Rebuilding Resilience: U.S. Army Corps of Engineers Restores Flood Protection Project in Pittsburgh’s West End

Pittsburgh District
Published Nov. 25, 2025
In a flood protection-project channel, a construction worker uses a bulldozer to move riprap.

A U.S. Army Corps of Engineers Pittsburgh District contractor moves riprap into the Saw Mill Run local flood-protection project channel in Pittsburgh, PA, Oct. 6, 2025. The riprap will be used to fill in toe trenches within the channel. The Saw Mill Run local flood-protection project was built to mitigate flood risk for Pittsburgh’s West End neighborhood. Spanning 4,717 feet, the LPP includes dredging, channel improvement and reinforced slope protection designed to handle flood flows of up to 6,900 cubic feet per second. The LPP was completed in October 2000 under Section 401 of the 1986 Flood Control Act. In June 2018, a severe storm damaged the project’s channel, eroding protective revetment and reducing the channel’s structural integrity. The U.S. Army Corps of Engineers Pittsburgh District, in partnership with the city of Pittsburgh, initiated rehabilitation under the Public Law 84-99 program to restore the project to its original flood risk-management capacity. The district awarded a nearly $1 million construction contract in February 2025 to complete the rehabilitation work. The current repairs reinforce key sections of the channel and ensure the project continues protecting the community from future flooding events. The Saw Mill Run local flood-protection project is one of 84 local flood-protection projects built by the district. (U.S. Army Corps of Engineers photo by Andrew Byrne)

A construction worker places stone in a channel.

A U.S. Army Corps of Engineers Pittsburgh District contractor places stone between the new and existing revetment along the Saw Mill Run local flood-protection project in Pittsburgh, PA, Oct. 6, 2025. The stone will be grouted to tie the new revetment into the existing concrete slab revetment in the channel. The Saw Mill Run local flood-protection project was built to mitigate flood risk for Pittsburgh’s West End neighborhood. Spanning 4,717 feet, the LPP includes dredging, channel improvement and reinforced slope protection designed to handle flood flows of up to 6,900 cubic feet per second. The LPP was completed in October 2000 under Section 401 of the 1986 Flood Control Act. In June 2018, a severe storm damaged the project’s channel, eroding protective revetment and reducing the channel’s structural integrity. The U.S. Army Corps of Engineers Pittsburgh District, in partnership with the city of Pittsburgh, initiated rehabilitation under the Public Law 84-99 program to restore the project to its original flood risk-management capacity. The district awarded a nearly $1 million construction contract in February 2025 to complete the rehabilitation work. The current repairs reinforce key sections of the channel and ensure the project continues protecting the community from future flooding events. The Saw Mill Run local flood-protection project is one of 84 local flood-protection projects built by the district. (U.S. Army Corps of Engineers photo by Andrew Byrne)

A construction worker holds a hose in a flood protection project channel.

A U.S. Army Corps of Engineers Pittsburgh District contractor pumps grout into the stone trench in the Saw Mill Run local flood-protection project in Pittsburgh, PA, Oct. 6, 2025. The grouting will tie the new revetment into the channel bottom. The Saw Mill Run local flood-protection project was built to mitigate flood risk for Pittsburgh’s West End neighborhood. Spanning 4,717 feet, the LPP includes dredging, channel improvement and reinforced slope protection designed to handle flood flows of up to 6,900 cubic feet per second. The LPP was completed in October 2000 under Section 401 of the 1986 Flood Control Act. In June 2018, a severe storm damaged the project’s channel, eroding protective revetment and reducing the channel’s structural integrity. The U.S. Army Corps of Engineers Pittsburgh District, in partnership with the city of Pittsburgh, initiated rehabilitation under the Public Law 84-99 program to restore the project to its original flood risk-management capacity. The district awarded a nearly $1 million construction contract in February 2025 to complete the rehabilitation work. The current repairs reinforce key sections of the channel and ensure the project continues protecting the community from future flooding events. The Saw Mill Run local flood-protection project is one of 84 local flood-protection projects built by the district. (U.S. Army Corps of Engineers photo by Andrew Byrne)

In a flood protection-project channel, a construction worker moves stone with an excavator.

