | Mahaffey MS Relocatable Removal | Fort Campbell (Kentucky) | Between $1M and $5M | 236220 | TBD | N/A | AE Design Build | FY25 Q1 | FY25 Q2 |
LRL | Consolidated Housing Furniture Storage | Fort Campbell (Kentucky) | Between $1M and $5M | 236220 | Unrestricted | N/A | Design Build | FY25 Q1 | FY25 Q2 |
LRL | Renovate Building 7214 Hangar | Fort Campbell (Kentucky) | Between $10M and $25M | 236220 | TBD | N/A | AE Design Bid Build | FY25 Q1 | FY25 Q3 |
LRL | Ambulatory Care Center | Fort Campbell (Kentucky) | Between $25M and $100M | 236220 | TBD | N/A | AE Design Bid Build | TBD | TBD |
LRL | Air Traffic Control Tower | Fort Campbell (Kentucky) | Between $25M and $100M | 236220 | TBD | N/A | AE Design Build | FY27 Q1 | FY27 Q2 |
LRL | Barracks | Fort Campbell (Kentucky) | Between $25M and $100M | 236220 | TBD | N/A | In House Design Build | FY26 Q1 | FY26 Q4 |
LRL | Renovate Building 3069 Child Development Center | Fort Campbell (Kentucky) | Between $10M and $25M | 236220 | TBD | N/A | AE Design Build | FY25 Q2 | FY25 Q3 |
LRL | Scott Middle School | Fort Knox (Kentucky) | Between $25M and $100M | 236220 | TBD | N/A | AE Design Bid Build | FY26 Q1 | FY26 Q2 |
LRL | IIS Lex- KY Forage Animal Production Research Unit | Lexington (Kentucky) | Between $25M and $100M | 236220 | Unrestricted | N/A | AE Design Bid Build | TBD | TBD |
LRL | Cyber Repair Maintenance | Mansfield (Illinois) | Between $25M and $100M | 236220 | TBD | N/A | AE Design Bid Build | FY25 Q2 | FY25 Q4 |
LRL | Construct Small Arms Range | Rickenbacker (Ohio) | Between $5M and $10M | 236220 | Small Business Set Aside | N/A | AE Design Bid Build | FY25 Q2 | FY25 Q3 |
LRL | Child Development Center | Rock Island Arsenal (Illinois) | Between $25M and $100M | 236220 | TBD | N/A | AE Design Build | FY25 Q2 | FY25 Q3 |
LRL | Emergency Exit Stairs Towers Bldg 390 | Rock Island Arsenal (Illinois) | Between $5M and $10M | 236220 | Small Business Set Aside | N/A | AE Design Bid Build | TBD | TBD |
LRL | Repair Fire Suppression Systems (Multiple facilities) | Rock Island Arsenal (Illinois) | Between $5M and $10M | 236220 | TBD | NA | AE Design Bid Build | FY25 Q2 | FY25Q4 |
LRL | Substation A Modernization | Rock Island Arsenal (Illinois) | Between $5M and $10M | 236220 | Small Business Set Aside | N/A | AE Design Bid Build | FY26 Q2 | FY26 Q4 |
LRL | Transmission Line Modernization | Rock Island Arsenal (Illinois) | Between $25M and $100M | 236220 | TBD | NA | AE Design Bid Build | FY26 Q2 | FY26 Q4 |
LRL | Indiana ANG Indoor Small Arms Range | Terre Haute (Indiana) | Between $5M and $10M | 236220 | Small Business Set Aside | Northeast MATOC | AE Design Build | FY25 TBD | FY25 TBD |
LRL | WPAFB 3rd Air Stream at Research Cell B18 Complex | Wright Patterson Air Force Base (Ohio) | Between $5M and $10M | 236220 | TBD | N/A | AE Design Bid Build | FY25 Q3 | TBD |
LRL | HPW HVAC Renovations | Wright Patterson Air Force Base (Ohio) | Between $5M and $10M | 236220 | TBD | N/A | AE Design Bid Build | FY25 Q2 | FY25 Q4 |
LRL | NAMRU-D Construct Lab Support Bldg - B900 | Wright Patterson Air Force Base (Ohio) | Between $5M and $10M | 236220 | Unrestricted | N/A | AE Design Bid Build | FY25 Q2 | FY25 Q4 |
LRL | Human Performance Lab | Wright Patterson Air Force Base (Ohio) | Between $25M and $100M | 236220 | TBD | N/A | AE Design Bid Build | FY26 Q3 | FY26 Q4 |
