The proposed residential project would continue the original master plan development with the construction of five hundred ninety-five (595) single-family homes, internal roadways, city sewer and water service infrastructure, stormwater management, and open space areas.
Aquatic resource impacts would primarily result from the proposed roadway connecting the neighborhoods. The proposed project would result in filling 1.85-acres of jurisdictional wetland and 0.20-acres of tributary. Additionally, 0.40-acres of temporary impact would result from the installation of a water main.