Contractors working for the U.S. Army Corps of Engineers Pittsburgh District install a 23-foot-tall concrete shaft enclosure weighing approximately 120,000 pounds as part of the guard wall at the Monongahela River Locks and Dam 4 in Charleroi, Pennsylvania, Nov. 16, 2023.

Featured Stories

Filter Featured Stories

Featured Stories

Mechanic team keeps navigation moving on Allegheny River, replaces hydraulics system in-house

Pittsburgh District
Published Aug. 4, 2022
Updated: Aug. 4, 2022
allegheny lock dam

Vince DeCarlo (right), U.S. Army Corps of Engineers Pittsburgh District operations chief, briefs Col. Kimberly Peeples (center), commander and district engineer of the Great Lakes and Ohio River Division, during a tour to show piping work being completed at C.W. Bill Young Lock & Dam in New Kensington, Pennsylvania, April 13, 2022. Employees at the facility have been replacing more than 700 feet of hydraulic pipes that will save the district more than $150,000 in contracted costs. The hydro lines control the opening and closing of gates and valves for lock operations. (U.S. Army Corps of Engineers Pittsburgh District photo by Michel Sauret)

allegheny lock dam

Nathan Connolly, U.S. Army Corps of Engineers Pittsburgh District lock operator, walks along a control gallery at C.W. Bill Young Lock & Dam on the Allegheny River in New Kensington, Pennsylvania, April 13, 2022. Two mechanics and a lock operations leader have been working together on a project to replace more than 700 feet of hydraulic pipes that will save the district more than $150,000 in contracted costs. The hydro lines control the opening and closing of gates and valves for lock operations. (U.S. Army Corps of Engineers Pittsburgh District photo by Michel Sauret)

allegheny lock dam

Col. Kimberly Peeples (right), commander and district engineer of the Great Lakes and Ohio River Division, visits employees of the C.W. Bill Young Lock & Dam operated by the U.S. Army Corps of Engineers Pittsburgh District on the Allegheny River in New Kensington, Pennsylvania, April 13, 2022. The facility needs repairs, including replacing concrete where many areas along the lock walls are cracked or deteriorating. (U.S. Army Corps of Engineers Pittsburgh District photo by Michel Sauret)

allegheny lock dam

Robert Nuss, U.S. Army Corps of Engineers Pittsburgh District mechanic at C.W. Bill Young Lock & Dam, briefs Col. Kimberly Peeples, commander and district engineer of the Great Lakes and Ohio River Division, on work he and other employees have been doing at the lock in New Kensington, Pennsylvania, April 13, 2022. Nuss led a project to replace more than 700 feet of hydraulic pipes that will save the district more than $150,000 in contracted costs. The hydro lines control the opening and closing of gates and valves for lock operations. (U.S. Army Corps of Engineers Pittsburgh District photo by Michel Sauret)

allegheny lock dam

Col. Kimberly Peeples, commander and district engineer of the Great Lakes and Ohio River Division, visits employees of the C.W. Bill Young Lock & Dam operated by the U.S. Army Corps of Engineers Pittsburgh District on the Allegheny River in New Kensington, Pennsylvania, April 13, 2022. Two mechanics and a lock operations leader have been working together on a project to replace more than 700 feet of hydraulic pipes that will save the district more than $150,000 in contracted costs. The hydro lines control the opening and closing of gates and valves for lock operations. (U.S. Army Corps of Engineers Pittsburgh District photo by Michel Sauret)

allegheny lock dam

Col. Kimberly Peeples, commander and district engineer of the Great Lakes and Ohio River Division, visits employees of the C.W. Bill Young Lock & Dam operated by the U.S. Army Corps of Engineers Pittsburgh District on the Allegheny River in New Kensington, Pennsylvania, April 13, 2022. Two mechanics and a lock operations leader have been working together on a project to replace more than 700 feet of hydraulic pipes that will save the district more than $150,000 in contracted costs. The hydro lines control the opening and closing of gates and valves for lock operations. (U.S. Army Corps of Engineers Pittsburgh District photo by Michel Sauret)

allegheny lock dam

John Dilla, chief of the locks and dams branch for the U.S. Army Corps of Engineers Pittsburgh Districts, climbs a ladder while visiting employees of the C.W. Bill Young Lock & Dam on the Allegheny River in New Kensington, Pennsylvania, April 13, 2022. Two mechanics and a lock operations leader have been working together on a project to replace more than 700 feet of hydraulic pipes that will save the district more than $150,000 in contracted costs. The hydro lines control the opening and closing of gates and valves for lock operations. (U.S. Army Corps of Engineers Pittsburgh District photo by Michel Sauret)