A U.S. Army Corps of Engineers Pittsburgh District contractor moves riprap into the Saw Mill Run local flood-protection project channel in Pittsburgh, PA, Oct. 6, 2025. The riprap will be used to fill in trenches at the toe of the new revetment within the channel. The Saw Mill Run local flood-protection project was built to mitigate flood risk for Pittsburgh’s West End neighborhood. Spanning 4,717 feet, the LPP includes dredging, channel improvement and reinforced slope protection designed to handle flood flows of up to 6,900 cubic feet per second. The LPP was completed in October 2000 under Section 401 of the 1986 Flood Control Act. In June 2018, a severe storm damaged the project’s channel, eroding protective revetment and reducing the channel’s structural integrity. The U.S. Army Corps of Engineers Pittsburgh District, in partnership with the city of Pittsburgh, initiated rehabilitation under the Public Law 84-99 program to restore the project to its original flood risk-management capacity. The district awarded a nearly $1 million construction contract in February 2025 to complete the rehabilitation work. The current repairs reinforce key sections of the channel and ensure the project continues protecting the community from future flooding events. The Saw Mill Run local flood-protection project is one of 84 local flood-protection projects built by the district. (U.S. Army Corps of Engineers photo by Andrew Byrne)

In a flood protection-project channel, construction workers stand near an excavator.

A U.S. Army Corps of Engineers Pittsburgh District contractor uses an excavator to backfill a trench in the Saw Mill Run local flood-protection project in Pittsburgh, PA, Oct. 6, 2025. The trench was created to divert water away from the channel’s revetment toe key during construction. The Saw Mill Run local flood-protection project was built to mitigate flood risk for Pittsburgh’s West End neighborhood. Spanning 4,717 feet, the LPP includes dredging, channel improvement and reinforced slope protection designed to handle flood flows of up to 6,900 cubic feet per second. The LPP was completed in October 2000 under Section 401 of the 1986 Flood Control Act. In June 2018, a severe storm damaged the project’s channel, eroding protective revetment and reducing the channel’s structural integrity. The U.S. Army Corps of Engineers Pittsburgh District, in partnership with the city of Pittsburgh, initiated rehabilitation under the Public Law 84-99 program to restore the project to its original flood risk-management capacity. The district awarded a nearly $1 million construction contract in February 2025 to complete the rehabilitation work. The current repairs reinforce key sections of the channel and ensure the project continues protecting the community from future flooding events. The Saw Mill Run local flood-protection project is one of 84 local flood-protection projects built by the district. (U.S. Army Corps of Engineers photo by Andrew Byrne)

In a flood protection-project channel, a construction worker operates an excavator.

A U.S. Army Corps of Engineers Pittsburgh District contractor uses an excavator to backfill a Saw Mill Run local flood-protection project trench during channel rehabilitation in Pittsburgh, PA, Oct. 6, 2025. The trench was created to divert water away from the channel’s revetment toe key during construction. The Saw Mill Run local flood-protection project was built to mitigate flood risk for Pittsburgh’s West End neighborhood. Spanning 4,717 feet, the LPP includes dredging, channel improvement and reinforced slope protection designed to handle flood flows of up to 6,900 cubic feet per second. The LPP was completed in October 2000 under Section 401 of the 1986 Flood Control Act. In June 2018, a severe storm damaged the project’s channel, eroding protective revetment and reducing the channel’s structural integrity. The U.S. Army Corps of Engineers Pittsburgh District, in partnership with the city of Pittsburgh, initiated rehabilitation under the Public Law 84-99 program to restore the project to its original flood risk-management capacity. The district awarded a nearly $1 million construction contract in February 2025 to complete the rehabilitation work. The current repairs reinforce key sections of the channel and ensure the project continues protecting the community from future flooding events. The Saw Mill Run local flood-protection project is one of 84 local flood-protection projects built by the district. (U.S. Army Corps of Engineers photo by Andrew Byrne)

In a flood protection-project channel, construction workers stand near an excavator.

A U.S. Army Corps of Engineers Pittsburgh District contractor directs an excavator operator to place additional riprap into a trench in the Saw Mill Run local flood-protection project during channel rehabilitation in Pittsburgh, PA, Oct. 6, 2025. The additional riprap establishes a key for the revetment toe, helping to prevent bank erosion. The Saw Mill Run local flood-protection project was built to mitigate flood risk for Pittsburgh’s West End neighborhood. Spanning 4,717 feet, the LPP includes dredging, channel improvement and reinforced slope protection designed to handle flood flows of up to 6,900 cubic feet per second. The LPP was completed in October 2000 under Section 401 of the 1986 Flood Control Act. In June 2018, a severe storm damaged the project’s channel, eroding protective revetment and reducing the channel’s structural integrity. The U.S. Army Corps of Engineers Pittsburgh District, in partnership with the city of Pittsburgh, initiated rehabilitation under the Public Law 84-99 program to restore the project to its original flood risk-management capacity. The district awarded a nearly $1 million construction contract in February 2025 to complete the rehabilitation work. The current repairs reinforce key sections of the channel and ensure the project continues protecting the community from future flooding events. The Saw Mill Run local flood-protection project is one of 84 local flood-protection projects built by the district. (U.S. Army Corps of Engineers photo by Andrew Byrne)

In a flood protection-project channel, a construction worker operates an excavator.