LRL | Acquisition Management Complex- V | Wright Patterson Air Force Base (Ohio) | Between $100M and $250M | 236220 | TBD | N/A | AE Design Bid Build | FY26 Q3 | FY26 Q4 |
LRL | 10 MW Dual Fuel Generator/Microgrid | Aberdeen Proving Ground (Maryland) | Between $25M and $100M | 237130 | TBD | N/A | AE Design Build | FY25 Q4 | FY25 Q4 |
LRL | Build Microgrid with Spinning Generation A | Anniston Army Depot (Alabama) | Between $25M and $100M | 237130 | SDVOSB | N/A | AE Design Bid Build | FY25 Q1 | FY25 Q1 |
LRL | Power Generation and Microgrid | Belgium | Between $25M and $100M | 237130 | TBD | N/A | AE Design Bid Build | FY26 Q2 | FY26 Q4 |
LRL | Electric Power- Photovoltaic | Camp Roberts (California) | Between $25M and $100M | 237130 | TBD | N/A | AE Design Bid Build | FY27 Q1 | FY27 Q1 |
LRL | Conroe RC Install Microgrid / PV / BESS & Generator | Conroe (Texas) | Between $10M and $25M | 237130 | Unrestricted | N/A | AE Design Bid Build | FY25 Q3 | FY25 Q4 |
LRL | Zone 1 Pad17 Hybrid Microgrid | Camp Buehring (Kuwait) | Between $10M and $25M | 237130 | TBD | N/A | AE Design Bid Build | FY25 Q3 | FY25 Q4 |
LRL | Microgrid System - Mobility (Railhead) Area | Fort Bliss (Texas) | Between $5M and $10M | 237130 | TBD | N/A | AE Design Bid Build | FY27 Q1 | FY27 Q1 |
LRL | DPTMS Simulation Training Campus Microgrid | Fort Bliss (Texas) | Between $5M and $10M | 237130 | TBD | N/A | AE Design Bid Build | FY26 Q1 | FY26 Q1 |
LRL | Microgrid - McGregor / Westbrook | Fort Bliss (Texas) | Between $10M and $25M | 237130 | TBD | N/A | AE Design Bid Build | FY28 Q1 | FY28 Q1 |
LRL | 5 MW NG Generator Microgrid - East | Fort Bliss (Texas) | Between $10M and $25M | 237130 | TBD | N/A | AE Design Bid Build | FY28 Q1 | FY28 Q1 |
LRL | Installation Level Microgrid | Fort Buchanan (Puerto Rico) | Between $25M and $100M | 237130 | TBD | N/A | AE Design Bid Build | FY25 Q2 | FY25 Q4 |
LRL | Water Treatment System at Las Casa Lake | Fort Buchanan (Puerto Rico) | Between $10M and $25M | 237110 | TBD | N/A | AE Design Bid Build | FY26 Q1 | FY26 Q2 |
LRL | Electric Power - Gas Fired | Fort Cavazos (formerly Fort Hood) (Texas) | Between $10M and $25M | 237130 | Potential Sole Source to Utility Provider | N/A | AE Design Bid Build | FY25 | TBD |
LRL | Phantom Warrior Central Microgrid | Fort Cavazos (formerly Fort Hood) (Texas) | Between $25M and $100M | 237130 | Potential Sole Source to Utility Provider | N/A | AE Design Bid Build | FY25 | TBD |
LRL | Water Supply Treatment Building - Potable | Fort Liberty (formerly Ft. Bragg) (North Carolina) | Between $10M and $25M | 237110 | Sole Source to Utility Provider | N/A | In House Design Build | FY25 | TBD |
LRL | Electric Power - Gas Fired | Fort Riley (Kansas) | Between $25M and $100M | 237130 | Sole Source to Utility Provider | N/A | AE Design Bid Build | FY25 | FY25 |
LRL | Construct 10MW Microgrid Utilizing Existin | Fort Liberty (formerly Ft. Bragg) (North Carolina) | Between $25M and $100M | 237130 | Sole Source to Utility Provider | N/A | AE Design Bid Build | FY25 Q3 | FY25 Q4 |
LRL | Emergency Diesel Microgrid | Fort Liberty (formerly Ft. Bragg) (North Carolina) | Between $5M and $10M | 237130 | Sole Source to Utility Provider | N/A | AE Design Bid Build | FY25 | FY25 |
LRL | Electric Power - Gas Fired | Fort Stewart (Georgia) | Between $25M and $100M | 237130 | Potential Sole Source to Utility Provider | N/A | AE Design Bid Build | TBD | TBD |