allegheny lock dam

Col. Kimberly Peeples, commander and district engineer of the Great Lakes and Ohio River Division, presents a commander's coin to Wayne Stone, lock operations leader at C.W. Bill Young Lock & Dam operated by the U.S. Army Corps of Engineers Pittsburgh District on the Allegheny River in New Kensington, Pennsylvania, April 13, 2022. Stone and two mechanics have been working together on a project to replace more than 700 feet of hydraulic pipes that will save the district more than $150,000 in contracted costs. The hydro lines control the opening and closing of gates and valves for lock operations. (U.S. Army Corps of Engineers Pittsburgh District photo by Michel Sauret)

allegheny lock dam

Col. Kimberly Peeples, commander and district engineer of the Great Lakes and Ohio River Division, presents a commander's coin to Gary Dernus, mechanic at C.W. Bill Young Lock & Dam operated by the U.S. Army Corps of Engineers Pittsburgh District on the Allegheny River in New Kensington, Pennsylvania, April 13, 2022. Dernus and two other employees have been working together on a project to replace more than 700 feet of hydraulic pipes that will save the district more than $150,000 in contracted costs. The hydro lines control the opening and closing of gates and valves for lock operations. (U.S. Army Corps of Engineers Pittsburgh District photo by Michel Sauret)

allegheny lock dam
PHOTO DETAILS  /   DOWNLOAD HI-RES 10 of 17

Robert Nuss, U.S. Army Corps of Engineers Pittsburgh District mechanic at C.W. Bill Young Lock & Dam, briefs Col. Kimberly Peeples, commander and district engineer of the Great Lakes and Ohio River Division, on work he and other employees have been doing at the lock in New Kensington, Pennsylvania, April 13, 2022. Nuss led a project to replace more than 700 feet of hydraulic pipes that will save the district more than $150,000 in contracted costs. The hydro lines control the opening and closing of gates and valves for lock operations. (U.S. Army Corps of Engineers Pittsburgh District photo by Michel Sauret)

allegheny lock dam
PHOTO DETAILS  /   DOWNLOAD HI-RES 11 of 17

Col. Kimberly Peeples, commander and district engineer of the Great Lakes and Ohio River Division, presents a commander's coin to Robert Nuss, mechanic at C.W. Bill Young Lock & Dam operated by the U.S. Army Corps of Engineers Pittsburgh District on the Allegheny River in New Kensington, Pennsylvania, April 13, 2022. Nuss and two other employees have been working together on a project to replace more than 700 feet of hydraulic pipes that will save the district more than $150,000 in contracted costs. The hydro lines control the opening and closing of gates and valves for lock operations. (U.S. Army Corps of Engineers Pittsburgh District photo by Michel Sauret)

allegheny lock dam
PHOTO DETAILS  /   DOWNLOAD HI-RES 12 of 17

Robert Nuss, U.S. Army Corps of Engineers Pittsburgh District mechanic at C.W. Bill Young Lock & Dam, briefs Col. Kimberly Peeples, commander and district engineer of the Great Lakes and Ohio River Division, on work he and other employees have been doing at the lock in New Kensington, Pennsylvania, April 13, 2022. Nuss led a project to replace more than 700 feet of hydraulic pipes that will save the district more than $150,000 in contracted costs. The hydro lines control the opening and closing of gates and valves for lock operations. (U.S. Army Corps of Engineers Pittsburgh District photo by Michel Sauret)

allegheny lock dam
PHOTO DETAILS  /   DOWNLOAD HI-RES 13 of 17

Col. Kimberly Peeples (left), commander and district engineer of the Great Lakes and Ohio River Division, visits employees of the C.W. Bill Young Lock & Dam operated by the U.S. Army Corps of Engineers Pittsburgh District on the Allegheny River in New Kensington, Pennsylvania, April 13, 2022. Two mechanics and a lock operations leader have been working together on a project to replace more than 700 feet of hydraulic pipes that will save the district more than $150,000 in contracted costs. The hydro lines control the opening and closing of gates and valves for lock operations. (U.S. Army Corps of Engineers Pittsburgh District photo by Michel Sauret)

allegheny lock dam
PHOTO DETAILS  /   DOWNLOAD HI-RES 14 of 17

Robert Nuss, U.S. Army Corps of Engineers Pittsburgh District mechanic at C.W. Bill Young Lock & Dam, briefs Col. Kimberly Peeples, commander and district engineer of the Great Lakes and Ohio River Division, on work he and other employees have been doing at the lock in New Kensington, Pennsylvania, April 13, 2022. Nuss led a project to replace more than 700 feet of hydraulic pipes that will save the district more than $150,000 in contracted costs. The hydro lines control the opening and closing of gates and valves for lock operations. (U.S. Army Corps of Engineers Pittsburgh District photo by Michel Sauret)