A U.S. Army Corps of Engineers Pittsburgh District contractor uses an excavator to backfill a Saw Mill Run local flood-protection project trench during channel rehabilitation in Pittsburgh, PA, Oct. 6, 2025. The trench was created to divert water away from the channel’s revetment toe key during construction. The Saw Mill Run local flood-protection project was built to mitigate flood risk for Pittsburgh’s West End neighborhood. Spanning 4,717 feet, the LPP includes dredging, channel improvement and reinforced slope protection designed to handle flood flows of up to 6,900 cubic feet per second. The LPP was completed in October 2000 under Section 401 of the 1986 Flood Control Act. In June 2018, a severe storm damaged the project’s channel, eroding protective revetment and reducing the channel’s structural integrity. The U.S. Army Corps of Engineers Pittsburgh District, in partnership with the city of Pittsburgh, initiated rehabilitation under the Public Law 84-99 program to restore the project to its original flood risk-management capacity. The district awarded a nearly $1 million construction contract in February 2025 to complete the rehabilitation work. The current repairs reinforce key sections of the channel and ensure the project continues protecting the community from future flooding events. The Saw Mill Run local flood-protection project is one of 84 local flood-protection projects built by the district. (U.S. Army Corps of Engineers photo by Andrew Byrne)

In a flood protection-project channel, construction workers stand near an excavator.

U.S. Army Corps of Engineers Pittsburgh District contractors watch an excavator backfill a Saw Mill Run local flood-protection project trench during channel rehabilitation in Pittsburgh, PA, Oct. 6, 2025. The trench was created to divert water away from the channel’s revetment toe key during construction. The Saw Mill Run local flood-protection project was built to mitigate flood risk for Pittsburgh’s West End neighborhood. Spanning 4,717 feet, the LPP includes dredging, channel improvement and reinforced slope protection designed to handle flood flows of up to 6,900 cubic feet per second. The LPP was completed in October 2000 under Section 401 of the 1986 Flood Control Act. In June 2018, a severe storm damaged the project’s channel, eroding protective revetment and reducing the channel’s structural integrity. The U.S. Army Corps of Engineers Pittsburgh District, in partnership with the city of Pittsburgh, initiated rehabilitation under the Public Law 84-99 program to restore the project to its original flood risk-management capacity. The district awarded a nearly $1 million construction contract in February 2025 to complete the rehabilitation work. The current repairs reinforce key sections of the channel and ensure the project continues protecting the community from future flooding events. The Saw Mill Run local flood-protection project is one of 84 local flood-protection projects built by the district. (U.S. Army Corps of Engineers photo by Andrew Byrne)

In a flood protection-project channel, a construction worker passes a stone to another construction worker.
PHOTO DETAILS  /   DOWNLOAD HI-RES 10 of 14

U.S. Army Corps of Engineers Pittsburgh District contractors place stone in the Saw Mill Run local flood-protection project trench during channel rehabilitation in Pittsburgh, PA, Oct. 6, 2025. The stone will be grouted in the trench to tie into the existing concrete slab revetment. The Saw Mill Run local flood-protection project was built to mitigate flood risk for Pittsburgh’s West End neighborhood. Spanning 4,717 feet, the LPP includes dredging, channel improvement and reinforced slope protection designed to handle flood flows of up to 6,900 cubic feet per second. The LPP was completed in October 2000 under Section 401 of the 1986 Flood Control Act. In June 2018, a severe storm damaged the project’s channel, eroding protective revetment and reducing the channel’s structural integrity. The U.S. Army Corps of Engineers Pittsburgh District, in partnership with the city of Pittsburgh, initiated rehabilitation under the Public Law 84-99 program to restore the project to its original flood risk-management capacity. The district awarded a nearly $1 million construction contract in February 2025 to complete the rehabilitation work. The current repairs reinforce key sections of the channel and ensure the project continues protecting the community from future flooding events. The Saw Mill Run local flood-protection project is one of 84 local flood-protection projects built by the district. (U.S. Army Corps of Engineers photo by Andrew Byrne)

In a flood protection-project channel, a construction worker hands stone to another construction worker.
PHOTO DETAILS  /   DOWNLOAD HI-RES 11 of 14