LRL | Water Distribution Lines- Potable | Hawthorne (Nevada) | Between $5M and $10M | 237130 | TBD | N/A | AE Design Bid Build | FY25 Q3 | FY25 Q4 |
LRL | YTC Microgrid | Joint Base Lewis-McChord (Washington) | Between $25M and $100M | 237130 | Potential Sole Source to Utility Provider | N/A | AE Design Bid Build | FY26 Q1 | FY26 Q1 |
LRL | Build 2.5 MW Microgrid for Gray Army Airfield | Joint Base Lewis-McChord (Washington) | Between $25M and $100M | 237130 | Potential Sole Source to Utility Provider | N/A | AE Design Bid Build | FY25 | FY25 |
LRL | AAP 15 MW NG CHP Microgrid | Lake City Army Ammo Plant (Missouri) | Between $25M and $100M | 237130 | TBD | N/A | In House Design Build | FY25 Q2 | FY25 Q3 |
LRL | Electric Power- Photovoltaic | Parks RFTA (California) | Between $25M and $100M | 237130 | TBD | N/A | AE Design Bid Build | TBD | TBD |
LRL | Electric Power- Photovoltaic | Redstone Arsenal (Alabama) | Between $25M and $100M | 237130 | TBD | N/A | AE Design Bid Build | FY25 Q2 | FY25 Q4 |
LRL | Build 15 MW Microgrid with 10 MW New NG RI | Rock Island Arsenal (Illinois) | Between $25M and $100M | 237130 | TBD | N/A | AE Design Bid Build | FY25 Q3 | FY25 Q4 |
LRL | Main Potable Water Lines for Resilience | Tooele Army Depot (Utah) | Between $10M and $25M | 237110 | TBD | N/A | AE Design Bid Build | FY25 Q3 | FY25 Q4 |
LRL | Electric Power - Photovoltaic | White Sands Missile Range (New Mexico) | Between $10M and $25M | 237130 | Unrestricted | N/A | AE Design Bid Build | FY26 Q2 | FY26 Q4 |
LRL | Solar Panels Installation | Camp Carroll (Korea) | Between $10M and $25M | 237130 | TBD | N/A | AE Design Bid Build | TBD | TBD |
LRL | Build 2.5 MW Microgrid for Gray Army Airfield | Joint Base Lewis-McChord (Washington) | Between $25M and $100M | 237130 | Potential Sole Source to Utility Provider | N/A | AE Design Bid Build | FY25 | FY25 |
LRL | ARTC Microgrid 14 Generator Consol 700kW Solar | Cp Buehring (Kuwait) | Between $25M and $100M | 237130 | Unrestricted | N/A | AE Design Bid Build | FY25 Q3 | FY25 Q4 |
LRL | ERCIP WPAFB District Cooling Plant | Wright Patterson Air Force Base (Ohio) | Between $25M and $100M | 237130 | TBD | N/A | AE Design Bid Build | FY25 Q4 | FY25 Q4 |
LRL | Electric Power Gas Fired Microgrid | Fort Sill (Oklahoma) | Between $100M and $250M | 237130 | TBD | N/A | AE Design Bid Build | FY25 Q4 | FY25 Q4 |
LRL | Install Microgrid- PV- Battery Energy Storage | Katterbach (Germany) | Between $25M and $100M | 237130 | TBD | N/A | A/E Design Bid Build | FY27 Q1 | FY27 Q1 |
LRL | Stilling Basin Repair & Dewatering | Caesar Creek Lake (Ohio) | Between $500K and $1M | 237990 | TBD | TBD | TBD | FY25 Q2 | FY25 Q2 |
LRL | Repair Emergency and Service Gate Lips and Seals | Caesar Creek Lake (Ohio) | Between $500K and $1M | 237990 | TBD | TBD | TBD | FY25 Q4 | FY25 Q4 |
LRL | Tower Bridge Painting & Bridge Deck Replacement | Cagles Mill Lake (Indiana) | Between $500K and $1M | 237990 | TBD | MATOC Task Order | RFP | FY25 Q2 | FY25 Q2 |
LRL | Culvert Valve | Cannelton Lock & Dam (Indiana) | Between $5M and $10M | 237990 | TBD | TBD | TBD | FY26 Q1 | FY26 Q1 |
LRL | Fixed Weir Repair | Cannelton Lock & Dam (Indiana) | Between $250K and $500K | 237990 | TBD | TBD | TBD | FY25 Q2 | FY25 Q2 |
LRL | Repair and Replace Lock Controls | Cannelton Lock & Dam (Indiana) | Between $500K and $1M | 237990 | TBD | TBD | TBD | FY25 Q3 | FY25 Q3 |