Mechanics replace old, rusted pipes for hydraulics system
PHOTO DETAILS  /   DOWNLOAD HI-RES 15 of 17

Robert Nuss and Gary Dernus, lock mechanics with the U.S. Army Corps of Engineers Pittsburgh District, give a tour and explain the work they performed to replace the hydraulics system at the C.W. Bill Young Lock & Dam on the Allegheny River. The project took a better part of a year and more than 800 work hours to complete, performed mainly by Robert Nuss and Gary Dernus. The lock and dam first went into operation in late 1934, with some piping and fittings dating back to the lock’s original construction. The mechanics’ team replaced hundreds of feet of rusted and deteriorating piping with new or refurbished material that the Corps expects to last several decades. (U.S. Army Corps of Engineers Pittsburgh District photo)

Mechanics replace old, rusted pipes for hydraulics system
PHOTO DETAILS  /   DOWNLOAD HI-RES 16 of 17

A mechanic with the U.S. Army Corps of Engineers Pittsburgh District holds chunks of deteriorating pipes from the hydraulics system at the C.W. Bill Young Lock & Dam on the Allegheny River. The project took a better part of a year and more than 800 work hours to complete, performed mainly by Robert Nuss and Gary Dernus. The lock and dam first went into operation in late 1934, with some piping and fittings dating back to the lock’s original construction. The mechanics’ team replaced hundreds of feet of rusted and deteriorating piping with new or refurbished material that the Corps expects to last several decades. (U.S. Army Corps of Engineers Pittsburgh District photo)

Mechanics replace old, rusted pipes for hydraulics system
PHOTO DETAILS  /   DOWNLOAD HI-RES 17 of 17

This "before" photo shows the deteriorating hydraulics system replaced by the U.S. Army Corps of Engineers Pittsburgh District mechanics at the C.W. Bill Young Lock & Dam on the Allegheny River. The project took a better part of a year and more than 800 work hours to complete, performed mostly by Robert Nuss and Gary Dernus, lock mechanics. The lock and dam first went into operation in late 1934. Some of the piping and fittings dated back to the lock’s original construction. The mechanics team replaced hundreds of feet of rusted and deteriorating piping with new or refurbished material expected to last several decades. (U.S. Army Corps of Engineers Pittsburgh District photo)

allegheny lock dam
Peeples Visit AR3
Nathan Connolly, U.S. Army Corps of Engineers Pittsburgh District lock operator, walks along a control gallery at C.W. Bill Young Lock & Dam on the Allegheny River in New Kensington, Pennsylvania, April 13, 2022. Two mechanics and a lock operations leader have been working together on a project to replace more than 700 feet of hydraulic pipes that will save the district more than $150,000 in contracted costs. The hydro lines control the opening and closing of gates and valves for lock operations. (U.S. Army Corps of Engineers Pittsburgh District photo by Michel Sauret)
Photo By: Michel Sauret
VIRIN: 220413-A-TI382-0538

PITTSBURGH – A small team of mechanics and lock operators replaced 740 feet of hydraulic steel piping, avoiding a six-figure cost in taxpayer dollars to keep navigation moving on the Allegheny River.

The project took the better part of a year and more than 800 work hours to complete, performed mostly by two mechanics.

“Failure was not an option,” said Robert Nuss, one of the two equipment mechanics in charge of the project at C.W. Bill Young Lock & Dam.

Despite its name, the lock is anything but young. The concrete walls are crumbling, and the hydraulic system faced potential rupture and fluid leak if Nuss and his team had not taken quick action. None of them had ever handled a job this big, so they approached the work with an emphasis on planning.

allegheny lock dam
Peeples Visit AR3
Col. Kimberly Peeples (right), commander and district engineer of the Great Lakes and Ohio River Division, visits employees of the C.W. Bill Young Lock & Dam operated by the U.S. Army Corps of Engineers Pittsburgh District on the Allegheny River in New Kensington, Pennsylvania, April 13, 2022. The facility needs repairs, including replacing concrete where many areas along the lock walls are cracked or deteriorating. (U.S. Army Corps of Engineers Pittsburgh District photo by Michel Sauret)
Photo By: Michel Sauret
VIRIN: 220413-A-TI382-0779

“If we didn’t take planning seriously, it could be like opening up Pandora’s Box,” Nuss said.

