The Louisville District End of Year Award Ceremony

Media Releases

Filter Media Releases

Contact a Public Affairs Office

Buffalo District
1-800-833-6390 (option 3)
Chicago District
312-846-5330
Detroit District
313-226-4680
Huntington District
304-399-5353
Louisville District
(502) 315-6766
Nashville District
(615) 736-7161
Pittsburgh District
412-395-7502

News Releases

Results:
Tag: New Lock at the Soo
Clear
  • New Lock at the Soo to host public meeting for 2024-2025 blasting activities

    U.S. Army Corps of Engineers, Detroit District and New Lock at the Soo contractor Kokosing Alberici Traylor, LLC (KAT) will host an in-person and virtual public meeting at 6 p.m., November 21, 2024, to inform the public of test blasting activities needed for project construction. The Corps of Engineers contracted KAT to complete Phase 3 construction of the New Lock at the Soo project. This work includes the excavation of bedrock scheduled for this year and 2025. “The project team will perform test blasts to fracture the existing bedrock to be excavated and removed,” Rachel Miller, New Lock at the Soo Contracting Officer’s Representative said. “All blasting will be completed within the Corps of Engineers Soo Locks facility in the existing decommissioned Sabin Lock area.”
  • New Lock at the Soo Phase 2 complete

    U.S. Army Corps of Engineers, Detroit District’s New Lock at the Soo project in Sault Ste. Marie, Michigan, substantially completed Phase 2 (Upstream Approach Walls) contract on September 17. “Phase 2 work focused on rehabilitating the upstream approach walls to guide vessels into the New Lock and will allow the vessels to moor on the wall,” New Lock at the Soo Project Engineer Ryan Berkompas said. “The old approach walls in the northern channel were the same age as the Sabin and Davis Locks, over 100 years old.” The Corps of Engineers awarded the $117 million contract in September 2020 to Kokosing-Alberici, of Westerville, Ohio.
  • Chamber Lock Operational Option 3 awarded for New Lock at the Soo

    U.S. Army Corps of Engineers, Detroit District’s New Lock at the Soo project in Sault Ste. Marie, Michigan, awards $222.7 million contract Option 3 (Chamber Lock Operational) to Kokosing Alberici Traylor, LLC (KAT) of Westerville, Ohio. The Option 3 award will allow for construction to proceed as required to have a fully functional lock. “Option 3 includes construction of the lock floor, installation of the mechanical and electrical systems, completion of the filling and emptying system, placing soil in between the New Lock and old Davis Lock, and commissioning of the lock chamber,” said Inland Navigation Design Center, New Lock at the Soo Technical Lead Darin White.  With the on-time award of Option 3, the project continues to be on track for completion in 2030.
  • Soo Locks Hydro Plant Tailrace Closing to Vessel Traffic

    Ongoing New Lock at the Soo construction activities are occurring in the St. Marys Falls Canal hydroelectric power plant tailrace. Beginning April 1, 2024, this area will close to all vessel traffic except at the specific direction of the Chief Lockmaster. Scheduled New Lock at the Soo construction activities are anticipated to allow exceptions to this closure beginning most Saturdays at 6 p.m. through the following Monday at 6 a.m., and infrequently on other days.
  • Chamber Wall Monoliths Option 1B Awarded for New Lock at the Soo

    U.S. Army Corps of Engineers, Detroit District’s New Lock at the Soo project in Sault Ste. Marie, Michigan, awards $213.8 million contract Option 1B (Chamber Wall Monoliths) to Kokosing Alberici Traylor, LLC (KAT) of Westerville, Ohio. Contract Option 1B includes construction of the lock wall monoliths, very large concrete wall portions that make up the sides of the chamber along the north and south side of the lock chamber. The chamber monoliths span between the Upstream wide wall monoliths and Downstream wide wall monoliths.
  • New Lock at the Soo to host public meeting for upcoming blasting activities

    SAULT STE. MARIE, Mich. – U.S. Army Corps of Engineers, Detroit District and New Lock at the Soo contractor Kokosing Alberici Traylor, LLC (KAT) will host an in-person and virtual public meeting 6 p.m., July 10, 2023, to inform the public of blasting activities needed for project construction. The Corps of Engineers contracted KAT to complete Phase 3 construction of the New Lock at the Soo. This work includes excavation and installation of a shaft and tunnel scheduled for this year. “The project team will blast as the means to fracture the existing bedrock to be excavated and removed,” Rachel Miller, New Lock Contracting Officer’s Representative said. “All blasting will be completed within the Corps of Engineers Soo Locks facility on the island north of the existing decommissioned Sabin Lock.”
  • New Lock at the Soo major construction continues

    SAULT STE. MARIE, Mich. – The U.S. Army Corps of Engineers New Lock at the Soo project remains on schedule as major construction continues with phases 2 and 3 this season. Joint ventures Kokosing-Alberici (Upstream Approach Walls, Phase 2), and Kokosing, Alberici, Traylor (New Lock, Phase 3) have a busy construction season ahead of them. “Since resuming major construction this season, the Phase 2 contractor has placed 13 concrete caps, bringing the total caps placed to 68 and preparation for placement of new steel sheets, steel posts and concrete panel wall are in progress,” New Lock Senior Project Manager Mollie Mahoney said. “The Phase 3 contractor plans to focus on demolition of aging structures, extensive electrical work, bridge construction, and coffer dam construction to allow for dewatering.”
  • New Lock at the Soo major construction continues

    SAULT STE. MARIE, Mich. – The U.S. Army Corps of Engineers New Lock at the Soo project remains on schedule as major construction continues with phases 2 and 3 this season. Joint ventures Kokosing-Alberici (Upstream Approach Walls, Phase 2), and Kokosing, Alberici, Traylor (New Lock, Phase 3) have a busy construction season ahead of them. “Since resuming major construction this season, the Phase 2 contractor has placed 13 concrete caps, bringing the total caps placed to 68 and preparation for placement of new steel sheets, steel posts and concrete panel wall are in progress,” New Lock Senior Project Manager Mollie Mahoney said. “The Phase 3 contractor plans to focus on demolition of aging structures, extensive electrical work, bridge construction, and coffer dam construction to allow for dewatering.”
  • New Lock at the Soo to host follow-up public meeting for Hydro Plant tail race closing

    SAULT STE. MARIE, Mich. – U.S. Army Corps of Engineers, Detroit District will host an in-person public meeting 6 p.m., March 15, 2023, to follow-up on the closure of the Soo Locks Hydro Plant tail race during New Lock at the Soo construction. The Corps of Engineers has a preliminary closure plan for the upcoming season and would like to present the strategy for the 2023 construction season to ensure effective communication of closures with anglers and interested parties. The Corps of Engineers previously hosted a public meeting to discuss the Hydro Plant tail race closures April 20, 2022.
  • New Lock at the Soo reauthorized in WRDA 2022 at $3.219 billion

    U.S. Army Corps of Engineers, Detroit District New Lock at the Soo Project in Sault Ste. Marie, Michigan is reauthorized in the Water Resources Development Act (WRDA) 2022 on Dec 23, 2022. The project reauthorization amount is $3.219 billion. An authorization sets how much money agencies and programs can receive, and how they should spend the money. This authorization makes it possible for the project to maintain efficient funding eligibility. Due to recent cost increases, the project cost was estimated to exceed the previously authorized spending limit. “With continued funding, the remaining construction work, valued at $794.5 million could be awarded over the next three years allowing the project to stay on schedule and be completed in 2030.” Deputy District Engineer Kevin McDaniels said.
Chick Lock

Through deeds, not words, we are BUILDING STRONG®