LRL | Tainter Gate Cable Connection Replacement | JT Myer Lock & Dam (Indiana) | Between $1M and $5M | 237990 | TBD | TBD | TBD | FY26 Q4 | FY26 Q4 |
LRL | Miter Gate Fabrication | Markland Lock & Dam (Kentucky) | Between $10M & $25M | 237990 | TBD | TBD | TBD | FY25 Q2 | FY25 Q3 |
LRL | Tainter Fate #1 Fabrication | McAlpine Lock & Dam (Kentucky) | Between $10M and $25M | 237990 | TBD | TBD | TBD | FY26 Q2 | FY26 Q3 |
LRL | Replace Culvert Valves | McAlpine Lock & Dam (Kentucky) | Between $1M and $5M | 237990 | TBD | MATOC Task Order | RFP | FY25 | FY25 |
LRL | Remove and Repair Service Gates | Monroe Lake (Indiana) | Between $1M and $5M | 237990 | TBD | MATOC Task Order | RFP | FY25 Q4 | FY25 Q4 |
LRL | Nolin Hoist | Nolin River Lake (Kentucky) | Between $500K and $1M | 237990 | TBD | TBD | TBD | FY25 Q2 | FY25 Q3 |
LRL | Install Articulated Block | Patoka Lake (Indiana) | Between $500K and $1M | 237990 | TBD | TBD | TBD | FY25 Q2 | FY25 Q2 |
LRL | Multilevel Intake and Hydraulic System Repairs | Patoka Lake (Indiana) | Between $250K and $500K | 237990 | TBD | TBD | TBD | FY25 Q3 | FY25 Q3 |
LRL | R3F Lock Maintenance Bulkheads | Regional Rivers Repair Fleet | Between $10M and $25M | 237900 | TBD | TBD | TBD | FY25 Q4 | FY25 Q4 |
LRL | Sewage Treatment Plant Replacement | Rough River Lake (Kentucky) | Between $500K and $1M | 237990 | TBD | TBD | TBD | FY25 | FY25 |
LRL | Training Wall Drain Gutter | West Fork Lake (Ohio) | Between $250K and $500K | 237990 | TDB | TBD | TBD | FY25 | FY26 |
LRL | ERCIP MATOC | Nationwide | $2B Shared Capacity | 237130 | Unrestricted with Small Business Reserve | | | FY24 Q4 | FY25 Q4 |
LRL | A/E Environmental MATOC | | $200M Shared Capacity | 541330 | Anticipate Unrestricted with SB Reserve | | | FY26 Q3 | FY25/26 |
LRL | Military Construction MATOC | | $240M Shared Capacity | 236220 | Small Business Set Aside | | Design Build | FY25 Q2 | FY25 Q4 |
LRL | Military Construction MATOC | | $200M Shared Capacity | 236220 | HubZone | | Design Build | FY25 Q3 | FY25 Q4 |
LRL | Military Construction MATOC | | $160M Shared Capacity | 236220 | SDVOSB | | Design Bid Build | FY25 Q2 | FY25 Q4 |
LRL | A/E Air Force Reserve MATOC | | $150M Shared Capacity | 541330 | Unrestricted with Small Business Reserve | | | FY25 Q3 | FY25 Q4 |
LRL | Environmental Heavy Metals MATOC | | $245M Shared Capacity | 562910 | Unrestricted | | | FY25 Q1 | FY25 Q3 |
LRL | Environmental Optimization (AE Svcs) | Scott AFB | $25M (SATOC) | 541330 | Small Business Set Aside | | | FY25 Q2 | FY25 Q4 |
LRL | Bureau of Prisons New Facility | Letcher County- KY | $150M (SATOC) | 541330 | TBD | | | FY25 Q3 | FY25 Q4 |
LRL | Risk Management Center Horizontal Design and Existing Condition Expert Reviews | Nationwide | $75M | 541330 | Unrestricted with a Small Business Reserve | | | FY25 Q3 | FY25 Q4 |
LRN | Wolf Creek GSU Transformer | Jamestown (Kentucky) | $10M-$25M | 335311 | Unrestricted | NA | RFP | Q4FY24 | FY25 |
LRN | Chickamauga Lock Approach Wall and Decommissioning | Chattanooga (Tennessee) | $250M-$500M | 237990 | Unrestricted | NA | RFP | Q2FY25 | Q4FY25 |
LRN | Wolf Creek Bridge Crane Rehab | Jamestown (Kentucky) | $5M-$10M | 333923 | TBD | LRN Crane MATOC | Task Order | FY25 | FY25 |
LRN | Cheatham Intake Crane Replacement | Ashland City (Tennessee) | $10M-$25M | 333923 | TBD | LRN Crane MATOC | Task Order | FY25 | FY25 |
LRN | Cordell Hull Powerhouse Crane - Rehabilitate powerhouse crane | Carthage (Tennessee) | TBD | 333923 | TBD | LRN Crane MATOC | Task Order | FY26 | FY26 |