If the installation went awry, it would mean shutting down navigation at the facility, also known as Lock and Dam 3, located 17 miles upstream from the point of Pittsburgh. Unlike many larger locking facilities, Lock 3 has only one chamber. As a result, the team didn’t have the luxury of keeping traffic moving through a second passage while they shut down for maintenance.

The hydraulic system opens and closes the miter gates. Removing even a single piece of the pipe means cutting off the flow of hydraulic fluid, rendering the system useless.

allegheny lock dam
Peeples Visit AR3
Robert Nuss, U.S. Army Corps of Engineers Pittsburgh District mechanic at C.W. Bill Young Lock & Dam, briefs Col. Kimberly Peeples, commander and district engineer of the Great Lakes and Ohio River Division, on work he and other employees have been doing at the lock in New Kensington, Pennsylvania, April 13, 2022. Nuss led a project to replace more than 700 feet of hydraulic pipes that will save the district more than $150,000 in contracted costs. The hydro lines control the opening and closing of gates and valves for lock operations. (U.S. Army Corps of Engineers Pittsburgh District photo by Michel Sauret)
Photo By: Michel Sauret
VIRIN: 220413-A-TI382-0442

“We pride ourselves in the fact we never shut down the facility to commercial traffic,” Dernus said.

To avoid shutdown, the mechanics constructed a bypass “soft” line to keep hundreds of gallons of hydraulic fluid in operation.

Usually, a job of this scale would have warranted an outside contract or a request to the maintenance fleet. Not only would that have been more costly, but it would have taken months to fund, market and approve a bid before work began. Nuss did not think the hydraulic system would last the wait.

allegheny lock dam
Peeples Visit AR3
Robert Nuss, U.S. Army Corps of Engineers Pittsburgh District mechanic at C.W. Bill Young Lock & Dam, briefs Col. Kimberly Peeples, commander and district engineer of the Great Lakes and Ohio River Division, on work he and other employees have been doing at the lock in New Kensington, Pennsylvania, April 13, 2022. Nuss led a project to replace more than 700 feet of hydraulic pipes that will save the district more than $150,000 in contracted costs. The hydro lines control the opening and closing of gates and valves for lock operations. (U.S. Army Corps of Engineers Pittsburgh District photo by Michel Sauret)
Photo By: Michel Sauret
VIRIN: 220413-A-TI382-0024

“My concern was the system would inevitably fail before a contractor would be able to come in and repair it,” Nuss said.

Before tackling the project, Nuss and fellow mechanic, Gary Dernus, thought only a few pipes would need replacing while they rehabbed the rest. However, when they inspected the system, they discovered most pipes were too corroded to scrape the rust off and repaint them.

“We saw different generations of piping, some all the way back to the 1930s,” Nuss said.

The lock and dam first went into operation in late 1934, with some piping and fittings dating back to the lock’s original construction. The fittings were made of heavy cast iron, which were still intact and usable. Other parts and pipes were more recent, but it was impossible to tell from which decade.

Removing and replacing the piping was like a journey back in history, Nuss said. But although it was interesting to go back in time, the labor itself was intensive.

Mechanics replace old, rusted pipes for hydraulics system
Replacing hydraulics system in-house
This "before" photo shows the deteriorating hydraulics system replaced by the U.S. Army Corps of Engineers Pittsburgh District mechanics at the C.W. Bill Young Lock & Dam on the Allegheny River. The project took a better part of a year and more than 800 work hours to complete, performed mostly by Robert Nuss and Gary Dernus, lock mechanics. The lock and dam first went into operation in late 1934. Some of the piping and fittings dated back to the lock’s original construction. The mechanics team replaced hundreds of feet of rusted and deteriorating piping with new or refurbished material expected to last several decades. (U.S. Army Corps of Engineers Pittsburgh District photo)
Photo By: Michel Sauret
VIRIN: 220801-A-XY123-0004
 
Mechanics replace old, rusted pipes for hydraulics system
Replacing hydraulics system in-house
A mechanic with the U.S. Army Corps of Engineers Pittsburgh District holds chunks of deteriorating pipes from the hydraulics system at the C.W. Bill Young Lock & Dam on the Allegheny River. The project took a better part of a year and more than 800 work hours to complete, performed mainly by Robert Nuss and Gary Dernus. The lock and dam first went into operation in late 1934, with some piping and fittings dating back to the lock’s original construction. The mechanics’ team replaced hundreds of feet of rusted and deteriorating piping with new or refurbished material that the Corps expects to last several decades. (U.S. Army Corps of Engineers Pittsburgh District photo)
Photo By: Michel Sauret
VIRIN: 220801-A-XY123-0002

It required Nuss, Dernus, and everyone who helped to thread heavy 20-foot pipes through a human-sized hole into a narrow concrete tunnel called a gallery. Each pipe weighed more than 200 pounds. They moved the same pipes up and down from the gallery multiple times, first to dry-fit them below, then to prep and weld parts of the pipes above ground, apply the protective coating, then lowered them again for installation.