U.S. Army Corps of Engineers Pittsburgh District contractors place stone in the Saw Mill Run local flood-protection project trench during channel rehabilitation in Pittsburgh, PA, Oct. 6, 2025. The stone will be grouted in the trench to tie into the existing concrete slab revetment. The Saw Mill Run local flood-protection project was built to mitigate flood risk for Pittsburgh’s West End neighborhood. Spanning 4,717 feet, the LPP includes dredging, channel improvement and reinforced slope protection designed to handle flood flows of up to 6,900 cubic feet per second. The LPP was completed in October 2000 under Section 401 of the 1986 Flood Control Act. In June 2018, a severe storm damaged the project’s channel, eroding protective revetment and reducing the channel’s structural integrity. The U.S. Army Corps of Engineers Pittsburgh District, in partnership with the city of Pittsburgh, initiated rehabilitation under the Public Law 84-99 program to restore the project to its original flood risk-management capacity. The district awarded a nearly $1 million construction contract in February 2025 to complete the rehabilitation work. The current repairs reinforce key sections of the channel and ensure the project continues protecting the community from future flooding events. The Saw Mill Run local flood-protection project is one of 84 local flood-protection projects built by the district. (U.S. Army Corps of Engineers photo by Andrew Byrne)

A wide view of a dewatered flood-protection project.
PHOTO DETAILS  /   DOWNLOAD HI-RES 12 of 14

An upstream-facing view of the Saw Mill Run Local Protection Project during channel rehabilitation in Pittsburgh, PA, Oct. 6, 2025. The U.S. Army Corps of Engineers Pittsburgh District is performing major construction on the channel to repair damages incurred during a 2018 storm. The contractor uses a water diversion system, pictured here, to dewater sections of the channel while construction progresses. The Saw Mill Run local flood-protection project was built to mitigate flood risk for Pittsburgh’s West End neighborhood. Spanning 4,717 feet, the LPP includes dredging, channel improvement and reinforced slope protection designed to handle flood flows of up to 6,900 cubic feet per second. The LPP was completed in October 2000 under Section 401 of the 1986 Flood Control Act. In June 2018, a severe storm damaged the project’s channel, eroding protective revetment and reducing the channel’s structural integrity. The U.S. Army Corps of Engineers Pittsburgh District, in partnership with the city of Pittsburgh, initiated rehabilitation under the Public Law 84-99 program to restore the project to its original flood risk-management capacity. The district awarded a nearly $1 million construction contract in February 2025 to complete the rehabilitation work. The current repairs reinforce key sections of the channel and ensure the project continues protecting the community from future flooding events. The Saw Mill Run local flood-protection project is one of 84 local flood-protection projects built by the district. (U.S. Army Corps of Engineers photo by Andrew Byrne)

In a flood protection-project channel, construction workers stand on the channel's revetment.
PHOTO DETAILS  /   DOWNLOAD HI-RES 13 of 14

U.S. Army Corps of Engineers Pittsburgh District contractors cast fabric revetment forms at the bottom of an access ramp at the Saw Mill Run local flood-protection project during channel rehabilitation in Pittsburgh, PA, Oct. 6, 2025. The trench will be backfilled with riprap and grout to protect the revetment from scour and undercutting. The Saw Mill Run local flood-protection project was built to mitigate flood risk for Pittsburgh’s West End neighborhood. Spanning 4,717 feet, the LPP includes dredging, channel improvement and reinforced slope protection designed to handle flood flows of up to 6,900 cubic feet per second. The LPP was completed in October 2000 under Section 401 of the 1986 Flood Control Act. In June 2018, a severe storm damaged the project’s channel, eroding protective revetment and reducing the channel’s structural integrity. The U.S. Army Corps of Engineers Pittsburgh District, in partnership with the city of Pittsburgh, initiated rehabilitation under the Public Law 84-99 program to restore the project to its original flood risk-management capacity. The district awarded a nearly $1 million construction contract in February 2025 to complete the rehabilitation work. The current repairs reinforce key sections of the channel and ensure the project continues protecting the community from future flooding events. The Saw Mill Run local flood-protection project is one of 84 local flood-protection projects built by the district. (U.S. Army Corps of Engineers photo by Andrew Byrne)

In a flood protection-project channel, a construction worker pours concrete.
PHOTO DETAILS  /   DOWNLOAD HI-RES 14 of 14