LRN | Ft. Loudoun and Watts Bar- Lock Ladder Install - Lock ladder installlation to meet the USACE safety manual requirements (EM 35-1-20) as well as OSHA standards. | Lenoir City and Spring City (Tennessee) | $1M-$5M | TBD | TBD | TBD | TBD | FY26 | FY26 |
LRN | Cordell Hull Phase II- Carthage- TN Streambank Stabilization - Stabilization of riverbank along Cumberland River at the Carthage WWTP | Carthage (Tennessee) | $1M-$5M | 237990 | Total Small Business Set Aside | LRN Stabilization MATOC | Task Order | FY25 | FY25 |
LRN | East Camp Creek Flood Risk Reduction - Construction of a detention structure to reduce flooding throughout downtown Gallatin area | Gallatin (Tennessee) | $1M-$5M | 237990 | Total Small Business Set Aside | LRN Stabilization MATOC | Task Order | FY25 | FY25 |
LRN | Nickajack Two (2) new low speed gear boxes | Jasper (Tennessee) | over SAT | 333612 | Small Business Set Aside | NA | SAP | FY26 | FY26 |
LRN | Brewster Road Repair - Roadway Stabilization | Big South Fork (Tennessee) | $500K-$1M | 237990 | Total Small Business Set Aside | LRN Stabilization MATOC | Task Order | FY25 | FY25 |
LRN | Blount Ave: Mouse Creek/Cleveland - Channel Modification | Cleveland (Tennessee) | $250K-$500K | 237990 | Small Business Set Aside | NA | IFB | Q4FY25 | Q1FY26 |
LRN | Williams St. Detention: Mouse Creek/Cleveland - Detention Structure | Cleveland (Tennessee) | $500K-$1M | 237990 | Small Business Set Aside | NA | IFB | Q4FY25 | Q2FY26 |
LRN | Wolf Creek Turbine Generator Rehab - Rewind 4 units- replace 6 turbines with auto-venting | Jamestown (Kentucky) | $100M-$250M | 237990 | Unrestricted | NA | RFP | FY26 | FY27 |
LRN | J. Percy Priest Exciter Replacement | Nashville (Tennessee) | $1M-$5M | 237130 | Unrestricted | LRN Excitation SATOC | Task Order | FY25 | FY26 |
LRN | Lee County Sewer Improvements - Phase 1A | Jonesville (Virginia) | $25M-$100M | TBD | TBD | NA | RFP | TBD | TBD |
LRN | J. Percy Priest DC Systems and Preferred AC Systems - Replace DC and Preferred ACSystems | Nashville (Tennessee) | $1M-$5M | TBD | TBD | NA | RFP | TBD | FY26 |
LRN | Cheatham Excitation | Ashland City (Tennessee) | TBD | 237130 | Unrestricted | LRN Excitation SATOC | Task Order | TBD | FY26 |
LRN | Old Hickory Planting and Landscaping (Tornado Recovery) - Restore vegetative cover (trees- shrubs- grass) | Hendersonville (Tennessee) | $1M-$5M | TBD | Small Business Set Aside | NA | IFB | TBD | FY25 |
LRN | Wolf Creek Mill Springs Mill Restoration | Mills Springs (Kentucky) | over SAT | TBD | TBD | TBD | TBD | TBD | Q4FY25 |
LRN | Dredging Post Oak and Looney | Post Oak Island and Looney Island (Tennessee) | $1M-$5M | TBD | TBD | LRH Regional Dredging MATOC | Task Order | TBD | FY25 |
LRN | Sevier Co. PAS - H&H Modeling for Sevier Co. | Sevier County (Tennessee) | over SAT | TBD | Unrestricted | H&H MATOC | Task Order | TBD | FY25 |
LRN | Regional Court Reporter BPA | Chatanooga (Tennessee) | under SAT | TBD | Small Business Set Aside | N/A | TBD | FY25 | FY25 |
LRN | Barkley Geophysics | Grand Rivers (Kentucky) | under SAT | TBD | Small Business Set Aside | N/A | TBD | FY25 | FY25 |
LRN | CT test sets for ESS | Tennessee | under SAT | TBD | Small Business Set Aside | N/A | TBD | FY25 | FY25 |
LRN | 3-Phase Test Set- purchase for ESS | Tennessee | under SAT | TBD | Small Business Set Aside | N/A | TBD | FY25 | FY25 |