“It was definitely not an easy task. Honestly, at first, it was pretty daunting,” Dernus said.

Completing the project was like assembling a massive puzzle, except without any diagrams or instructions to follow. So instead, Nuss and Dernus wrote down their own plans, often modifying the design to overcome obstacles along the way. Nuss said he is thankful for the guidance and advice he received from his peers.

“After this experience, I feel a lot more confident now going to any facility and being able to troubleshoot and rebuild their hydraulic system if I had to,” Dernus said.

allegheny lock dam
Peeples Visit AR3
Robert Nuss, U.S. Army Corps of Engineers Pittsburgh District mechanic at C.W. Bill Young Lock & Dam, briefs Col. Kimberly Peeples, commander and district engineer of the Great Lakes and Ohio River Division, on work he and other employees have been doing at the lock in New Kensington, Pennsylvania, April 13, 2022. Nuss led a project to replace more than 700 feet of hydraulic pipes that will save the district more than $150,000 in contracted costs. The hydro lines control the opening and closing of gates and valves for lock operations. (U.S. Army Corps of Engineers Pittsburgh District photo by Michel Sauret)
Photo By: Michel Sauret
VIRIN: 220413-A-TI382-0833

Working inside the gallery didn’t make the installation any easier. The tunnel is like a concrete cavern. The space is narrow, barely wide enough for a person to walk through without accidentally smacking their shoulders into something. Unfortunately, it is also hundreds of feet long, and there was only one entry point for each pipe.

“Yeah, it wasn’t pleasant. The first day the pipe was delivered, we joked about how awful it was going to be. And then we never spoke about it again because it wouldn’t help,” Nuss said.

Saving money on the project was critical due to the lack of funding on the Allegheny River for navigation. Locking facilities receive much of their funding from the shipping industries that use them. However, the Allegheny River is mostly used by recreation boats, which don’t pay any fees to use locks. Funding on the Allegheny is limited to a small portion of tax revenue, unlike the Monongahela and Ohio rivers, which receive more funding from industry traffic.

To save additional costs, Nuss coordinated with other lock facilities in the region that had hydraulic pipes and materials not being used. Those pipes were used but still in good enough shape to refurbish.

Walking down into the gallery now is a different experience from a year ago. Before the project, the tunnel had hundreds of feet of rusted and deteriorating piping. Now the pipes are either new or refurbished, freshly painted, bright white, and expected to last several decades.

allegheny lock dam
Peeples Visit AR3
Robert Nuss, U.S. Army Corps of Engineers Pittsburgh District mechanic at C.W. Bill Young Lock & Dam, briefs Col. Kimberly Peeples, commander and district engineer of the Great Lakes and Ohio River Division, on work he and other employees have been doing at the lock in New Kensington, Pennsylvania, April 13, 2022. Nuss led a project to replace more than 700 feet of hydraulic pipes that will save the district more than $150,000 in contracted costs. The hydro lines control the opening and closing of gates and valves for lock operations. (U.S. Army Corps of Engineers Pittsburgh District photo by Michel Sauret)
Photo By: Michel Sauret
VIRIN: 220413-A-TI382-0195

“I have a tremendous amount of pride and a sense of accomplishment in finishing the work,” said Gary Dernus. “I really enjoyed the experience I got out of it because hydraulics is the heart and soul of these facilities. You’re not going to get that on-the-job training experience anywhere else.”

allegheny lock dam
Peeples Visit AR3
Col. Kimberly Peeples, commander and district engineer of the Great Lakes and Ohio River Division, presents a commander's coin to Robert Nuss, mechanic at C.W. Bill Young Lock & Dam operated by the U.S. Army Corps of Engineers Pittsburgh District on the Allegheny River in New Kensington, Pennsylvania, April 13, 2022. Nuss and two other employees have been working together on a project to replace more than 700 feet of hydraulic pipes that will save the district more than $150,000 in contracted costs. The hydro lines control the opening and closing of gates and valves for lock operations. (U.S. Army Corps of Engineers Pittsburgh District photo by Michel Sauret)
Photo By: Michel Sauret
VIRIN: 220413-A-TI382-0433


Chick Lock

Through deeds, not words, we are BUILDING STRONG®