U.S. Army Corps of Engineers Pittsburgh District contractors pass grout through a sieve for use at the Saw Mill Run local flood-protection project during channel rehabilitation in Pittsburgh, PA, Oct. 6, 2025. The grout will be used to backfill the riprap in the trenches to protect the revetment from scour and undercutting. The Saw Mill Run local flood-protection project was built to mitigate flood risk for Pittsburgh’s West End neighborhood. Spanning 4,717 feet, the LPP includes dredging, channel improvement and reinforced slope protection designed to handle flood flows of up to 6,900 cubic feet per second. The LPP was completed in October 2000 under Section 401 of the 1986 Flood Control Act. In June 2018, a severe storm damaged the project’s channel, eroding protective revetment and reducing the channel’s structural integrity. The U.S. Army Corps of Engineers Pittsburgh District, in partnership with the city of Pittsburgh, initiated rehabilitation under the Public Law 84-99 program to restore the project to its original flood risk-management capacity. The district awarded a nearly $1 million construction contract in February 2025 to complete the rehabilitation work. The current repairs reinforce key sections of the channel and ensure the project continues protecting the community from future flooding events. The Saw Mill Run local flood-protection project is one of 84 local flood-protection projects built by the district. (U.S. Army Corps of Engineers photo by Andrew Byrne)

When torrential rains hit Pittsburgh’s West End in 2018, the Saw Mill Run surged with more force than the neighborhood had seen in years. Within eight hours, more than four inches of rain funneled down the steep watershed into a narrow urban channel.

The storm did not just test the system – it critically damaged portions of the Saw Mill Run local flood-protection project, a 4,717-foot channel built by the U.S. Army Corps of Engineers Pittsburgh District (USACE) in 2000 to defend thousands of residents and commuters just across the river from downtown Pittsburgh.

By the time the 2018 stormwaters receded, the channel had suffered several structural damages, and the storm exacerbated existing erosion, leaving areas of the local flood-protection project vulnerable to further damage.

“The high flows washed out the exposed bank material beneath the revetment, creating a void,” said Krista Kutzner, the local flood-protection project’s construction manager. “The concrete revetment collapsed under its own weight or broke off, washing out the toe of the bank. After the 2018 storm, any rain event just continuously washed away material because it was exposed and couldn’t withstand the flows.”

In the upstream work area, a massive scour hole – roughly ten feet deep – had formed below the drop structure.

“There was a huge hydraulic jump during rain events that continuously scoured out that hole,” said Kutzner. “It was even beginning to undercut the wall below Route 51. That area was slowly degrading over time, but the 2018 storm accelerated everything.”

Left unrepaired, this damage threatened the structural stability of the revetment, gravity walls, soldier pile and lagging walls, and other elements that give the channel its protective capability.

However, since the local flood-protection project’s construction was federally authorized, it can receive federal assistance under Public Law (PL) 84-99. Under PL84-99, communities can request USACE to provide rehabilitation assistance for flood risk-management projects damaged by storm events.

“Congress authorized the funding for the Corps of Engineers to build it, and in the case of local flood-protection projects, they are turned over to the sponsor to maintain after USACE completes construction,” said Al Coglio, the district’s chief of emergency management and PL84-99 program manager. “If the project is kept in good working condition, and our inspections show it’s at least minimally acceptable, and then if high water or a flood causes damage, USACE can go in and repair those damages.”

In the case of Saw Mill Run, the district evaluated multiple repair strategies, including restoring the original concrete revetment and using high-performance turf reinforcement matting. Ultimately, the district decided to revive the channel to pre-storm conditions, ensuring it can withstand future floods.

The sponsor, the city of Pittsburgh, shares the project cost with USACE at a rate of 31.5 to 68.5 percent, respectively. USACE awarded a contract for the work to Gale Construction Company in February.

The federally-funded portion of the repair totaled $637,000, with the project delivering an estimated 20-to-1 benefit-to-cost ratio – meaning every dollar spent returns 20 dollars in avoided flood damage.

However, property damage would not be the only concern if the local flood-protection project’s channel was left unfixed – regional mobility would also see direct impacts.

“The project protects the community from flooding, but additionally, Route 51 runs right past the project,” said Coglio. “Any failure of that channel would cause a traffic nightmare for anyone living south of the city.”

The Saw Mill Run local flood-protection project is one of 84 local flood-protection projects within the Pittsburgh District.

Major construction on the Saw Mill Run channel repairs is complete, with follow-on work transitioning into routine maintenance. What remains is a strengthened system designed to withstand the sudden, forceful storms that characterize Saw Mill Run’s steep watershed.

The restored channel doesn’t just represent concrete, engineering, and cost-effective federal investment – it represents peace of mind. Because of the Saw Mill Run and local flood-protection projects like it, communities are safer, more resilient, and better prepared for the next storm.

“Small projects can have big impacts, and this project is an excellent example of how federal partnerships can benefit local communities,” said Patrick Moore, a project manager with the Pittsburgh District. “By partnering with the district, the city of Pittsburgh can complete this project without increasing costs to taxpayers, and the district can continue reducing flood risk for the people of West End.”