LRN | SCADA Miscellaneous Parts | Nashville (Tennesee) | under SAT | TBD | Small Business Set Aside | N/A | TBD | FY25 | FY25 |
LRN | Kentucky Lock Wall Armor Purchase | Grand Rivers (Kentucky) | under SAT | TBD | Small Business Set Aside | N/A | TBD | FY25 | FY25 |
LRN | Ops- MST-Broaderson Crane Purchase | Tennessee | under SAT | TBD | Small Business Set Aside | N/A | TBD | FY25 | FY25 |
LRN | Ops- MST - pump and piping purchase | Tennessee | under SAT | TBD | Small Business Set Aside | N/A | TBD | FY25 | FY25 |
LRN | Wolf Creek- mower purchase (2) | Jamestown (Kentucky) | under SAT | TBD | Small Business Set Aside | N/A | TBD | FY25 | FY25 |
LRN | Barkley Hydro- Generator Governor Rebuild Parts | Clarksville (Tennessee) | under SAT | TBD | Small Business Set Aside | N/A | TBD | FY25 | FY25 |
LRN | Dale Hollow- Drain Line | Knoxville (Tennessee) | under SAT | TBD | Small Business Set Aside | N/A | TBD | FY25 | FY25 |
LRN | Wheeler Lower Gate Fenders | Rogersville (Alabama) | under SAT | TBD | Small Business Set Aside | N/A | TBD | FY25 | FY25 |
LRN | Wheeler Lock- New shop doors w/ incidental install | Rogersville (Alabama) | under SAT | TBD | Small Business Set Aside | N/A | TBD | FY25 | FY25 |
LRN | Wilson Lock- New shop doors w/ incidental install | Florence (Alabama) | under SAT | TBD | Small Business Set Aside | N/A | TBD | FY25 | FY25 |
LRN | Arc Flash Protective Gear | TBD | under SAT | TBD | Small Business Set Aside | N/A | TBD | FY25 | FY25 |
LRN | Wilson Lock upper gate seal | Florence (Alabama) | under SAT | TBD | Small Business Set Aside | N/A | TBD | FY25 | FY25 |
LRN | Pickwick Aux Lock- Segmental Valve- Top Seals | Counce (Tennessee) | under SAT | TBD | Small Business Set Aside | N/A | TBD | FY25 | FY25 |
LRN | Channels - Purchase a new smaller size boat | TBD | under SAT | TBD | Small Business Set Aside | N/A | TBD | FY25 | FY25 |
LRN | TMDE Calibration | Tennessee | under SAT | TBD | Small Business Set Aside | N/A | TBD | FY25 | FY25 |
LRN | Wolf Creek- New Playground and Install | Jamestown (Kentucky) | under SAT | TBD | Small Business Set Aside | N/A | TBD | FY25 | FY25 |
LRN | FY25 New Park Attendants | Tennessee | under SAT | TBD | Small Business Set Aside | N/A | TBD | FY25 | FY25 |
LRN | Martin's Fork- Crane Rental | Knoxville (Tennessee) | under SAT | TBD | Small Business Set Aside | N/A | TBD | FY25 | FY25 |
LRN | Nickajack Lock- Tow Haulage Unit Rehab | Chattanooga (Tennessee) | under SAT | TBD | Small Business Set Aside | N/A | TBD | FY25 | FY25 |
LRN | BPA's - Elevator Inspections | Tennessee | under SAT | TBD | Small Business Set Aside | N/A | TBD | FY25 | FY25 |
LRN | BPA's - Bridge Inspections | Tennessee | under SAT | TBD | Small Business Set Aside | N/A | TBD | FY25 | FY25 |
LRN | Barkley Dam- Em. Gate Machinery Repairs | Clarksville (Tennessee) | under SAT | TBD | Small Business Set Aside | N/A | TBD | FY25 | FY25 |
LRN | FY26 New Park Attendants LRN | Tennessee | under SAT | TBD | Small Business Set Aside | N/A | TBD | FY26 | FY26 |
LRN | Dale Hollow TQ Security Fence | Knoxville (Tennessee) | under SAT | TBD | Small Business Set Aside | N/A | TBD | FY25 | FY25 |
LRN | BPA- Ops-Lakes- Sunken Vessel Removal | TBD | under SAT | TBD | Small Business Set Aside | N/A | TBD | FY25 | FY25 |
LRN | Ops- MST Iroquois-Dry Dock- replace engine cooler | TBD | under SAT | TBD | Small Business Set Aside | N/A | TBD | FY25 | FY25 |
LRN | Old Hickory ESS Building Rehabilitation from tornado damage | Hendersonville (Tennessee) | $10M-$25M | TBD | Small Business Set Aside | TBD | TBD | TBD | FY26 |
LRN | PAS TN H2O | Hendersonville (Tennessee) | over SAT | TBD | Unrestricted | H&H MATOC | Task Order | TBD | FY25 |
LRN | Old Hickory turbine generator rehabilitation asbestos abatement | Hendersonville (Tennessee) | under SAT | TBD | Small Business Set Aside | LRN Environmental Services MATOC | Task Order | TBD | FY25 |
LRN | Old Hickory Toe Drain Remediation | Hendersonville (Tennessee) | $1M-$5M | TBD | Small Business Set Aside | LRN Stabilization MATOC | Task Order | TBD | FY25 |
LRN | Watts Bar TVA Ramp. Construct a permanment ramp at Watts Bar to allow river access for TVA Nuclear for the movement of critical equipment via barge to the facility. | Spring City (Tennessee) | $500K-$1M | 237990 | Small Business Set Aside | TBD | TBD | TBD | FY26 |
LRN | Claims Consultant. Services for claims consulant associated with Chickamauga Lock construction claims and disputes | Grand Rivers (Kentucky) & Chattanooga (Tennessee) | over SAT | TBD | TBD | N/A | SAP | TBD | FY25 |
LRN | Temporary liquid oxygen system for construction and testing of the diffusion system within the Lake Cumberland reservoir at Wolf Creek Dam. | Jamestown (Kentucky) | under SAT | TBD | TBD | N/A | SAP | TBD | Q2FY25 |
LRN | Wolf Creek and Center Hill Instrumentation Survey Phase II | Jamestown (Kentucky) & Lancaster (Tennessee) | under SAT | TBD | Small Business Set-Aside | GSA | Task Order | TBD | Q2FY25 |
LRN | Kentucky Lock Gearbox Repair | Grand Rivers (Kentucky) | Over SAT | TBD | TBD | TBD | SAP | TBD | FY25 |
LRN | Debris Removal Vessel Barges Supply/Fab | Jamestown (Kentucky) | Over SAT | 334411 | Small Business Set-Aside | TBD | SAP | Q2 FY25 | FY25 |
LRN | Supply Remote Switch Operator for Nickajack and Chickamauga Locks | Newhope (Tennessee) and Chattanooga (Tennessee) | Under SAT | TBD | Small Business Set-Aside | TBD | SAP | Q3 FY25 | FY25 |
LRN | Dumpster Service for Laurel River Lake | London (Kentucky) | Under SAT | TBD | Small Business Set-Aside | TBD | SAP | Q3 FY25 | FY25 |
LRN | Real Estate Titles | Nashville (Tennessee) | Over SAT | TBD | Small Business Set-Aside | Base Purchase Agreement (BPA) | SAP | Q4 FY25 | Q1 FY26 |
LRN | Real Estate Appraisals | Nashville (Tennessee) | Over SAT | TBD | Small Business Set-Aside | Base Purchase Agreement (BPA) | SAP | Q1 FY26 | Q2 FY26 |
LRN | Mechanical Engineer CMS Support for Chickamauga Lock | Chattanooga (Tennessee) | Over SAT | TBD | WOSB | LRD AE CMS MATOC | Task Order | TBD | TBD |
LRN | H&H Services - WM Water Quality Database Updates | Nashville (Tennessee) | Over SAT | TBD | Unrestricted | H&H MATOC | Task Order | TBD | FY25 |
LRN | Dale Hollow Supplies for Site Remediation | Celina (Tennessee) | Under SAT | TBD | Small Business Set-Aside | TBD | SAP | Q3 FY25 | Q3 FY25 |
LRN | Cordell Hull O&M Requirements | Carthage (Tennessee) | Over SAT | 561210 | Small Business Set Aside | N/A | RFP | Q4 FY25 | Q1 FY26 |
LRN | Wilson Lock Ceramic Metal Base and Solidifier | Florence (Alabama) | Under SAT | | Small Business Set Aside | N/A | SAP | Q3 FY25 | Q3 FY25 |
LRP | Saw Mill Run Local Protection Project | Pittsburgh- Allegheny County- PA | $1M and $5M | 237990 | Small Business Set-Aside | N/A | IFB | FY25 Q1 | FY25 Q2 |
LRP | SEC 219 City of Chester Water System Improvements | Chester- Hancock County- WV | $1M and $5M | 237110 | Small Business Set-Aside | N/A | RFP | FY25 Q1 | FY25 Q2 |
LRP | IIJA Ohio River - Emsworth Replace Hydraulic Gate Cylinders | Pittsburgh- Allegheny County- PA | $5M and $10M | 237990 | Unrestricted - Full & Open | N/A | IFB | FY25 Q1 | FY25 Q2 |
LRP | DRSAA FY23 AR - Replace Anchor Point Buoys for Safety Boom | Allegheny County- PA | $100K and $250K | 238290 | Unrestricted - Full & Open | Construction DBB Rivers & Marine MATOC Pool W9123722D0027 - W9123722D0030 | RFP | FY25 Q1 | FY25 Q1 |
LRP | SEC 219 McMechen WV Storm Water Project | Mcmechen- Marshall County- WV | $1M and $5M | 237110 | Small Business Set-Aside | N/A | IFB | FY25 Q1 | FY25 Q2 |
LRP | IIJA Loyalhanna Solar Lights | Saltsburg- Westmoreland County- Pa | $25K and $100K | 238210 | Small Business Set-Aside | N/A | | FY25 Q1 | FY25 Q2 |
LRP | SEC 219 City of Paden City | Paden City- Tyler and Wetzel Counties- WV | $5M and $10M | 237110 | Small Business Set-Aside | N/A | IFB | FY25 Q1 | FY25 Q1 |
LRP | FY22 Dashields Upper Guide Wall Stabilization Project | Coraopolis- Allegheny County- PA | $5M and $10M | 237990 | Unrestricted - Full & Open | N/A | IFB | FY25 Q1 | FY25 Q2 |
LRP | FY23 MR Maxwell - Repair Interlocks | Centerville- Washington and Fayette County- PA | $1M and $5M | 237990 | Small Business Set-Aside | N/A | IFB | FY25 Q1 | FY25 Q2 |
LRP | FY24 IIJA Johnstown Sediment Removal Phase 4 | Johnstown- Cambria County- PA | $5M and $10M | 237990 | Small Business Set-Aside | N/A | IFB | FY25 Q1 | FY25 Q2 |
LRP | FY24 Tionesta Construct Bulkhead Hoist Jib Platform | Tionesta- Forest County- PA | $500K and $1M | 237990 | Small Business Set-Aside | N/A | IFB | FY25 Q1 | FY25 Q2 |
LRP | FY24 OR Hannibal - 4-Corner Hydraulic System | New Martinsville- Wetzel County- WV | $10M and $25M | 237990 | Unrestricted - Full & Open | N/A | IFB | FY25 Q1 | FY25 Q2 |
LRP | FY24 Ohio River - Dredging | Ohio River | $1M and $5M | 237990 | Unrestricted - Full & Open | Regional Dredging MATOC Pool W9123722D0002 - W9123722D0004 | RFP | FY25 Q2 | FY25 Q3 |
LRP | FY24 Tygart Replace PLC for Dam Sluice Gates | Taylor County- WV | $1M and $5M | 237990 | Small Business Set-Aside | N/A | IFB | FY25 Q2 | FY25 Q3 |
LRP | IIJA Berlin Sewage Treatment and Collection System | Mahoning County- Ohio | $1M and $5M | 237110 | Small Business Set-Aside | N/A | IFB | FY25 Q2 | FY25 Q3 |
LRP | SEC 219 City of McKeesport - Long Run Watershed Improvements | Mckeesport- Allegheny County- PA | $500K and $1M | 237110 | Small Business Set-Aside | N/A | IFB | FY25 Q2 | FY25 Q3 |
LRP | Lower Mon 234 | Elizabeth- PA | $10M and $25M | 237990 | Unrestricted - Full & Open | N/A | IFB | FY25 Q2 | FY25 Q3 |
LRP | FY24 Allegheny River - Dredging | Allegheny River | $500K and $1M | 237990 | Unrestricted - Full & Open | Regional Dredging MATOC Pool W9123722D0002 - W9123722D0004 | RFP | FY25 Q2 | FY25 Q3 |
LRP | FY24 Monongahela River - Dredging | Monongahela River | $1M and $5M | 237990 | Unrestricted - Full & Open | Regional Dredging MATOC Pool W9123722D0002 - W9123722D0004 | RFP | FY25 Q2 | FY25 Q3 |
LRP | IIJA & FY23 Conemaugh Dredging | Saltsburg- Westmoreland County- Pa | $10M and $25M | 237990 | Small Business Set-Aside | N/A | IFB | FY25 Q3 | FY25 Q4 |
LRP | SEC 219 Follansbee- Northern WV | Follansbee- Brooke County- WV | $1M and $5M | 237110 | Small Business Set-Aside | N/A | IFB | FY25 Q1 | FY25 Q2 |